1 | FDP Form 10a - Bid Results on Civil Works | 3 Forms to Use: | |||||||||||||||||||||||
2 | 1. Bid Results on Civil Works | ||||||||||||||||||||||||
3 | 2. Bid Results on Goods and Services | ||||||||||||||||||||||||
4 | 3. Bid Results on Consulting Services | ||||||||||||||||||||||||
5 | INDIVIDUAL BID-OUTS ARE NOT ALLOWED | ||||||||||||||||||||||||
6 | Republic of the Philippines | ||||||||||||||||||||||||
7 | CIVIL WORKS BID-OUT | ||||||||||||||||||||||||
8 | Province, City or Municipality: Antipolo City | ||||||||||||||||||||||||
9 | 1st Quarter, CY 2020 | ||||||||||||||||||||||||
10 | |||||||||||||||||||||||||
11 | No. | Reference No. | Name of Project | Approved Budget for Contract | Location | Winning Bidder | Name and Address | Bid Amount | Bidding Date | Contract Duration | |||||||||||||||
12 | |||||||||||||||||||||||||
13 | 1 | Antipolo-06February2020-01 | Construction of 10 X 24 Ynares Multi-Purpose Covered Court at Sumilang Elementary School, Brgy. San Jose, Antipolo City | P 3,500,000.00 | Brgy. San Jose, Antipolo City | 1C4M BUILDERS INC. | Meynard C. Ko Antipolo City | 3,486,500.00 | Feb. 6, 2020 | 150 | |||||||||||||||
14 | 2 | Antipolo-06February2020-02 | Installation of Traffic Light Circumferential Road Corner Marigman St., Brgy. San Roque, Antipolo City | P 4,194,148.18 | Brgy. San Roque, Antipolo City | ANROL CONSTRUCTION | Clarence C. Cacho Sampaloc, Manila | 4,180,600.00 | Feb. 6, 2020 | 150 | |||||||||||||||
15 | 3 | Antipolo-06February2020-03 | Construction of Regulatory Sign Steel Structure at Various Footbridges, Antipolo City | P 1,995,403.25 | City Wide, Antipolo City | KIT UBIADAS CONTRUCTION CORP. | Francisco G. Ubiadas Binangonan, Rizal | 1,985,789.50 | Feb. 6, 2020 | 120 | |||||||||||||||
16 | 4 | Antipolo-06February2020-04 | Various Improvement of City Animal Pound and Animal Control Center at Motorpool Area, Brgy. San Jose, Antipolo City | P 2,500,000.00 | Brgy. San Jose, Antipolo City | TNV CONSTRUCTION | Eliza N. Villarico Malolos City, Bulacan | 2,487,500.00 | Feb. 6, 2020 | 120 | |||||||||||||||
17 | 5 | Antipolo-06February2020-05 | Repair / Improvement of Hinulugang Taktak Protected Landscape Swimming Pool, Brgy. Dela Paz, Antipolo City | P 4,999,999.64 | Brgy. Dela Paz, Antipolo City | ANROL CONSTRUCTION | Clarence C. Cacho Sampaloc, Manila | 4,985,000.00 | Feb. 6, 2020 | 150 | |||||||||||||||
18 | 6 | Antipolo-06February2020-06 | Construction of Drainage Canal Along Don Lucas Street and Don Pablo Street at Villa Cecilla Subdivision, Brgy. Mambugan, Antipolo City | P 3,300,000.00 | Brgy. Mambugan, Antipolo City | FLAG CONSTRUCTION CORP. | Fernando L. Arada Binangonan, Rizal | 3,286,500.00 | Feb. 6, 2020 | 180 | |||||||||||||||
19 | |||||||||||||||||||||||||
20 | 7 | Antipolo-27February2020-01 | Various Improvements at San Roque National High School and URS Antipolo, Brgy. San Roque, Antipolo City ( 2020 – Package 01) a. Repainting of Main Gate, Fence and Waiting Shed at San Roque National High School, Brgy. San Roque, Antipolo City b. Installation of Steel Gratings on the Open Canals of URS Antipolo, Brgy. San Roque, Antipolo City | a. 157,061.40 b. 699,881.40 -------------------- P 856,942.80 | a. Brgy. San Roque, Antipolo City b. Brgy. San Roque, Antipolo City | OLIVER AQUINO CONSTRUCTION | Oliver O. Aquino Binangonan, Rizal | a. 155,165.27 b. 691,734.73 ___________ 846,900.00 | Feb. 27, 2020 | 120 | |||||||||||||||
21 | 8 | Antipolo-27February2020-02 | Construction of Stone Masonry Riverwall and Sidewalk with Drainage at Brgy. Mayamot and Brgy. San Roque, Antipolo City ( 2020 – Package 02) a. Construction of Stone Masonry Riverwall (Portion) Along Creek at Ocean Street Interior, Virginia Summerfield Subd., Brgy. Mayamot, Antipolo City b. Construction of Sidewalk with Drainage (Portion) at J. Sumulong Street, Brgy. San Roque, Antipolo City | a. 677,258.42 b. 386,718.60 -------------------- P 1,063,977.02 | a. Brgy. Mayamot, Antipolo City b. Brgy. San Roque, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | a. 671,768.96 b. 379,698.50 ____________ 1,051,467.46 | Feb. 27, 2020 | 120 | |||||||||||||||
22 | 9 | Antipolo-27February2020-03 | Construction of Slope Protection Masonry Wall along Labahan Creek, Valley Homes II, Brgy. Cupang, Antipolo City | P 1,450,935.80 | Brgy. Cupang, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 1,445,958.15 | Feb. 27, 2020 | 160 | |||||||||||||||
23 | 10 | Antipolo-27February2020-04 | Construction of Various Stone Masonry Riverwalls at Brgy. San Jose, Antipolo City ( 2020 – Package 03) a. Construction of Stone Masonry Riverwall at Both Ends of Mini-Bridge 1 in Sitio Kaysakat, Brgy. San Jose, Antipolo City b. Construction of Stone Masonry Riverwall at Both Ends of Mini-Bridge 2 in Sitio Kaysakat, Brgy. San Jose, Antipolo City c. Construction of Stone Masonry Riverwall at Both Ends of Mini-Bridge 3 in Sitio Kaysakat, Brgy. San Jose, Antipolo City | a. 792,063.58 b. 791,330.90 c. 799,900.95 -------------------- P 2,383,295.43 | a. Brgy. San Jose, Antipolo City b. Brgy. San Jose, Antipolo City c. Brgy. San Jose, Antipolo City | MARIANO M. MACLANG CONSTRUCTION & DEV'T | Mariano M. Maclang Taytay, Rizal | a. 788,099.80 b. 785,300.05 c. 796,596.00 ___________ 2,369,995.85 | Feb. 27, 2020 | 160 | |||||||||||||||
24 | 11 | Antipolo-27February2020-05 | Construction of Stone Masonry Riverwall and Improvement/Construction of Drainage Canal at Brgy. San Jose, Antipolo City ( 2020 – Package 04) a. Construction of Stone Masonry Riverwall at Both Ends of Mini-Bridge 4 in Sitio Kaysakat, Brgy. San Jose, Antipolo City b. Improvement/Construction of Drainage Canal at Jacksonville Street, Joyous Heights, Sitio Hinapao, Brgy. San Jose, Antipolo City | a. 598,141.19 b. 448,775.85 -------------------- P 1,046,917.04 | a. Brgy. San Jose, Antipolo City b. Brgy. San Jose, Antipolo City | FLAG CONSTRUCTION CORPORATION | Fernando L. Arada Binangonan, Rizal | a. 592,126.48 b. 442,760.15 ____________ 1,034,886.63 | Feb. 27, 2020 | 120 | |||||||||||||||
25 | 12 | Antipolo-27February2020-06 | Construction of Stone Masonry Riverwall (Portion) along Singalong Creek at PCUP-RPG Ville, Brgy. San Jose, Antipolo City (Phase 3) | P 1,779,629.08 | Brgy. San Jose, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 1,770,000.00 | Feb. 27, 2020 | 120 | |||||||||||||||
26 | 13 | Antipolo-27February2020-07 | Construction of Trash Trap, Road Concreting (Portion) and Construction of Riprap at Brgy. Cupang, Antipolo City ( 2020 – Package 05) a. Construction of Trash Trap along Labahan Creek and at the end of Dionysus Street, Crestview Subdivision, Brgy. Cupang, Antipolo City b. Road Concreting (Portion) and Construction of Riprap (Portion) at Road Lot 8, Sanchez Realty Subdivision, Brgy. Cupang, Antipolo City | a. 415,000.00 b. 432,742.62 -------------------- P 847,742.62 | a. Brgy. Cupang, Antipolo City b. Brgy. Cupang, Antipolo City | RSS CONSTRUCTION & SUPPLIES | Noemi D. Soriano Teresa, Rizal | a. 411,101.75 b. 427,905.53 ____________ 839,007.28 | Feb. 27, 2020 | 160 | |||||||||||||||
27 | 14 | Antipolo-27February2020-08 | Construction of Stone Masonry Riverwall (Portion) along Tabak Creek between Carigma Street and Dela Paz Street, Brgy. San Jose, Antipolo City | P 2,222,882.48 | Brgy. San Jose, Antipolo City | PST CONSTRUCTION | Procopio S. Torres Jr. Antipolo, City | 2,209,879.81 | Feb. 27, 2020 | 160 | |||||||||||||||
28 | 15 | Antipolo-27February2020-09 | Various Improvement at Antipolo City Jail, Brgy. San Jose, Antipolo City | P 2,500,000.00 | Brgy. San Jose, Antipolo City | OLIVER AQUINO CONSTRUCTION | Oliver O. Aquino Binangonan, Rizal | 2,486,500.00 | Feb. 27, 2020 | 160 | |||||||||||||||
29 | 16 | Antipolo-27February2020-10 | Concreting of Road with Drainage System (Phase II) At Zapanta Compound, M. L. Quezon Extension, Barangay San Roque | P 2,000,000.00 | Brgy. San Roque, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 1,987,500.00 | Feb. 27, 2020 | 160 | |||||||||||||||
30 | 17 | Antipolo-27February2020-11 | Improvement of Road with Drainage System at Sto. Niño Street , Milagros Estate Subdivision, Barangay Dalig | P 2,500,000.00 | Brgy. Dalig, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 2,486,500.01 | Feb. 27, 2020 | 160 | |||||||||||||||
31 | 18 | Antipolo-27February2020-12 | Various Improvement/Construction of Roads with Drainage System at Brgy. San Jose, Antipolo City( 2020 – Package 06) a. Improvement/Construction of Roads with Drainage System for Road Lot -8 at Sitio Kaban, Brgy. San Jose, Antipolo City b. Improvement/Construction of Roads with Drainage System for Alley-2 at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | a. 708,236.29 b. 562,647.95 -------------------- P 1,270,884.24 | a. Brgy. San Jose, Antipolo City b. Brgy. San Jose, Antipolo City | ST. IVADZ BUILDERS | Adrian Z. Matienzo Tanay, Rizal | a. 698,639.35 b. 559,860.65 ___________ 1,258,500.00 | Feb. 27, 2020 | 160 | |||||||||||||||
32 | 19 | Antipolo-27February2020-13 | Concreting of Main Road and Construction of Riprap (Portion) at PCUP-RPG Ville, Brgy. San Jose, Antipolo City | P 598,692.02 | a. Brgy. San Jose, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 592,190.00 | Feb. 27, 2020 | 120 | |||||||||||||||
33 | 20 | Antipolo-27February2020-14 | Repair/ Repainting of School Building and Pathwalk Concreting at Brgy. Calawis, Antipolo City ( 2020 – Package 07) a. Repair/ Repainting of Two (2) Storey Four (4) Classrooms Deped Building at Calawis Elementary School, Brgy. Calawis, Antipolo City b. Pathwalk Concreting (Portion) at Calawis Elementary School, Brgy. Calawis, Antipolo City | a. 999,411.71 b. 98,392.22 -------------------- P 1,097,803.93 | a. Brgy. Calawis, Antipolo City b. Brgy. Calawis, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | a. 990,500.00 b. 97,500.00 ___________ 1,088,000.00 | Feb. 27, 2020 | 120 | |||||||||||||||
34 | 21 | Antipolo-27February2020-15 | Various Repair/ Improvement of School Buildings at Tanza Elementary School, Brgy. San Jose, Antipolo City ( 2020 – Package 08) a. Repair/Improvement of Two(2) Storey, Four(4) Classrooms PLED Building at Tanza Elementary School, Sitio Tanza II Brgy. San Jose, Antipolo City b. Repair/Improvement of Two(2) Storey, Four(4) Classrooms DPWH Building at Tanza Elementary School, Sitio Tanza II Brgy. San Jose, Antipolo City | a. 1,053,375.83 b. 1,106,323.15 -------------------- P 2,159,698.98 | a. Brgy. San Jose, Antipolo City b. Brgy. San Jose, Antipolo City | OLIVER AQUINO CONSTRUCTION | Oliver O. Aquino Binangonan, Rizal | a. 1,047,666.64 b. 1,098,513.36 ____________ 2,146,180.00 | Feb. 27, 2020 | 120 | |||||||||||||||
35 | 22 | Antipolo-27February2020-16 | Repair/ Repainting of Four (4) Storey Twelve Rooms ACG Building at San Roque National High School, Brgy. San Roque, Antipolo City | P 2,500,000.00 | Brgy. San Roque, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | 2,486,000.00 | Feb. 27, 2020 | 120 | |||||||||||||||
36 | 23 | Antipolo-27February2020-17 | Repair/Rehabilitation Works of Three (3) Storey Six (6) Rooms PLED Building at San Isidro National High School Brgy San Isidro, Antipolo City | P 1,197,787.23 | Brgy. San Isidro, Antipolo City | FAILURE OF BIDS | Feb. 27, 2020 | 120 | |||||||||||||||||
37 | 24 | Antipolo-27February2020-18 | Repair of Comfort Rooms at Kaysakat Elementary School, Brgy. San Jose, Antipolo City | P 1,004,204.55 | Brgy. San Jose, Antipolo City | FLAG CONSTRUCTION CORPORATION | Fernando L. Arada Binangonan, Rizal | 992,700.00 | Feb. 27, 2020 | 120 | |||||||||||||||
38 | 25 | Antipolo-27February2020-19 | Construction of Slope Protection Wall at Engineering Workshop Building at Government Center (AITECH), Brgy. San Jose, Antipolo City | P 2,965,484.26 | Brgy. San Jose, Antipolo City | 22 PRIME CONSTRUCTION AND REALTY DEVELOPMENT INC. | Sheryl M. Chua | 2,952,000.00 | Feb. 27, 2020 | 120 | |||||||||||||||
39 | 26 | Antipolo-27February2020-20 | Asphalt Overlaying (Portion) at Golden Shower Drive, Villa Grande Subdivision, Brgy. Cupang, Antipolo City | P 4,842,896.95 | Brgy. Cupang, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 4,827,900.02 | Feb. 27, 2020 | 60 | |||||||||||||||
40 | 27 | Antipolo-27February2020-21 | Construction of Ynares Stage at Sumilang Elementary School, Brgy. San Jose, Antipolo City | P 1,140,445.03 | Brgy. San Jose, Antipolo City | RSS CONSTRUCTION & SUPPLIES | Noemi D. Soriano Teresa, Rizal | 1,128,900.00 | Feb. 27, 2020 | 120 | |||||||||||||||
41 | |||||||||||||||||||||||||
42 | 28 | Antipolo-05March2020-01 | Various Improvement of 17x30 Ynares Multi-Purpose Covered Court at Cuesta Verde Executive Village, Brgy. Dalig, Antipolo City | P 2,133,899.89 | Brgy. Dalig, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 2,120,400.00 | March 5, 2020 | 120 | |||||||||||||||
43 | 29 | Antipolo-05March2020-02 | Construction of 2 - Arcs at Sitio Kabute, Barangay Dela Paz, Antipolo City | P 587,021.35 | Brgy. Dela Paz, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 579,321.18 | March 5, 2020 | 120 | |||||||||||||||
44 | 30 | Antipolo-05March2020-03 | Various Repair/ Improvement of Multi-Purpose Buildings at Brgy. San Isidro and Brgy. San Jose, Antipolo City ( 2020 – Package 09) a. Repair/ Improvement of Multi-Purpose Building at Sitio Monte Oro, Loremar Homes, Barangay San Isidro, Antipolo City b. Improvement of One (1) Storey ACG Multi - Purpose Building at Sitio Kaban, Brgy. San Jose, Antipolo City | a. 779,261.51 b. 899,933.41 ----------------- P 1,679,194.92 | a. Brgy. San Isidro, Antipolo City b. Brgy. San Jose, Antipolo City | OLIVER AQUINO CONSTRUCTION | Oliver O. Aquino Binangonan, Rizal | a. 773,950.98 b. 893,649.02 ___________ 1,667,600.00 | March 5, 2020 | 120 | |||||||||||||||
45 | 31 | Antipolo-05March2020-04 | Repair/Rehabilitation of Stone Masonry Riverwall (Portion) along the Creek from Hermes Street to Prixus Street, Crestview Subdivision, Brgy. Cupang, Antipolo City | P 2,914,950.50 | Brgy. Cupang, Antipolo City | 1C4M BUILDERS INC. | Meynard C. Ko Antipolo City | 2,899,950.00 | March 5, 2020 | 120 | |||||||||||||||
46 | 32 | Antipolo-05March2020-05 | Construction of Riprap and Reblocking of Road at Brgy. San Isidro and Brgy. San Roque, Antipolo City ( 2020 – Package 10) a. Construction of Riprap at Monang Creek (Portion), Brgy. San Isidro, Antipolo City b. Reblocking of Road (Portion) of Gumamela St. at Lornaville Subd., Brgy. San Roque, Antipolo City | a. 592,914.97 b. 1,262,016.44 ----------------- P 1,854,931.41 | a. Brgy. San Isidro, Antipolo City b. Brgy. San Roque, Antipolo City | CJBJ CONSTRUCTION AND SUPPLIES | Charles Jeison B. Javier Taytay, Rizal | a. 588,024.78 b. 1,256,945.00 _____________ 1,844,969.78 | March 5, 2020 | 120 | |||||||||||||||
47 | 33 | Antipolo-05March2020-06 | Construction of Stone Masonry Wall along the Creek near Santos Compound Extension, Brgy. Mambugan, Antipolo City | P 1,314,264.23 | Brgy. Mambugan, Antipolo City | BIGBOY CONSTRUCTION SERVICES | Noel S. Flores Marikina, City | 1,301,756.82 | March 5, 2020 | 120 | |||||||||||||||
48 | 34 | Antipolo-05March2020-07 | Construction of Stone Masonry Riverwall along Labahan Creek at Crestview Subdivision, Brgy. Cupang, Antipolo City | P 1,328,216.37 | Brgy. Cupang, Antipolo City | 1C4M BUILDERS INC. | Meynard C. Ko Antipolo City | 1,314,356.21 | March 5, 2020 | 120 | |||||||||||||||
49 | 35 | Antipolo-05March2020-08 | Road Concreting of Road Lot 2 (with PIN No. 177-01-012-023-036) At Josephina Subdivision, Brgy. Mambugan, Antipolo City | P 1,850,000.00 | Brgy. Mambugan, Antipolo City | E.P. CORNEJO CONSTRUCTION | Edmundo P. Cornejo Antipolo, City | 1,835,500.00 | March 5, 2020 | 120 | |||||||||||||||
50 | 36 | Antipolo-05March2020-09 | Improvement of Martinez Street, Brgy. San Roque, Antipolo City | P 2,542,347.82 | Brgy. San Roque, Antipolo City | PST CONSTRUCTION | Procopio S. Torres Jr. Antipolo, City | 2,527,800.00 | March 5, 2020 | 120 | |||||||||||||||
51 | 37 | Antipolo-05March2020-10 | Concreting of Rosal St. at Bermuda Heights Subd., Brgy. San Luis, Antipolo City | P 703,964.60 | Brgy. San Luis, Antipolo City | GKB BUILDERS | Gerald Kenn SJ. Bilog Morong, Rizal | 694,500.00 | March 5, 2020 | 120 | |||||||||||||||
52 | 38 | Antipolo-05March2020-11 | Improvement/Construction of Roads with Drainage System for Alley-1 at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | P 960,117.35 | Brgy. San Jose, Antipolo City | PST CONSTRUCTION | Procopio S. Torres Jr. Antipolo, City | 950,940.26 | March 5, 2020 | 120 | |||||||||||||||
53 | 39 | Antipolo-05March2020-12 | Construction of Stone Masonry Riverwall along the Creek Lower Buhanginan, Sitio Tagbac, Brgy. San Jose, Antipolo City | P 975,726.97 | Brgy. San Jose, Antipolo City | PST CONSTRUCTION | Procopio S. Torres Jr. Antipolo, City | 965,726.69 | March 5, 2020 | 120 | |||||||||||||||
54 | 40 | Antipolo-05March2020-13 | Construction of Drainage Canal and Repair/Rehabilitation of Stone Masonry Riverwall at Brgy. Cupang, Antipolo City ( 2020 – Package 11) a. Construction of Drainage Canal from Tethys Street to Labahan Creek, Crestview Subdivision, Brgy. Cupang, Antipolo City b. Repair/Rehabilitation of Stone Masonry Riverwall (Portion) along the Creek at the Upstream Portion of Bridge 2, beside Hermes Street, Crestview Subdivision, Brgy. Cupang, Antipolo City c. Construction of Drainage Canal at Don Vicente St. Peñafrancia Subd., Brgy. Cupang, Antipolo City | a. 304,223.40 b. 589,253.23 c. 581,090.19 ----------------- P 1,474,566.82 | a. Brgy. Cupang, Antipolo City b. Brgy. Cupang, Antipolo City c. Brgy. Cupang, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | a. 301,359.74 b. 583,303.02 c. 577,384.04 ____________ 1,462,046.80 | March 5, 2020 | 150 | |||||||||||||||
55 | 41 | Antipolo-05March2020-14 | Various Concreting of Roads at Josephina Subdivision, Brgy. Mambugan, Antipolo City ( 2020 – Package 12) a. Road Concreting of Road Lot 1 (with PIN No. 177-01-012-023-041) at Josephina Subdivision, Brgy. Mambugan, Antipolo City b. Road Concreting of Road Lot 3 (with PIN No. 177-01-012-023-029) at Josephina Subdivision, Brgy. Mambugan, Antipolo City c. Road Concreting of Road Lot 4 (with PIN No. 177-01-012-023-019) at Josephina Subdivision, Brgy. Mambugan, Antipolo City | a. 1,224,560.96 b. 234,997.55 c. 379,207.54 ----------------- P 1,838,766.05 | a. Brgy. Mambugan, Antipolo City b. Brgy. Mambugan, Antipolo City c. Brgy. Mambugan, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | a. 1,217,327.69 b. 233,506.75 c. 375,425.56 _____________ 1,826,260.00 | March 5, 2020 | 150 | |||||||||||||||
56 | 42 | Antipolo-05March2020-15 | Improvement/Construction of Drainage Canal and Repair/ Improvement of School Building at Brgy. San Jose, Antipolo City ( 2020 – Package 13) a. Improvement/Construction of Drainage Canal at Jacksonville and Brookfield Street, Joyous Heights, Sitio Hinapao, Brgy. San Jose, Antipolo City b. Repair/ Improvement of Two(2) Storey, Four(4) Classrooms AUS-AID Building at Old Boso-Boso Elementary School, Sitio Boso-Boso Brgy. San Jose, Antipolo City | a. 846,609.14 b 1,032,820.97 ----------------- P 1,879,430.11 | a. Brgy. San Jose, Antipolo City b. Brgy. San Jose, Antipolo City | CANCELLED | 150 | ||||||||||||||||||
57 | 43 | Antipolo-05March2020-16 | Construction of Perimeter Fence at Sapinit Elem. School, Sitio Sapinit, Brgy. San Juan, Antipolo City | P 747,070.60 | Brgy. San Juan, Antipolo City | CANCELLED | 120 | ||||||||||||||||||
58 | 44 | Antipolo-05March2020-17 | Improvement of Drainage System at C. Lawis St. (From M.L. Quezon to Tabak) Phase II, Antipolo City | P 2,500,000.00 | City Wide, Antipolo City | INTERBUILD CONSTRUCTION | Serafin R. Santiago Jr. Pasig, City | 2,486,490.34 | March 5, 2020 | 120 | |||||||||||||||
59 | |||||||||||||||||||||||||
60 | 45 | Antipolo-12March2020-01 | Improvement/Construction of Drainage Canal at Nashville Street, Joyous Heights, Sitio Hinapao, Brgy. San Jose, Antipolo City | P 1,383,107.79 | Brgy. San Jose, Antipolo City | PST CONSTRUCTION | Procopio S. Torres Jr. Antipolo, City | 1,371,600.00 | March 12, 2020 | 120 | |||||||||||||||
61 | 46 | Antipolo-12March2020-02 | Rehabilitation of Drainage Canal and Road Concreting at Road Lot 1 Peace Village Phase - 3, Brgy. San Luis Antipolo City | P 2,594,235.66 | Brgy. San Luis, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | 2,582,200.00 | March 12, 2020 | 120 | |||||||||||||||
62 | 47 | Antipolo-12March2020-03 | Repair/Repainting of Three (3) Storey Nine (9) Classroom DepEd School Building A at Bagong Nayon I Elementary School, Brgy. Bagong Nayon, Antipolo City | P 1,200,000.00 | Brgy. Bagong Nayon, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 1,188,000.00 | March 12, 2020 | 120 | |||||||||||||||
63 | 48 | Antipolo-12March2020-04 | Repair/Repainting of Three (3) Storey Nine (9) Classroom DepEd School Building B at Bagong Nayon I Elementary School, Brgy. Bagong Nayon, Antipolo City | P 2,709,987.30 | Brgy. Bagong Nayon, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | 2,697,400.00 | March 12, 2020 | 120 | |||||||||||||||
64 | 49 | Antipolo-12March2020-05 | Repair/ Repainting of Various School Buildings at Mayamot Elementary School, Brgy. Mayamot, Antipolo City (2020 – Package 14) a. Repair/Repaint of Two (2) Storey Four (4) Classroom ACG Building B at Mayamot Elementary School, Brgy. Mayamot, Antipolo City b. Repair/Repaint of Three (3) Storey Nine (9) DepEd Building F at Mayamot Elementary School, Brgy. Mayamot, Antipolo City | a. 850,000.00 b. 1,000,000.00 -------------------- P 1,850,000.00 | a. Brgy. Mayamot, Antipolo City b. Brgy. Mayamot, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 1,838,500.00 | March 12, 2020 | 150 | |||||||||||||||
65 | 50 | Antipolo-12March2020-06 | Repainting of School Building and Improvement of Perimeter Fence at Brgy. San Isidro and Brgy. San Jose, Antipolo City (2020 – Package 15) a. Repaint of Three (3) Storey Six (6) Classroom DepEd Building B at Bagong Nayon II Elementary School, Brgy. San Isidro, Antipolo City b. Improvement of Perimeter Fence (Portion) at Pantay Elementary School, Brgy. San Jose, Antipolo City | a. 400,000.00 b. 706,063.84 -------------------- P 1,106,063.84 | a. Brgy. San Isidro, Antipolo City b. Brgy. San Jose, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | 1,094,500.00 | March 12, 2020 | 150 | |||||||||||||||
66 | 51 | Antipolo-12March2020-07 | Repair/ Improvement of Various School Buildings at Brgy. San Juan and Brgy. San Jose, Antipolo City (2020 – Package 16) a. Repair/Improvement Two(2) Storey, Six(6) Classrooms DepEd Building At Sapinit Elementary School, Brgy. San Juan, Antipolo City b. Repair/Improved of Three(3) Storey, Six(6) Classrooms DepEd Building at Tanza Elementary School, Sitio Tanza II, Brgy. San Jose, Antipolo City | a. 1,786,408.64 b. 1,162,007.51 -------------------- P 2,948,416.15 | a. Brgy. San Juan, Antipolo City b. Brgy. San Jose, Antipolo City | MAGLULUMA ENTERPRISES | Sunshine Grace M. Guevara Antipolo, City | 2,933,900.00 | March 12, 2020 | 150 | |||||||||||||||
67 | 52 | Antipolo-12March2020-08 | Repair/ Rehabilitation Works of Various School Buildings at Brgy. San Isidro, Antipolo City (2020 – Package 17) a. Repair/Rehabilitation Works of Two (2) Storey Four (4) Rooms PLED Building at San Isidro Elementary School, Brgy San Isidro Antipolo City b. Repair/Rehabilitation Works of Two (2) Storey Four (4) Rooms PLED Building at San Isidro National High School Brgy San Isidro, Antipolo City c. Repair/Rehabilitation Works of Three (3) Storey Nine (9) Rooms PLED Building at San Isidro National High School Brgy San Isidro, Antipolo City | a. 727,727.34 b. 994,590.36 c. 1,485,576.29 -------------------- P 3,207,893.99 | a. Brgy. San Isidro, Antipolo City b. Brgy. San Isidro, Antipolo City c. Brgy. San Isidro, Antipolo City | LARD BUILDERS | Renato C. Villaroman Baras, Rizal | 3,191,119.35 | March 12, 2020 | 150 | |||||||||||||||
68 | 53 | Antipolo-12March2020-09 | Reconcreting of Ground near Court at Mambugan II Elementary School, Brgy. Mambugan Antipolo City | P 250,000.00 | Brgy. Mambugan, Antipolo City | RSS CONSTRUCTION & SUPPLIES | Noemi D. Soriano Teresa, Rizal | 245,000.00 | March 12, 2020 | 120 | |||||||||||||||
69 | 54 | Antipolo-12March2020-10 | Repair/Rehabilitation Works of Two (2) Storey Six (6) Rooms Ynares Building at San Isidro National High School, Brgy San Isidro, Antipolo City | P 1,136,060.04 | Brgy. San Isidro, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | 1,124,382.16 | March 12, 2020 | 120 | |||||||||||||||
70 | 55 | Antipolo-12March2020-11 | Repair/Improvement of One(1) Storey, Six(6) Classroom Ynares Building at Antipolo City National Science and Technology High School, Brgy. San Jose, Antipolo City | P 1,230,156.19 | Brgy. San Jose, Antipolo City | JRD-D2 ENTERPRISES | Porfirio P. Mina Tanay, Rizal | 1,217,656.19 | March 12, 2020 | 120 | |||||||||||||||
71 | 56 | Antipolo-12March2020-12 | Repair/ Repainting of Various Comfort Rooms at Brgy. San Isidro and Brgy. San Roque, Antipolo City (2020 – Package 18) a. Repair/Repainting of Comfort Rooms at Bagong Nayon II National Highschool - Annex, Brgy. San Isidro, Antipolo City b. Repair/Repainting of Comfort Rooms at Knights of Columbus Elementary School, Brgy. San Roque, Antipolo City | a. 400,000.00 b. 272,862.80 -------------------- P 672,862.80 | a. Brgy. San Isidro, Antipolo City b. Brgy. San Roque Antipolo City | K.B.B. EL BUILDERS | Benito O. Kim An Antipolo City | 664,816.29 | March 12, 2020 | 150 | |||||||||||||||
72 | 57 | Antipolo-12March2020-13 | Rehabilitation of Drainage Canal of Road 2 at Villa Eloisa, Brgy. Dalig, Antipolo City | P 593,437.76 | Brgy. Dalig, Antipolo City | PST CONSTRUCTION | Procopio S. Torres Jr. Antipolo, City | 586,200.00 | March 12, 2020 | 120 | |||||||||||||||
73 | 58 | Antipolo-12March2020-14 | Construction of Drainage Canal at Road Lot 3 Peace Village Phase - 3, Brgy. San Luis Antipolo City | P 565,036.59 | Brgy. San Luis, Antipolo City | GKB BUILDERS | Gerald Kenn SJ. Bilog Morong, Rizal | 558,000.00 | March 12, 2020 | 120 | |||||||||||||||
74 | 59 | Antipolo-12March2020-15 | Concreting of Road with Riprap in Front of Covered Court Creek at Sitio PCUP-RPG Ville, Brgy. San Jose, Antipolo City | P 1,197,873.97 | Brgy. San Jose, Antipolo City | FLAG CONSTRUCTION CORPORATION | Fernando L. Arada Binangonan, Rizal | 1,185,383.25 | March 12, 2020 | 120 | |||||||||||||||
75 | 60 | Antipolo-12March2020-16 | Repair/ Repainting of Two (2) Storey, Six (6) Rooms GMA School Building at Antipolo National High School, Brgy. Sta. Cruz, Antipolo City | P 1,600,000.00 | Brgy. Sta Cruz, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | 1,586,500.00 | March 12, 2020 | 120 | |||||||||||||||
76 | 61 | Antipolo-12March2020-17 | Repair/ Repainting of Four (4) Storey, Seventeen (17) Rooms DPWH School Building C at Antipolo National High School, Brgy. Sta. Cruz, Antipolo City | P 3,120,372.06 | Brgy. Sta Cruz, Antipolo City | KIT UBIADAS CONSTRUCTION CORPORATION | Francisco G. Ubiadas Binangonan, Rizal | 3,105,000.00 | March 12, 2020 | 120 | |||||||||||||||
77 | 62 | Antipolo-12March2020-18 | Repair/ Repainting of Three (3) Storey, Nine (9) Rooms DPWH School Building at Dalig National High School, Brgy. Dalig, Antipolo City | P 1,462,693.06 | Brgy. Dalig, Antipolo City | FLS CONSTRUCTION & BUILDERS | Felimon Santos Taytay, Rizal | 1,450,192.54 | March 12, 2020 | 120 | |||||||||||||||
78 | |||||||||||||||||||||||||
79 | We hereby certify that we have reviewed the contents and hereby attest to the veracity and correctness of the data or information contained in this document. | ||||||||||||||||||||||||
80 | GLENN C. ALTARES (SGD.) | ENGR. JESUS S. GONZAGA (SGD.) | ATTY. CEDRICK JUSTICE U. CAPIRAL (SGD.) | MS. PRISCILLA R. PADUA (SGD.) | ENGR. VIOLETA S. FAIYAZ (SGD.) | ||||||||||||||||||||
81 | Business Permit & Licensing Officer | City Engineer | City Legal Officer | Officer In Charge | City Environment and Waste Management Officer | ||||||||||||||||||||
82 | Business Permit & Licensing Office | Office of the City Engineer | City Legal Office | City Budget Office | City Environment and Waste Management Office | ||||||||||||||||||||
83 | Chairman-BAC | Vice Chairman – BAC | Member-BAC | Member-BAC | Member-BAC | ||||||||||||||||||||
84 | |||||||||||||||||||||||||
85 | |||||||||||||||||||||||||
86 | |||||||||||||||||||||||||
87 | |||||||||||||||||||||||||
88 | |||||||||||||||||||||||||
89 | |||||||||||||||||||||||||
90 | |||||||||||||||||||||||||
91 | |||||||||||||||||||||||||
92 | |||||||||||||||||||||||||
93 | |||||||||||||||||||||||||
94 | |||||||||||||||||||||||||
95 | |||||||||||||||||||||||||
96 | |||||||||||||||||||||||||
97 | |||||||||||||||||||||||||
98 | |||||||||||||||||||||||||
99 | |||||||||||||||||||||||||
100 | |||||||||||||||||||||||||