ABCDEFGHIJKLMNOPQRSTUVWXYZAAABACADAEAFAGAHAIAJ
1
2
DETAILED BREAKDOWN OF ITEMS
3
Project NameABC
4
Project AddressXYZ
5
Scope:SITEWORK
6
S#Dwg.CSI NODESCRIPTIONQTY.WastageQty w/ WasteUNITUNIT LABOR HOURTOTAL LABOR HOURLABOR WAGE/ HOURUNIT LABOR COSTTOTAL LABOR COSTUNIT MATERIAL COSTTOTAL MATERIAL COSTUNIT PRICE (Labor & Material)TRADE TOTAL
7
000001DIVISION 01-GENERAL REQUIREMENTS
8
1Permits10%1LS0.0000.0 $ - $ - $ - $ - $ - $ - $ 117,000.00
9
2Supervision and Coordination10%1LS0.0000.0 $ - $ - $ - $ - $ - $ -
10
3Submittals and Shop drawings10%1LS0.0000.0 $ - $ - $ - $ - $ - $ -
11
4Final Cleaning10%1LS0.0000.0 $ - $ - $ - $ - $ - $ -
12
5Mobilization Costs10%1LS0.0000.0 $ - $ - $ - $ - $ - $ -
13
6Temporary Control & Facilities10%1LS0.0000.0 $ - $ - $ - $ - $ - $ -
14
7Scaffolding10%1LS0.0000.0 $ - $ - $ - $ - $ - $ -
15
SUBTOTAL $ 117,000
16
17
000002DIVISION 02- EXISTING CONDITIONS
18
SITE DEMOLITION
19
8C2.0Existing Structure To Be Removed9550%955SF0.02826.7 $ 45.00 $ 1.3 $ 1,203.3 $ - $ - $ 1.3 $ 1,203
20
9Existing Fence & Walls & Gate To Be Removed3550%355LF0.12243.3 $ 45.00 $ 5.5 $ 1,949.0 $ - $ - $ 5.5 $ 1,949
21
10Existing Side Walk To Be Removed6750%675SF0.02416.2 $ 45.00 $ 1.1 $ 729.0 $ - $ - $ 1.1 $ 729
22
11Existing Wire Fence To Be Removed6360%636LF0.10063.6 $ 45.00 $ 4.5 $ 2,862.0 $ - $ - $ 4.5 $ 2,862
23
12Existing Asphalt Pavement To Be Removed72050%7205SF0.028201.7 $ 45.00 $ 1.3 $ 9,078.3 $ - $ - $ 1.3 $ 9,078
24
13Sawcut For Pavement Removal490%49LF0.0452.2 $ 45.00 $ 2.0 $ 99.2 $ - $ - $ 2.0 $ 99
25
26
Landscaping Demolition $ -
27
14Existing Oak Trees To Be Removed880%88EA2.850250.8 $ 45.00 $ 128.3 $ 11,286.0 $ - $ - $ 128.3 $ 11,286
28
15Existing Oak Trees To Be Removed410%41EA2.850116.9 $ 45.00 $ 128.3 $ 5,258.3 $ - $ - $ 128.3 $ 5,258
29
16Existing Oak Trees To Be Removed530%53EA2.850151.1 $ 45.00 $ 128.3 $ 6,797.3 $ - $ - $ 128.3 $ 6,797
30
17Existing Oak Trees To Be Removed500%50EA2.850142.5 $ 45.00 $ 128.3 $ 6,412.5 $ - $ - $ 128.3 $ 6,413
31
18Existing Oak Trees To Be Removed490%49EA2.850139.7 $ 45.00 $ 128.3 $ 6,284.3 $ - $ - $ 128.3 $ 6,284
32
19Existing Oak Trees To Be Removed610%61EA2.850173.9 $ 45.00 $ 128.3 $ 7,823.3 $ - $ - $ 128.3 $ 7,823
33
20Existing Oak Trees To Be Removed14910%1491EA2.8504249.4 $ 45.00 $ 128.3 $ 191,220.8 $ - $ - $ 128.3 $ 191,221
34
21Existing Pecan Trees To Be Removed500%50EA2.850142.5 $ 45.00 $ 128.3 $ 6,412.5 $ - $ - $ 128.3 $ 6,413
35
36
22Hauling Of demolation Materials10%1LS0.0000.0 $ 45.00 $ - $ - $ 5,000.0 $ 5,000.0 $ 5,000.0 $ 5,000
37
SUBTOTAL $ 262,416
38
39
000031DIVISION 31- EARTHWORK
40
GRADING
41
23C2.0-C9Total Cut16860%1686CY0.220370.9 $ 45.00 $ 9.9 $ 16,691.2 $ 5.0 $ 8,429.9 $ 14.9 $ 25,121
42
24Total Fill67190%6719CY0.2001343.7 $ 45.00 $ 9.0 $ 60,466.6 $ 5.0 $ 33,592.6 $ 14.0 $ 94,059
43
25Soil To Be Import42620%4262CY0.4401875.1 $ 45.00 $ 19.8 $ 84,378.3 $ 10.0 $ 42,615.3 $ 29.8 $ 126,994
44
45
SUBTOTAL $ 246,174
46
47
000032DIVISION 32- EXTERIOR IMPROVEMENTS
48
EXTERIOR IMPROVEMENTS
49
C2.0-F1.1Wood Fence
50
26"G" Wood Fence (8' H )465%48LF0.1929.3 $ 45.00 $ 8.6 $ 417.3 $ 21.6 $ 1,043.3 $ 30.2 $ 1,461
51
52
(Light Duty) - Asphalt Pavement
53
27"A1" 1.5" Thick Type "D" Hot Asphalt Mix Pavement
(Light Duty)
1498910%16488SF0.032527.6 $ 45.00 $ 1.4 $ 23,742.6 $ 1.0 $ 16,487.9 $ 2.4 $ 40,230
54
289" Thick Compacted Flexible Base41610%458CY1.000458.0 $ 45.00 $ 45.0 $ 20,609.9 $ 68.2 $ 31,235.4 $ 113.2 $ 51,845
55
296" Thick Compacted Sub-Grade1498910%16488SF0.007115.4 $ 45.00 $ 0.3 $ 5,193.7 $ 0.4 $ 6,595.2 $ 0.7 $ 11,789
56
57
Heavy-Duty Concrete Pavement
58
30"A3" 6" Thick Heavy-Duty Concrete Pavement
W/ Reinforcement
4010%44CY2.700118.1 $ 45.00 $ 121.5 $ 5,316.3 $ 235.0 $ 10,282.6 $ 356.5 $ 15,599
59
316" Thick Compacted Sub-Grade214810%2363SF0.00716.5 $ 45.00 $ 0.3 $ 744.3 $ 0.4 $ 945.1 $ 0.7 $ 1,689
60
321/2" Expansion Joint 1/2" X3/8" Sealant1435%150LF0.0182.7 $ 45.00 $ 0.8 $ 121.8 $ 0.8 $ 123.3 $ 1.6 $ 245
61
331/2"X1/8" Bond Breaker Material1435%150LF0.0101.5 $ 45.00 $ 0.5 $ 67.7 $ 0.2 $ 33.1 $ 0.7 $ 101
62
341/2" X 6" Resilient Filler1435%150LF0.0203.0 $ 45.00 $ 0.9 $ 135.3 $ 1.3 $ 188.0 $ 2.2 $ 323
63
351/2" Construction Joint 1/2" X3/8" Sealant2155%226LF0.0184.1 $ 45.00 $ 0.8 $ 182.7 $ 0.8 $ 184.9 $ 1.6 $ 368
64
36Formwork16410%180SF0.0183.2 $ 45.00 $ 0.8 $ 145.7 $ 3.0 $ 539.6 $ 3.8 $ 685
65
66
Concrete Sidewalk
67
37"B1" 4" Thick Concrete Sidewalk W/ Welded Wire Flat6710%74CY2.600192.5 $ 45.00 $ 117.0 $ 8,664.1 $ 198.0 $ 14,662.3 $ 315.0 $ 23,326
68
38Sheets 6" X 6" W2.9 X W2.9 Or #3 Bars @ 12" O.C.B.W. Centered In Slab534610%5881SF0.00847.0 $ 45.00 $ 0.4 $ 2,117.0 $ 0.6 $ 3,234.3 $ 0.9 $ 5,351
69
391" Thick Sand Cushion1710%18CY0.80014.6 $ 45.00 $ 36.0 $ 658.6 $ 63.0 $ 1,152.6 $ 99.0 $ 1,811
70
40Compacted Sub-Grade534610%5881SF0.00741.2 $ 45.00 $ 0.3 $ 1,852.4 $ 0.4 $ 2,352.2 $ 0.7 $ 4,205
71
41Formwork108110%1189SF0.01821.4 $ 45.00 $ 0.8 $ 963.2 $ 3.0 $ 3,567.3 $ 3.8 $ 4,530
72
73
42"B2" 4" Thick Concrete Sidewalk W/ Welded Wire Flat1110%12CY2.60030.0 $ 45.00 $ 117.0 $ 1,351.6 $ 198.0 $ 2,287.4 $ 315.0 $ 3,639
74
43#3 Bars @ 12" O.C Centered In Slab3145%329LBS0.0113.6 $ 45.00 $ 0.5 $ 163.0 $ 1.0 $ 329.3 $ 1.5 $ 492
75
44#3 Bars @ 8" O.C Centered In Slab3145%329LBS0.0113.6 $ 45.00 $ 0.5 $ 163.0 $ 1.0 $ 329.3 $ 1.5 $ 492
76
452" Thick Sand Cushion510%5CY0.8004.3 $ 45.00 $ 36.0 $ 195.7 $ 63.0 $ 342.5 $ 99.0 $ 538
77
46Compacted Sub-Grade83410%917SF0.0076.4 $ 45.00 $ 0.3 $ 289.0 $ 0.4 $ 367.0 $ 0.7 $ 656
78
47Formwork15510%171SF0.0183.1 $ 45.00 $ 0.8 $ 138.1 $ 3.0 $ 511.5 $ 3.8 $ 650
79
80
Concrete Curb
81
48"C1" (6"X9") Concrete Curb (2390 Lf)3310%37CY2.70098.6 $ 45.00 $ 121.5 $ 4,436.4 $ 180.0 $ 6,572.5 $ 301.5 $ 11,009
82
492#3 Bar1797.285%1887LBS0.01120.8 $ 45.00 $ 0.5 $ 934.1 $ 1.0 $ 1,887.1 $ 1.5 $ 2,821
83
50Formwork239010%2629SF0.01847.3 $ 45.00 $ 0.8 $ 2,129.5 $ 3.0 $ 7,887.0 $ 3.8 $ 10,016
84
85
51"C2" (20"X9") Standard / Flush Concrete Curb (150 Lf)710%8CY2.70020.7 $ 45.00 $ 121.5 $ 930.0 $ 180.0 $ 1,377.8 $ 301.5 $ 2,308
86
523#3 Bar112.85%118LBS0.0111.3 $ 45.00 $ 0.5 $ 58.6 $ 0.9 $ 106.6 $ 1.4 $ 165
87
53Formwork50110%551SF0.0189.9 $ 45.00 $ 0.8 $ 446.4 $ 3.0 $ 1,653.3 $ 3.8 $ 2,100
88
89
54"C3" (9"X12") Concrete Curb (156 Lf)4.310%5CY2.70012.9 $ 45.00 $ 121.5 $ 579.2 $ 180.0 $ 858.0 $ 301.5 $ 1,437
90
5518" Bar @ 18" O.C1565%164LF0.0111.8 $ 45.00 $ 0.5 $ 81.1 $ 1.0 $ 163.8 $ 1.5 $ 245
91
56Formwork31210%343SF0.0186.2 $ 45.00 $ 0.8 $ 278.0 $ 3.0 $ 1,029.6 $ 3.8 $ 1,308
92
93
Concrete Wheel stop
94
57"F" (10" X6'-0") Precast Concrete Wheel stop W/ 2 #4 Bars870%87EA1.285111.8 $ 45.00 $ 57.8 $ 5,030.8 $ 124.0 $ 10,788.0 $ 181.8 $ 15,819
95
58"A2" 2" Thick Type "D" Hot Asphalt Mix Pavement
(Medium Duty)
3411610%37528SF0.0381426.0 $ 45.00 $ 1.7 $ 64,172.2 $ 1.2 $ 46,534.2 $ 3.0 $ 110,706
96
5912" Thick Compacted Flexible Base126410%1390CY1.0001389.9 $ 45.00 $ 45.0 $ 62,546.0 $ 62.0 $ 86,174.5 $ 107.0 $ 148,720
97
606" Thick Compacted Sub-Grade3411610%37528SF0.007262.7 $ 45.00 $ 0.3 $ 11,821.2 $ 0.4 $ 15,011.0 $ 0.7 $ 26,832
98
99
Parking Paint
100
61"E1" Pavement Marking International Handicap Symbol60%6EA0.5003.0 $ 45.00 $ 22.5 $ 135.0 $ 72.0 $ 432.0 $ 94.5 $ 567