Restaurant Construction Budget12/5/2025
5
Color
WBS Number
Task name / TitleAssigned to
Planned start date
Planned end date
Deadline
Progress (%)
Duration (hours)
Estimated hours
Time log (minutes)
StatusPriority
Task description
Cost
Actual cost
6
1GENERAL REQUIREMENTS3/6/202610/17/2026012960000
7
1.1Plans & Specifications3/6/20265/7/2026036000OpenMedium00
8
1.2Plan Review4/21/20266/20/2026036000OpenMedium00
9
1.3
Permits: Zoning, Building, Environemental
5/19/20267/18/2026036000OpenMedium00
10
1.4Survey5/19/20267/18/2026036000OpenMedium00
11
1.5Impact Fee5/19/20267/18/2026036000OpenMedium00
12
1.6Adminstrative Costs6/19/20268/20/2026036000OpenMedium00
13
1.7Financing Costs7/17/20269/17/2026036000OpenMedium00
14
1.8Legal Fees7/17/20269/17/2026036000OpenMedium00
15
1.9Engineering Fees7/17/20269/17/2026036000OpenMedium00
16
1.10Other8/18/202610/17/2026036000OpenMedium00
17
2SITE PREP10/20/20261/7/202704640000
18
2.1Demolition (Remodel)11/6/20261/7/2027036000OpenMedium00
19
2.2Jacking & Shoring (Remodel)11/6/20261/7/2027036000OpenMedium00
20
2.3
Dust control, Surface Protection
11/6/20261/7/2027036000OpenMedium00
21
2.4Job-Site Access11/6/20261/7/2027036000OpenMedium00
22
2.5Job-Site Security11/6/20261/7/2027036000OpenMedium00
23
2.6Dumpster & Removal11/6/20261/7/2027036000OpenMedium00
24
2.7Clear Lot11/6/20261/7/2027036000OpenMedium00
25
2.8Storage On Site11/6/20261/7/2027036000OpenMedium00
26
2.9Portable Toilet11/6/20261/7/2027036000OpenMedium00
27
2.10Temporary Power11/6/20261/7/2027036000OpenMedium00
28
2.11Temporary Heat11/6/20261/7/2027036000OpenMedium00
29
2.12Scaffolding Rental11/6/20261/7/2027036000OpenMedium00
30
2.13Tool/Equipment Rental11/6/20261/7/2027036000OpenMedium00
31
2.14Other10/20/202612/19/2026036000OpenMedium00
32
3ON-SITE WATER/SEWER12/17/20262/17/202703600000
33
3.1Soil & Perc Tests12/17/20262/17/2027036000OpenMedium00
34
3.2Septic System Design12/17/20262/17/2027036000OpenMedium00
35
3.3
Septic Permits, Inspections, Fees
12/17/20262/17/2027036000OpenMedium00
36
3.4
Septic System Installation, Tie in to House
12/17/20262/17/2027036000OpenMedium00
37
3.5Dewatering (High Water Table)12/17/20262/17/2027036000OpenMedium00
38
3.6
Well, Pump, Trenching, Plumbing to House
12/17/20262/17/2027036000OpenMedium00
39
3.7Well Permits & Fees12/17/20262/17/2027036000OpenMedium00
40
3.8Other12/17/20262/17/2027036000OpenMedium00
41
4UTILITIES1/19/20273/20/202703600000
42
4.1
Town Water: Tap Fees & Hookup
1/19/20273/20/2027036000OpenMedium00
43
4.2
Town Sewer: Tap Fees & Hookup
1/19/20273/20/2027036000OpenMedium00
44
4.3
Electrical: Permit, Connection Fee, Installation
1/19/20273/20/2027036000OpenMedium00
45
4.4
Gas: Permit, Connection Fee, Installation
1/19/20273/20/2027036000OpenMedium00
46
4.5LPN: Tank installation, Hookup1/19/20273/20/2027036000OpenMedium00
47
4.6Oil Tank Installation1/19/20273/20/2027036000OpenMedium00
48
4.7Telecom Hookup1/19/20273/20/2027036000OpenMedium00
49
4.8Other1/19/20273/20/2027036000OpenMedium00
50
5EXCAVATION & EARTHWORK2/16/20275/20/202705440000
51
5.1Cut & Fill2/16/20274/17/2027036000OpenMedium00
52
5.2Blasting2/16/20274/17/2027036000OpenMedium00
53
5.3Removal of Stone/Dirt2/16/20274/17/2027036000OpenMedium00
54
5.4Rough Grading2/16/20274/17/2027036000OpenMedium00
55
5.5Trenching For Utility Hookups2/16/20274/17/2027036000OpenMedium00
56
5.6Foundation Excavation2/16/20274/17/2027036000OpenMedium00
57
5.7Foundation Footing Drains2/16/20274/17/2027036000OpenMedium00
58
5.8Curtain Drains2/16/20274/17/2027036000OpenMedium00
59
5.9Culverts2/16/20274/17/2027036000OpenMedium00
60
5.10Swales2/16/20274/17/2027036000OpenMedium00
61
5.11Retaining Walls2/16/20274/17/2027036000OpenMedium00
62
5.12Ponds2/16/20274/17/2027036000OpenMedium00
63
5.13Other Site Drainage3/19/20275/20/2027036000OpenMedium00
64
5.14Backfill3/19/20275/20/2027036000OpenMedium00
65
5.15Compaction3/19/20275/20/2027036000OpenMedium00
66
5.16Top Soil3/19/20275/20/2027036000OpenMedium00
67
5.17Finish Grading3/19/20275/20/2027036000OpenMedium00
68
5.18Seeding/Sod3/19/20275/20/2027036000OpenMedium00
69
5.19Other3/19/20275/20/2027036000OpenMedium00
70
6FOUNDATION5/19/20277/20/202703600000
71
6.1Footings/Pads5/19/20277/20/2027036000OpenMedium00
72
6.2
Foundation walls/stem walls/grade beams
5/19/20277/20/2027036000OpenMedium00
73
6.3Piers5/19/20277/20/2027036000OpenMedium00
74
6.4
Slabs - Foundation, Basement, Garage
5/19/20277/20/2027036000OpenMedium00
75
6.5Steel Reinforcing5/19/20277/20/2027036000OpenMedium00
76
6.6Anchor Bolts, Hold Downs5/19/20277/20/2027036000OpenMedium00
77
6.7Buikheads5/19/20277/20/2027036000OpenMedium00
78
6.8Sub-Slab Vapor Barrier5/19/20277/20/2027036000OpenMedium00
79
6.9Sump Pump5/19/20277/20/2027036000OpenMedium00
80
6.10Crawlspace Vapor Barrier5/19/20277/20/2027036000OpenMedium00
81
6.11Crawlspace Vents5/19/20277/20/2027036000OpenMedium00
82
6.12Foundation Windows5/19/20277/20/2027036000OpenMedium00
83
6.13Damproofing, Water-proofing5/19/20277/20/2027036000OpenMedium00
84
6.14Foundation Drain Board5/19/20277/20/2027036000OpenMedium00
85
6.15Slab insulation: Edge/Blow5/19/20277/20/2027036000OpenMedium00
86
6.16Exterior Foundation Insulation5/19/20277/20/2027036000OpenMedium00
87
6.17
Exterior Insulation Coating/ Protection
5/19/20277/20/2027036000OpenMedium00
88
6.18Other5/19/20277/20/2027036000OpenMedium00
89
7OTHER MASONRY/PAVING6/22/20278/21/202703600000
90
7.1Patios6/22/20278/21/2027036000OpenMedium00
91
7.2Exterior Stairs6/22/20278/21/2027036000OpenMedium00
92
7.3Masonry Chimneys6/22/20278/21/2027036000OpenMedium00
93
7.4Fireplaces/Hearths6/22/20278/21/2027036000OpenMedium00
94
7.5Driveway6/22/20278/21/2027036000OpenMedium00
95
7.6Walkways6/22/20278/21/2027036000OpenMedium00
96
7.7Other6/22/20278/21/2027036000OpenMedium00
97
8ROUGH FRAMING7/20/20279/18/202703600000
98
8.1Sill & Seal7/20/20279/18/2027036000OpenMedium00
99
8.2
Steel/Wood Carrying Beam, Lolly Columns
7/20/20279/18/2027036000OpenMedium00
100
8.3Floor Framing7/20/20279/18/2027036000OpenMedium00