1 | FDP Form 10a - Bid Results on Civil Works | |||||||||||||||||||||||||
2 | Note: Bid Results are in three (3) separate forms, particularly, for Civil Works (Form 10a -CW), Goods and Services (Form 10b - GS) and Consulting Services | |||||||||||||||||||||||||
3 | (Form 10c - CS). If there is no bidded project, good or service for the quarter, the forms must still be submitted with the said notation and signed accordingly. | |||||||||||||||||||||||||
4 | ||||||||||||||||||||||||||
5 | CIVIL WORKS BID-OUT | |||||||||||||||||||||||||
6 | ||||||||||||||||||||||||||
7 | REGION: | REGION X - NORTHERN MINDANAO | CALENDAR YEAR: | 2023 | ||||||||||||||||||||||
8 | PROVINCE: | MISAMIS ORIENTAL | QUARTER: | 2 | ||||||||||||||||||||||
9 | CITY/MUNICIPALITY: | |||||||||||||||||||||||||
10 | ||||||||||||||||||||||||||
11 | No. | Reference No. | Name of Project | Approved Budget for Contract | Location | Winning Bidder | Name and Address | Bid Amount | Bidding Date | Contract Duration | ||||||||||||||||
12 | ||||||||||||||||||||||||||
13 | 1 | 0783-23 | Construction of Water Tank, Balay Kaugmaon Center, Claveria, Misamis Oriental | 1,049,896.37 | Claveria, Misamis Oriental | NONE | N/A | N/A | April 20, 2023 | 40 Calendar Days | ||||||||||||||||
14 | 2 | 0672-23 | Improvement of Building Phase II Balay Kaugmaon, Poblacion, Claveria, Misamis Oriental | 1,582,816.18 | Poblacion, Claveria, Misamis Oriental | NONE | N/A | N/A | April 20, 2023 | 78 Calendar Days | ||||||||||||||||
15 | 3 | 0782-23 | Road Concreting Barangay Ulaliman, El Salvador City, Misamis Oriental | 999,427.58 | Ulaliman, El Salvador City, Misamis Oriental | L & L CONSTRUCTION | N/A | 996,668.10 | April 20, 2023 | 40 Calendar Days | ||||||||||||||||
16 | 4 | 0579-23 | Construction of Drainage Project at Purok 2 Barangay Patag, Manticao, Misamis Oriental | 998,972.48 | Patag, Manticao, Misamis Oriental | L & L CONSTRUCTION | N/A | 995,430.39 | April 20, 2023 | 11 Calendar Dyas | ||||||||||||||||
17 | 5 | 0671-23 | Purchase & Installation of Ice Making Machinery & Cols Storages Facility, Barangay Calangahan, Lugait, Misamis Oriental | 999,540.06 | Calangahan, Lugait, Misamis Oriental | L & L CONSTRUCTION | N/A | 997,549.72 | April 20, 2023 | 70 Calendar Days | ||||||||||||||||
18 | 6 | 0810-23 | Renovation of White House Building Misamis Oriental Integrated Sport Center, Misamis Oriental | 1,815,358.02 | Misamis Oriental | NONE | N/A | N/A | April 27, 2023 | 49 Calendar Days | ||||||||||||||||
19 | 7 | 0786-23 | Construction of Water System in Zone 8 Poblacion, Opol, Misamis Oriental | 1,999,799.45 | Poblacio, Opol, Misamis Oriental | NONE | N/A | N/A | April 27, 2023 | 62 Calendar Days | ||||||||||||||||
20 | 8 | 0803-23 | One Unit Establishment of Milk Fish Nursery Compound MSU, Naawan, Misamis Oriental | 3,998,061.67 | Naawan, Misamis Oriental | NONE | N/A | N/A | April 27, 2023 | 152 Calendar Days | ||||||||||||||||
21 | 9 | 0789-23 | Renovation of Hospital Building and Landscaping of MOHP-Gingoog MOPH Gingoog, Misamis Oriental | 1,406,256.93 | Gingoog, Misamis Oriental | NONE | N/A | N/A | April 27, 2023 | 152 Calendar Days | ||||||||||||||||
22 | 10 | 0753-23 | Replacement of Concrete Pavement of Various Provincial Roads in Misamis Oriental | 37,000,000.00 | Misamis Oriental | NONE | N/A | N/A | April 27, 2023 | 140 Calendar Days | ||||||||||||||||
23 | 11 | 0788-23 | Renovation of Hospital and Landscaping of MOPH Balingasag, Misamis Oriental | 1,499,407.34 | Balingasag, Misamis Oriental | NONE | N/A | N/A | April 27, 2023 | 140 Calendar Days | ||||||||||||||||
24 | 12 | 0754-23 | Repair of X-Ray Room, MOPH-Claveria Poblacion, Misamis Oriental | 793,345.72 | Poblacion, Claveria, Misamis Oriental | NONE | N/A | N/A | April 27, 2023 | 25 Calendar Days | ||||||||||||||||
25 | 13 | 0948-23 | Construction of Child Development Center at Barangay Kabangasan, Balingoan, Misamis Oriental | 3,109,418.20 | Kabangasan, Balingoan, Misamis Oriental | NONE | N/A | N/A | May 4, 2023 | 126 Calendar Days | ||||||||||||||||
26 | 14 | 0941-23 | Renovation/Rehabilitation of Capitol Building/Structures and Premises, Misamis Oriental | 2,552,671.22 | Misamis Oriental | NONE | N/A | N/A | May 4, 2023 | 87 Calendar Days | ||||||||||||||||
27 | 15 | 0943-23 | MOGCHS Gate and Façade Rehabilitation, Misamis Oriental General Comprehensive High School, Cagayan de Oro City | 1,498,399.30 | Cagayan de Oro City | NONE | N/A | N/A | May 4, 2023 | 48 Calendar Days | ||||||||||||||||
28 | 16 | 0945-23 | Construction of Child Development Center at Digkilaan, Manticao, Misamis Oriental | 3,195,989.75 | Digkilaan, Manticao, Misamis Oriental | NONE | N/A | N/A | May 4, 2023 | 126 Calendar Days | ||||||||||||||||
29 | 17 | 0809-23 | Completion of Provincial Health Office Building at Capitol Compound, Cagayan de Oro City | 21,999,999.99 | Cagayan de Oro City | NONE | N/A | N/A | May 4, 2023 | 134 Calendar Days | ||||||||||||||||
30 | 18 | 0790-23 | Completion of the 58th Infantry Battalion Evaluation Center/Covered Court, Claveria, Misamis Oriental | 2,465,407.11 | Claveria, Misamis Oriental | NONE | N/A | N/A | May 4, 2023 | 131 Calendar Days | ||||||||||||||||
31 | 19 | 0784-23 | Expansion of Medical Records Building of MOPH-Balingasag, Balingasag, Misamis Oriental | 1,676,279.97 | Balingasag, Misamis Oriental | NONE | N/A | N/A | May 4, 2023 | 63 Calendar Days | ||||||||||||||||
32 | 20 | 0837-23 | Construction of Perimeter Fence PNP San Martin, Villanueva, Misamis Oriental | 8,994,651.00 | San Martin, Villanueva, Misamis Oriental | NONE | N/A | N/A | May 4, 2023 | 180 Calendar Days | ||||||||||||||||
33 | 21 | 0785-23 | Road Opening/Concreting Project in Zone 8, Barangay Poblacion, Misamis Oriental | 2,996,986.28 | Poblacion, Misamis Oriental | NONE | N/A | N/A | May 4, 2023 | 46 Calendar Days | ||||||||||||||||
34 | 22 | 0783-23 | Construction of Water Tank, Balay Kaugmaon Center, Claveria, Misamis Oriental | 1,049,896.37 | Claveria, Misamis Oriental | CLC CONSTRUCTION SERVICES & SUPPLY | N/A | 1,047,922.03 | May 4, 2023 | 40 Calendar Days | ||||||||||||||||
35 | 23 | 0672-23 | Improvement of Building Phase II Balay Kaugmaon, Poblacion, Claveria, Misamis Oriental | 1,582,816.18 | Poblacion, Claveria, Misamis Oriental | CLC CONSTRUCTION SERVICES & SUPPLY | N/A | 1,579,810.97 | May 4, 2023 | 78 Calendar Days | ||||||||||||||||
36 | 24 | 0963-23 | Ripraping of Elementary School, Barangay Lubilan, Naawan, Misamis Oriental | 1,009,410.45 | Lubilan, Naawan, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 34 Calendar Days | ||||||||||||||||
37 | 25 | 0949-23 | Construction of 2 Storey 4 Classroom School Building Blanco Elementary School, Balingasag, Misamis Oriental | 9,757,549.22 | Balingasag, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 195 Calendar Days | ||||||||||||||||
38 | 26 | 0946-23 | Construction of 2 Storey 4 Classroom School Building Natubo Integrated School, Jasaan, Misamis Oriental | 9,930,178.84 | Jasaan, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 196 Calendar Days | ||||||||||||||||
39 | 27 | 0947-23 | Construction of 2 Storey 4 Classroom School Building Rosario National High School, Tagoloan, Misamis Oriental | 10,418,072.33 | Tagoloan, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 166 Calendar Days | ||||||||||||||||
40 | 28 | 0952-23 | Construction of 2 Storey 4 Classroom School Building with Complete Facilities Kabangasan Elementary School, Balingoan, Misamis Oriental | 9,903,902.65 | Balingoan, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 196 Calendar Days | ||||||||||||||||
41 | 29 | 0942-23 | Construction of 2 Storey 4 Classroom School Building Silad Elementary School, Sugbongcogon, Misamis Oriental | 9,729,837.12 | Sugbongcogon, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 196 Calendar Days | ||||||||||||||||
42 | 30 | 0787-22 | Water Works System San Luis, Gingoog City, Misamis Oriental | 2,484,297.59 | Gingoog City, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 70 Calendar Days | ||||||||||||||||
43 | 31 | 0964-23 | Proposed Access Footbridge Poblacion, Villanueva, Misamis Oriental | 6,649,481.50 | Poblacion, Villanueva, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 110 Calendar Days | ||||||||||||||||
44 | 32 | 0967-23 | Construction of Concrete of Community Plaza Umagos, Lagonglong, Misamis Oriental | 1,197,784.53 | Lagonglong, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 62 Calendar Days | ||||||||||||||||
45 | 33 | 0951-23 | Construction of 2 Storey 4 Classroom School Building Digkilaan Elementary School, Manticao, Misamis Oriental | 10,057,721.30 | Manticao, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 196 Calendar Days | ||||||||||||||||
46 | 34 | 0950-23 | Construction of 2 Storey 4 Classroom School Building Tubajon Integrated School, Laguindingan, Misamis Oriental | 10,018,702.66 | Laguindingan, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 196 Calendar Days | ||||||||||||||||
47 | 35 | 0938-23 | Construction of 2 Storey 4 Classroom School Building Cauyunan Integrated School, Opol, Misamis Oriental | 10,785,262.24 | Opol, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 196 Calendar Days | ||||||||||||||||
48 | 36 | 0944-23 | Construction of 2 Storey 4 Classroom School Building Lubilan Integrated School, Naawan, Misamis Oriental | 10,063,653.31 | Naawan, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 196 Calendar Days | ||||||||||||||||
49 | 37 | 0810-23 | Renovation of White House Building Misamis Oriental Integrated Sport Center, Misamis Oriental | 1,815,358.02 | Misamis Oriental | EQUALYZ TRADING | N/A | 1,814,514.68 | May 11, 2023 | 49 Calendar Days | ||||||||||||||||
50 | 38 | 0786-23 | Construction of Water System in Zone 8 Poblacion, Opol, Misamis Oriental | 1,999,799.45 | Poblacio, Opol, Misamis Oriental | CAGALAWAN ENTERPRISES | N/A | 1,998,738.58 | May 11, 2023 | 62 Calendar Days | ||||||||||||||||
51 | 39 | 0803-23 | One Unit Establishment of Milk Fish Nursery Compound MSU, Naawan, Misamis Oriental | 3,998,061.67 | Naawan, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 152 Calendar Days | ||||||||||||||||
52 | 40 | 0789-23 | Renovation of Hospital Building and Landscaping of MOHP-Gingoog MOPH Gingoog, Misamis Oriental | 1,406,256.93 | Gingoog, Misamis Oriental | CAGALAWAN ENTERPRISES | N/A | 1,405,512.22 | May 11, 2023 | 152 Calendar Days | ||||||||||||||||
53 | 41 | 0753-23 | Replacement of Concrete Pavement of Various Provincial Roads in Misamis Oriental | 37,000,000.00 | Misamis Oriental | CAGALAWAN ENTERPRISES | N/A | 36,951,851.78 | May 11, 2023 | 140 Calendar Days | ||||||||||||||||
54 | 42 | 0789-23 | Renovation of Hospital Building and Landscaping of MOHP-Gingoog MOPH Gingoog, Misamis Oriental | 1,406,256.93 | Gingoog, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 152 Calendar Days | ||||||||||||||||
55 | 43 | 0754-23 | Repair of X-Ray Room, MOPH-Claveria Poblacion, Misamis Oriental | 793,345.72 | Poblacion, Claveria, Misamis Oriental | RAM DAAN CONSTRUCTION | N/A | 996,132.78 | May 11, 2023 | 25 Calendar Days | ||||||||||||||||
56 | 44 | 0791-23 | Improvement of BPO Office Building Provincial Budget Office, Capitol Building, Cagayan de Oro City | 272,644.49 | Capitol Building, Cagayan de Oro City | GEG BUILDERS | N/A | 267,265.50 | May 11, 2023 | 16 Calendar Days | ||||||||||||||||
57 | 45 | 0939-23 | Construction of Pathway from Gate to Covered Court Mat-I Central School, Mat-I, Claveria, Misamis Oriental | 996,752.26 | Mat-I, Claveria, Misamis Oriental | NONE | N/A | N/A | May 11, 2023 | 63 Calendar Days | ||||||||||||||||
58 | 46 | 1084-23 | Proposed Capitol Powerhouse, Capitol Compound, Cagayan de Oro City, Misamis Oriental | 2,568,213.67 | Cagayan de Oro City, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 60 Calendar Days | ||||||||||||||||
59 | 47 | 0940-23 | Construction of Tobacco Farmer's Multipurpose Building, Mat-I, Claveria, Misamis Oriental | 1,855,541.98 | Mat-I, Claveria, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 48 Calendar Days | ||||||||||||||||
60 | 48 | 0871-23 | Construction of Staff Building Sitio Daruca Poblacion, Claveria, Misamis Oriental | 1,999,906.03 | Poblacion, Claveria, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 96 Calendar Days | ||||||||||||||||
61 | 49 | 0937-23 | Completion of 58th Infantry Battalion Multi-Purpose Building 58th I.B, Claveria, Misamis Oriental | 1,475,640.09 | Claveria, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 62 Calendar Days | ||||||||||||||||
62 | 50 | 0965-23 | Rehabilitation/Renovation of De Lara Park, Provincial Capitol, Capitol Compound, Cagayan de Oro City | 1,494,763.11 | Capitol Compound, Cagayan de Oro City | NONE | N/A | N/A | May 18, 2023 | 52 Calendar Days | ||||||||||||||||
63 | 51 | 0966-23 | Construction of Covered Court Patag, Naawan, Misamis Oriental | 5,873,003.46 | Naawan, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 149 Calendar Days | ||||||||||||||||
64 | 52 | 0948-23 | Construction of Child Development Center at Barangay Kabangasan, Balingoan, Misamis Oriental | 3,109,418.20 | Kabangasan, Balingoan, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 126 Calendar Days | ||||||||||||||||
65 | 53 | 0941-23 | Renovation/Rehabilitation of Capitol Building/Structures and Premises, Misamis Oriental | 2,552,671.22 | Misamis Oriental | GEG BUILDERS | N/A | 2,527,488.24 | May 18, 2023 | 87 Calendar Days | ||||||||||||||||
66 | 54 | 0943-23 | MOGCHS Gate and Façade Rehabilitation, Misamis Oriental General Comprehensive High School, Cagayan de Oro City | 1,498,399.30 | Cagayan de Oro City | NONE | N/A | N/A | May 18, 2023 | 48 Calendar Days | ||||||||||||||||
67 | 55 | 0945-23 | Construction of Child Development Center at Digkilaan, Manticao, Misamis Oriental | 3,195,989.75 | Digkilaan, Manticao, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 126 Calendar Days | ||||||||||||||||
68 | 56 | 0809-23 | Completion of Provincial Health Office Building at Capitol Compound, Cagayan de Oro City | 21,999,999.99 | Cagayan de Oro City | EQUALYZ TRADING | N/A | 21,998,312.52 | May 18, 2023 | 134 Calendar Days | ||||||||||||||||
69 | 57 | 0790-23 | Completion of the 58th Infantry Battalion Evaluation Center/Covered Court, Claveria, Misamis Oriental | 2,465,407.11 | Claveria, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 131 Calendar Days | ||||||||||||||||
70 | 58 | 0784-23 | Expansion of Medical Records Building of MOPH-Balingasag, Balingasag, Misamis Oriental | 1,676,279.97 | Balingasag, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 63 Calendar Days | ||||||||||||||||
71 | 59 | 0837-23 | Construction of Perimeter Fence PNP San Martin, Villanueva, Misamis Oriental | 8,994,651.00 | San Martin, Villanueva, Misamis Oriental | EQUALYZ TRADING | N/A | 8,993,719.36 | May 18, 2023 | 180 Calendar Days | ||||||||||||||||
72 | 60 | 0785-23 | Road Opening/Concreting Project in Zone 8, Barangay Poblacion, Misamis Oriental | 2,996,986.28 | Poblacion, Misamis Oriental | NONE | N/A | N/A | May 18, 2023 | 46 Calendar Days | ||||||||||||||||
73 | 61 | 1062-23 | Construction of Perimeter Fence for the Barangay Property in Sitio El Mundo Natumolan, Barangay Natumolan, Tagoloan, Misamis Oriental | 808,648.59 | Natumolan, Tagoloan, Misamis Oriental | RAM DAAN CONSTRUCTION | N/A | 807,141.18 | May 18, 2023 | 45 Calendar Days | ||||||||||||||||
74 | 62 | 1086-23 | Rehabilitation of Child Development Center at Barangay Mintalao-Hinaplanan, Claveria, Misamis Oriental | 977,295.80 | Mintalao, Hinaplanan, Misamis Oriental | RAM DAAN CONSTRUCTION | N/A | 977,721.35 | May 18, 2023 | 49 Calendar Days | ||||||||||||||||
75 | 63 | 0963-23 | Ripraping of Elementary School, Barangay Lubilan, Naawan, Misamis Oriental | 1,009,410.45 | Lubilan, Naawan, Misamis Oriental | NONE | N/A | N/A | May 29, 2023 | 34 Calendar Days | ||||||||||||||||
76 | 64 | 0949-23 | Construction of 2 Storey 4 Classroom School Building Blanco Elementary School, Balingasag, Misamis Oriental | 9,757,549.22 | Balingasag, Misamis Oriental | EQUALYZ TRADING | N/A | 9,756,405.34 | May 29, 2023 | 195 Calendar Days | ||||||||||||||||
77 | 65 | 0946-23 | Construction of 2 Storey 4 Classroom School Building Natubo Integrated School, Jasaan, Misamis Oriental | 9,930,178.84 | Jasaan, Misamis Oriental | NONE | N/A | N/A | May 29, 2023 | 196 Calendar Days | ||||||||||||||||
78 | 66 | 0947-23 | Construction of 2 Storey 4 Classroom School Building Rosario National High School, Tagoloan, Misamis Oriental | 10,418,072.33 | Tagoloan, Misamis Oriental | RAM DAAN CONSTRUCTION | N/A | 10,419,880.38 | May 29, 2023 | 166 Calendar Days | ||||||||||||||||
79 | 67 | 0952-23 | Construction of 2 Storey 4 Classroom School Building with Complete Facilities Kabangasan Elementary School, Balingoan, Misamis Oriental | 9,903,902.65 | Balingoan, Misamis Oriental | TRI-FOLD CONSTRUCTION SERVICES | N/A | 9,851,157.13 | May 29, 2023 | 196 Calendar Days | ||||||||||||||||
80 | 68 | 0942-23 | Construction of 2 Storey 4 Classroom School Building Silad Elementary School, Sugbongcogon, Misamis Oriental | 9,729,837.12 | Sugbongcogon, Misamis Oriental | CAGALAWAN ENTERPRISES | N/A | 9,728,461.08 | May 29, 2023 | 196 Calendar Days | ||||||||||||||||
81 | 69 | 0787-22 | Water Works System San Luis, Gingoog City, Misamis Oriental | 2,484,297.59 | Gingoog City, Misamis Oriental | NONE | N/A | N/A | May 29, 2023 | 70 Calendar Days | ||||||||||||||||
82 | 70 | 0964-23 | Proposed Access Footbridge Poblacion, Villanueva, Misamis Oriental | 6,649,481.50 | Poblacion, Villanueva, Misamis Oriental | NONE | N/A | N/A | May 29, 2023 | 110 Calendar Days | ||||||||||||||||
83 | 71 | 0967-23 | Construction of Concrete of Community Plaza Umagos, Lagonglong, Misamis Oriental | 1,197,784.53 | Lagonglong, Misamis Oriental | EQUALYZ TRADING | N/A | 1,196,868.19 | May 29, 2023 | 62 Calendar Days | ||||||||||||||||
84 | 72 | 0951-23 | Construction of 2 Storey 4 Classroom School Building Digkilaan Elementary School, Manticao, Misamis Oriental | 10,057,721.30 | Manticao, Misamis Oriental | TRI-FOLD CONSTRUCTION SERVICES | N/A | 10,037,238.52 | May 29, 2023 | 196 Calendar Days | ||||||||||||||||
85 | 73 | 0950-23 | Construction of 2 Storey 4 Classroom School Building Tubajon Integrated School, Laguindingan, Misamis Oriental | 10,018,702.66 | Laguindingan, Misamis Oriental | BZAR CONSTRUCTION | N/A | 10,017,064.88 | May 29, 2023 | 196 Calendar Days | ||||||||||||||||
86 | 74 | 0938-23 | Construction of 2 Storey 4 Classroom School Building Cauyunan Integrated School, Opol, Misamis Oriental | 10,785,262.24 | Opol, Misamis Oriental | MIKKIL CONSTRUCTION | N/A | 10,784,768.90 | May 29, 2023 | 196 Calendar Days | ||||||||||||||||
87 | 75 | 0944-23 | Construction of 2 Storey 4 Classroom School Building Lubilan Integrated School, Naawan, Misamis Oriental | 10,063,653.31 | Naawan, Misamis Oriental | NONE | N/A | N/A | May 29, 2023 | 196 Calendar Days | ||||||||||||||||
88 | 76 | 1094-23 | Construction of Covered Court Barangay Alicomohan, Sugbongcogon, Misamis Oriental | 5,388,717.94 | Alicomohan, Sugbongcogon, Misamis Oriental | NONE | N/A | N/A | June 1, 2023 | 192 Calendar Days | ||||||||||||||||
89 | 77 | 1138-23 | Construction of OPD Building and Landscaping MOPH Claveria, Barangay Poblacion, Claveria, Misamis Oriental | 2,306,793.00 | Poblacion, Claveria, Misamis Oriental | NONE | N/A | N/A | June 1, 2023 | 78 Calendar Days | ||||||||||||||||
90 | 78 | 1084-23 | Proposed Capitol Powerhouse, Capitol Compound, Cagayan de Oro City, Misamis Oriental | 2,568,213.67 | Cagayan de Oro City, Misamis Oriental | EQUALYZ TRADING | N/A | 2,567,148.65 | June 1, 2023 | 60 Calendar Days | ||||||||||||||||
91 | 79 | 0940-23 | Construction of Tobacco Farmer's Multipurpose Building, Mat-I, Claveria, Misamis Oriental | 1,855,541.98 | Mat-I, Claveria, Misamis Oriental | ISRAEL MULTI-BUILDERS DEV'T CORP. | N/A | 1,850,970.70 | June 1, 2023 | 48 Calendar Days | ||||||||||||||||
92 | 80 | 0871-23 | Construction of Staff Building Sitio Daruca Poblacion, Claveria, Misamis Oriental | 1,999,906.03 | Poblacion, Claveria, Misamis Oriental | ISRAEL MULTI-BUILDERS DEV'T CORP. | N/A | 1,995,348.15 | June 1, 2023 | 96 Calendar Days | ||||||||||||||||
93 | 81 | 0937-23 | Completion of 58th Infantry Battalion Multi-Purpose Building 58th I.B, Claveria, Misamis Oriental | 1,475,640.09 | Claveria, Misamis Oriental | NONE | N/A | N/A | June 1, 2023 | 62 Calendar Days | ||||||||||||||||
94 | 82 | 0965-23 | Rehabilitation/Renovation of De Lara Park, Provincial Capitol, Capitol Compound, Cagayan de Oro City | 1,494,763.11 | Capitol Compound, Cagayan de Oro City | L & L CONSTRUCTION | N/A | 1,490,851.94 | June 1, 2023 | 52 Calendar Days | ||||||||||||||||
95 | 83 | 0966-23 | Construction of Covered Court Patag, Naawan, Misamis Oriental | 5,873,003.46 | Naawan, Misamis Oriental | TRI-FOLD CONSTRUCTION SERVICES | N/A | 5,870,518.81 | June 1, 2023 | 149 Calendar Days | ||||||||||||||||
96 | 84 | 1088-23 | Installation of Pipeline with Hog Pen Faucets- Communal, Kalawitan, Claveria, Misamis Oriental | 344,806.96 | Kalawitan, Claveria, Misamis Oriental | NONE | N/A | N/A | June 1, 2023 | 12 Calendar Days | ||||||||||||||||
97 | 85 | 0973-23 | Construction of Additional Communal Toilet at Sitio Tugas-Tugason, Purok 6, Blanco, Balingasag, Misamis Oriental | 243,655.61 | Blanco, Balingasag, Misamis Oriental | NONE | N/A | N/A | June 1, 2023 | 54 Calendar Days | ||||||||||||||||
98 | 86 | 0972-23 | Repair and Renovation of Communal Toilet at Sitio Tugas-Tugason, Purok 6, Blanco, Balingasag, Misamis Oriental | 509,579.37 | Blanco, Balingasag, Misamis Oriental | FJQ CONSTRUCTION | N/A | 2,567,148.65 | June 1, 2023 | 53 Calendar Days | ||||||||||||||||
99 | 87 | 1139-23 | Improvement of Barangay Hall Stage, Barangay Matangad, Gitagum, Misamis Oriental | 844,485.89 | Matangad, Gitagum, Misamis Oriental | E & P BUILDERS | N/A | 841,576.18 | June 1, 2023 | 34 Calendar Days | ||||||||||||||||
100 | 88 | 1272-23 | Improvement of Water System Barangay Taytay, El Salvador City, Misamis Oriental | 1,009,657.69 | Taytay, El Slavador City, Misamis Oriental | NONE | N/A | N/A | June 16, 2023 | 29 Calendar Days | ||||||||||||||||