3 | DIVISION | SECTOR | name of the road | DATE | BT | MT | SH | FW | Upload time | Remarks | Status | Expandture | Value of Work Done | |||||||||||
4 | Kulgam | CnT | xenkul98@gmail.com | Macadamization of D K Marg to Sarmarg road | 19-07-2022 | 0.5 | 19/07/2022 11:03:50 | In Progress | ||||||||||||||||
5 | Kulgam | CnT | xenkul98@gmail.com | Macadamization of Arrah to Padderpora including Link Reshi mohalla Chirbagh. | 19-07-2022 | 1 | 19/07/2022 11:03:05 | In Progress | ||||||||||||||||
6 | Ganderbal | NABARD | rnbganderbal786@gmail.com | Strengthening/upgradation of inner roads at Lar Town | 17-07-2022 | 2.3 | 18/07/2022 21:39:12 | In Progress | ||||||||||||||||
7 | Ganderbal | CnT | rnbganderbal786@gmail.com | Nuner Urpash main road and Inner links at urpash Shajnag | 15-07-2022 | 0.25 | 18/07/2022 21:37:03 | In Progress | ||||||||||||||||
8 | Ganderbal | CnT | rnbganderbal786@gmail.com | Inner links of Badampora incl. link road from Govt. middle School to main road Badampora | 14-07-2022 | 1 | 18/07/2022 21:36:14 | Physically Completed | ||||||||||||||||
9 | Ganderbal | CnT | rnbganderbal786@gmail.com | Narayanbagh shadipora Bridge road, incl inner links of Khanpora-Wakura | 06-07-2022 | 0.5 | 18/07/2022 21:35:26 | In Progress | ||||||||||||||||
10 | Ganderbal | CnT | rnbganderbal786@gmail.com | PHC Ganiwan link road including NHW to Jarapati Road | 17-07-2022 | 1 | 18/07/2022 21:34:05 | Physically Completed | ||||||||||||||||
11 | Ganderbal | CnT | rnbganderbal786@gmail.com | National Highway to mammer road incl. allied links | 16-07-2022 | 1 | 18/07/2022 21:33:29 | Physically Completed | ||||||||||||||||
12 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation of road from Nowdal to Dadsara via Naibugh | 20-06-2022 | 2 | 2 | 0 | 0 | 20/06/2022 00:06:21 | In Progress | |||||||||||||
13 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation of IR Rahmoo, Romreshi Chewa Kalan, Wani Mohalla roads | 20-06-2022 | 3.9 | 3.9 | 0 | 0 | 20/06/2022 05:01:51 | In Progress | |||||||||||||
14 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation / Improvement of Drabgam Iyengund road including interior roads of Drabgam | 14-06-2022 | 2 | 6 | 0 | 0 | 14/06/2022 04:08:09 | In Progress | |||||||||||||
15 | Pulwama | NABARD | techrbpul786@gmail.com | Construction of Khrew to Bad Dalow road | 23-06-2022 | 3.8 | 23/06/2022 02:04:51 | |||||||||||||||||
16 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation / Strengthening of Midoora Rajpora road including IR Midoora & CRPF Camp Road | 23-06-2022 | 0.5 | 23/06/2022 05:32:28 | |||||||||||||||||
17 | Tangdar | CRIF | xenssdtdr@gmail.com | Construction of road from Tangdar to Gabra via Hajitra | 27-06-2022 | 0 | 0 | 0 | 0 | 27/06/2022 08:17:23 | ||||||||||||||
18 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation / Improvement of Drabgam Iyengund road including interior roads of Drabgam | 27-06-2022 | 2 | 27/06/2022 05:00:26 | In Progress | ||||||||||||||||
19 | Tangdar | CRIF | xenssdtdr@gmail.com | Construction/upgradation of Dhani Tadd upto Paradda Pandov including Surmapadi road | 26-06-2022 | 1 | 1 | 1 | 1 | 26/06/2022 00:19:48 | In Progress | |||||||||||||
20 | Khanabal | CRIF | xenrnbkhanabal@gmail.com | Upgradation of Seer Hapatnar Ashmuqam road | 28-06-2022 | 0 | 0 | 0 | 0 | 28/06/2022 03:57:18 | ||||||||||||||
21 | Khanabal | CRIF | xenrnbkhanabal@gmail.com | Upgrd of road from Sangam to Serigufwara via Khiram | 16-06-2022 | 2.4 | 2.4 | 0 | 0 | 28/06/2022 05:24:45 | In Progress | |||||||||||||
22 | Khanabal | CRIF | xenrnbkhanabal@gmail.com | Upgrd of Khanabal Pahalgam road from Km 14.50 to Km 43rd (Seer Hamdan to Pahalgam 28.50 Kms) | 14-06-2022 | 0.3 | 0.3 | 0 | 0 | 28/06/2022 02:42:07 | In Progress | |||||||||||||
23 | Khanabal | CRIF | xenrnbkhanabal@gmail.com | Widening/upgradaton of Pahalgam Aaroo road | 28-06-2022 | 0 | 0 | 2 | 6 | 28/06/2022 05:39:42 | ||||||||||||||
24 | Pulwama | NABARD | techrbpul786@gmail.com | Construction of Khrew to Bad Dalow road | 28-06-2022 | 1 | 28/06/2022 06:57:26 | In Progress | ||||||||||||||||
25 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of interior Road Pulwama for aggr.length 3 km incl. approach roads leading to Covid-19 Hospital and IR of District Hospital Pulwama for 1.5 km and DPL | 27-06-2022 | 1.1 | 1.1 | 27/06/2022 06:36:09 | In Progress | |||||||||||||||
26 | Pulwama | CnT | techrbpul786@gmail.com | Rawatpora Nikloora road | 26-06-2022 | 0.7 | 0.7 | 26/06/2022 01:27:04 | In Progress | |||||||||||||||
27 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of Interior roads of Chandgam for 0.8 km and Macadamization of Wahipora Yadder road for 0.5 km | 27-06-2022 | 0.45 | 27/06/2022 09:33:23 | In Progress | ||||||||||||||||
28 | Pulwama | CnT | techrbpul786@gmail.com | Interior roads of Beighpora and Gulzarpora" | 26-06-2022 | 0.73 | 0.33 | 26/06/2022 01:18:56 | In Progress | |||||||||||||||
29 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of Chandpora Iyengund Pachar for 1.0 km and Macadamization of Putrigam Kachipora road for 1.0 km resp. | 28-06-2022 | 0.5 | 28/06/2022 01:12:37 | In Progress | ||||||||||||||||
30 | Budgam | NABARD | xenrnbdivbud@gmail.com | Restoration/upradation of Budgam Mamath Handjan road including allied links | 29-06-2022 | 2 | 2 | 0 | 0 | 29/06/2022 08:04:31 | In Progress | |||||||||||||
31 | Budgam | NABARD | xenrnbdivbud@gmail.com | Upgradation of Chandpora Labertal Dandina road including Alamdar and link | 29-06-2022 | 1.5 | 1.5 | 0 | 0 | 29/06/2022 03:39:49 | In Progress | |||||||||||||
32 | Tangdar | CnT | xenssdtdr@gmail.com | Prada Amrohi Road | 25-06-2022 | 6 | 0 | 0 | 0 | 25/06/2022 06:06:38 | In Progress | |||||||||||||
33 | Bandipora | CnT | xenrnbbandipora@gmail.com | Sopore Bnadipora -- Phase 2nd | 28-06-2022 | 0.85 | 28/06/2022 06:59:24 | In Progress | ||||||||||||||||
34 | Budgam | NABARD | xenrnbdivbud@gmail.com | Upgradation of Hamchipora Pethsharah road via Village Trappy including Labrain link | 29-06-2022 | 2 | 2 | 0 | 0 | 29/06/2022 08:38:56 | In Progress | |||||||||||||
35 | Magam-Tangmarg | CRIF | xenrnbmagam0006@gmail.com | Upgradation from Dobiwan to Zandpal via Hardaboora Checkfrestreshi Kharpora Naidcheck Phase 1st | 05-06-2022 | 1.2 | 29/06/2022 02:20:54 | In Progress | ||||||||||||||||
36 | Magam-Tangmarg | NABARD | xenrnbmagam0006@gmail.com | Upgradation of Mangloora Yall road via Kachama | 06-06-2022 | 1.3 | 29/06/2022 02:47:25 | In Progress | ||||||||||||||||
37 | Magam-Tangmarg | NABARD | xenrnbmagam0006@gmail.com | Upgradation of Kongamdara Batakcheck road (Kharikhan Check) including inner links Kongamdara | 07-06-2022 | 3.9 | 29/06/2022 01:23:20 | In Progress | ||||||||||||||||
38 | Bandipora | CnT | xenrnbbandipora@gmail.com | Approach Road Ledaing to District Police Lines from Bridge | 28-06-2022 | 1.1 | 28/06/2022 03:28:49 | In Progress | ||||||||||||||||
39 | Bandipora | CnT | xenrnbbandipora@gmail.com | Naz Colony Sector A, B | 28-06-2022 | 0.95 | 28/06/2022 05:58:26 | In Progress | ||||||||||||||||
40 | Bandipora | CnT | xenrnbbandipora@gmail.com | Bandipora Town -- Phase 2nd viz Roads Naz Colony/Dub Mohalla Ward No. 2 | 28-06-2022 | 0.9 | 28/06/2022 09:23:15 | In Progress | ||||||||||||||||
41 | Budgam | CnT | xenrnbdivbud@gmail.com | Upgradation of Ustad Mohalla link incl. Asthan Bagh, Fund Office & Haknipora Links of Budgam Hqr , Housing Colony Ompora SIDCO gate (LHS), Imptt of inner Links at Humhama , Rehan Clony, Fitratabad | 28-06-2022 | 1.85 | 0 | 0 | 0 | 28/06/2022 07:30:11 | In Progress | |||||||||||||
42 | Budgam | CnT | xenrnbdivbud@gmail.com | Khudpora Potnard at kachwari | 29-06-2022 | 0.5 | 0 | 0 | 0 | 29/06/2022 09:25:00 | In Progress | |||||||||||||
43 | Budgam | CnT | xenrnbdivbud@gmail.com | Bugroo Doodpathri road incl. Yarikhah Mir Mohalla Sheikh Mohalla , Yarikhah Bugchill Talapora road | 29-06-2022 | 0.25 | 0 | 0 | 0 | 29/06/2022 09:05:46 | In Progress | |||||||||||||
44 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Up-gradation of Narbal Tangmarg road | 08-06-2022 | 3.9 | 29/06/2022 05:35:25 | In Progress | ||||||||||||||||
45 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Upgradation of sheikhpora salamdeedor road | 09-06-2022 | 0.89 | 29/06/2022 04:25:23 | In Progress | ||||||||||||||||
46 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Baharampora link road | 10-06-2022 | 1.2 | 29/06/2022 01:59:21 | In Progress | ||||||||||||||||
47 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Check charathram to Bonshoora via Bewa raod incl. check link | 11-06-2022 | 1.3 | 29/06/2022 08:04:05 | In Progress | ||||||||||||||||
48 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Katipora Kampora incl Solinda link | 12-06-2022 | 0.1 | 29/06/2022 04:19:54 | In Progress | ||||||||||||||||
49 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Ziren Hajibal from Km 4th onwards | 13-06-2022 | 0.75 | 29/06/2022 00:25:00 | In Progress | ||||||||||||||||
50 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Dobiwan Lalpora road Balance part | 14-06-2022 | 1 | 29/06/2022 07:22:19 | In Progress | ||||||||||||||||
51 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Waripora Main road | 15-06-2022 | 0.8 | 29/06/2022 06:29:35 | In Progress | ||||||||||||||||
52 | Pulwama | NABARD | techrbpul786@gmail.com | Construction of Khrew to Bad Dalow road | 28-06-2022 | 0.2 | 0.3 | 28/06/2022 08:40:55 | In Progress | |||||||||||||||
53 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation / Improvement of Drabgam Iyengund road including interior roads of Drabgam | 28-06-2022 | 0.5 | 0.3 | 28/06/2022 01:51:58 | In Progress | |||||||||||||||
54 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Dobiwan to Barzulla Adda incl inner links of Sheikhul alm Colony | 16-06-2022 | 1.2 | 29/06/2022 08:46:57 | In Progress | ||||||||||||||||
55 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Tangmarg Gulmarg Road Km 01 to03 | 17-06-2022 | 1.6 | 29/06/2022 06:13:41 | In Progress | ||||||||||||||||
56 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Reram to Narikhar road | 18-06-2022 | 0.9 | 29/06/2022 06:11:41 | In Progress | ||||||||||||||||
57 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Inner links at Hardsoora | 19-06-2022 | 0.35 | 29/06/2022 03:59:57 | In Progress | ||||||||||||||||
58 | Chadoora | LANGUISHING | xenrnbchd@gmail.com | Completion of Alamdar road from Hapatnar to Chrarisharief | 29-06-2022 | 2 | 2 | 29/06/2022 02:32:42 | In Progress | |||||||||||||||
59 | Chadoora | NABARD | xenrnbchd@gmail.com | Restoration/upgradation of Kolibagh road taking off from Repora Zuhama Azad road | 29-06-2022 | 2 | 2 | 2 | 29/06/2022 07:57:56 | In Progress | ||||||||||||||
60 | Magam-Tangmarg | CnT | xenrnbmagam0006@gmail.com | Chukar Dandora link | 20-06-2022 | 1.25 | 29/06/2022 05:31:23 | In Progress | ||||||||||||||||
61 | Pulwama | CRIF_LANGUISHING | techrbpul786@gmail.com | Widening/upgragation Pulwama Rahmoo road inctuding Putwama Rajpora Shadimarg road | 30-06-2022 | 3 | 0.2 | 30/06/2022 05:14:49 | In Progress | |||||||||||||||
62 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of interior Road Pulwama for aggr.length 3 km incl. approach roads leading to Covid-19 Hospital and IR of District Hospital Pulwama for 1.5 km and DPL | 29-06-2022 | 0.5 | 0.5 | 29/06/2022 04:12:55 | In Progress | |||||||||||||||
63 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of Interior roads of Chandgam for 0.8 km and Macadamization of Wahipora Yadder road for 0.5 km | 29-06-2022 | 0.5 | 0.5 | 29/06/2022 02:24:42 | In Progress | |||||||||||||||
64 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of nterior roads of Kakapora for 1.00 km and Macadamization of IR of Lelhara for 1.00 km | 28-06-2022 | 0.1 | 0.4 | 28/06/2022 03:08:15 | In Progress | |||||||||||||||
65 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of Chandpora Iyengund Pachar for 1.0 km and Macadamization of Putrigam Kachipora road for 1.0 km resp. | 29-06-2022 | 0.75 | 0.2 | 29/06/2022 08:36:13 | In Progress | |||||||||||||||
66 | Pulwama | CRIF_LANGUISHING | techrbpul786@gmail.com | Widening/upgragation Pulwama Rahmoo road inctuding Putwama Rajpora Shadimarg road | 27-06-2022 | 3 | 27/06/2022 02:24:40 | In Progress | ||||||||||||||||
67 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation / Improvement of Drabgam Iyengund road including interior roads of Drabgam | 30-06-2022 | 1 | 1 | 30/06/2022 06:07:51 | In Progress | |||||||||||||||
68 | Ganderbal | NABARD | rnbganderbal786@gmail.com | Upgrd of Guzhama Batwani Dab-Batpora and Waskura road | 29-06-2022 | 2.3 | 30/06/2022 02:06:01 | In Progress | ||||||||||||||||
69 | Ganderbal | NABARD | rnbganderbal786@gmail.com | Improvement/ugprd of Watlar linkr oads at Lar Ganderbal | 28-06-2022 | 3 | 3 | 30/06/2022 02:52:53 | In Progress | |||||||||||||||
70 | Ganderbal | NABARD | rnbganderbal786@gmail.com | Strengthening/upgradation of inner roads at Lar Town | 27-06-2022 | 1 | 1 | 30/06/2022 08:44:18 | In Progress | |||||||||||||||
71 | Ganderbal | NABARD | rnbganderbal786@gmail.com | Strengthening/upgradation of inner roads at Waheedpora | 26-06-2022 | 3.8 | 3.8 | 30/06/2022 05:01:24 | In Progress | |||||||||||||||
72 | Chadoora | CnT | xenrnbchd@gmail.com | Road from Masjid Milat to Aribagh RD 0 TO 1500 | 29-06-2022 | 0 | 0.65 | 29/06/2022 02:09:30 | ||||||||||||||||
73 | Chadoora | CnT | xenrnbchd@gmail.com | Khanday colony Nowgam and SK bagh link road RD 0 to 1800 | 29-06-2022 | 0.55 | 0.55 | 29/06/2022 02:01:16 | In Progress | |||||||||||||||
74 | Chadoora | CnT | xenrnbchd@gmail.com | Road from Masjid Milat to Aribagh RD 0 TO 1500 | 29-06-2022 | 0.74 | 29/06/2022 09:32:12 | In Progress | ||||||||||||||||
75 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of town roads of Awantipora | 30-06-2022 | 0.8 | 30/06/2022 06:50:15 | |||||||||||||||||
76 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of nterior roads of Kakapora for 1.00 km and Macadamization of IR of Lelhara for 1.00 km | 30-06-2022 | 0.3 | 0.6 | 30/06/2022 01:36:27 | In Progress | |||||||||||||||
77 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of interior Road Pulwama for aggr.length 3 km incl. approach roads leading to Covid-19 Hospital and IR of District Hospital Pulwama for 1.5 km and DPL | 30-06-2022 | 0.4 | 0.45 | 30/06/2022 07:11:36 | In Progress | |||||||||||||||
78 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of Interior roads of Chandgam for 0.8 km and Macadamization of Wahipora Yadder road for 0.5 km | 30-06-2022 | 0.29 | 0.29 | 30/06/2022 00:34:00 | In Progress | |||||||||||||||
79 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of Chandpora Iyengund Pachar for 1.0 km and Macadamization of Putrigam Kachipora road for 1.0 km resp. | 30-06-2022 | 0.3 | 30/06/2022 02:56:42 | |||||||||||||||||
80 | Tangdar | NABARD | xenssdtdr@gmail.com | Construction of Dildar Karama Road vial Village Batilyan Km 4 to 7 | 01-07-2022 | 0 | 2 | 01/07/2022 09:16:20 | ||||||||||||||||
81 | Pulwama | NABARD | techrbpul786@gmail.com | Upgradation / Improvement of Drabgam Iyengund road including interior roads of Drabgam | 01-07-2022 | 0.5 | 0.5 | 01/07/2022 01:41:33 | In Progress | |||||||||||||||
82 | Pulwama | CRIF_LANGUISHING | techrbpul786@gmail.com | Widening/upgragation Pulwama Rahmoo road inctuding Putwama Rajpora Shadimarg road | 01-07-2022 | 0.3 | 01/07/2022 02:53:20 | |||||||||||||||||
83 | Pulwama | NABARD | techrbpul786@gmail.com | Construction of Khrew to Bad Dalow road | 01-07-2022 | 0.8 | 01/07/2022 08:45:01 | In Progress | ||||||||||||||||
84 | Ganderbal | CnT | rnbganderbal786@gmail.com | Improvement/Upgradation of road from NH to Community Centre Manigam incl. Nagrazo link. | 24-06-2022 | 0.81 | 0.81 | 30/06/2022 04:15:16 | In Progress | |||||||||||||||
85 | Ganderbal | CnT | rnbganderbal786@gmail.com | Sheikhul Alam Lane No.1 incl. sub Lanes at Pandach upto Hakeem residence. | 21-06-2022 | 0.8 | 0.8 | 30/06/2022 09:20:14 | In Progress | |||||||||||||||
86 | Ganderbal | CnT | rnbganderbal786@gmail.com | Dursuma Main road to Hospital & Tantray Mohallaincl. allied links | 22-06-2022 | 1 | 1 | 30/06/2022 02:23:17 | In Progress | |||||||||||||||
87 | Ganderbal | CnT | rnbganderbal786@gmail.com | Beehama to Wayil km 4 to km7 incl. Jamia MAsjid link road at Wayil incl allied links | 30-06-2022 | 1.61 | 1.61 | 30/06/2022 07:30:24 | In Progress | |||||||||||||||
88 | Ganderbal | NABARD | rnbganderbal786@gmail.com | Upgrd of Guzhama Batwani Dab-Batpora and Waskura road | 01-07-2022 | 0.4 | 0.4 | 01/07/2022 04:57:57 | In Progress | |||||||||||||||
89 | Ganderbal | CnT | rnbganderbal786@gmail.com | Fishries Deptt Rangil via Grid station upto Sher Baba Ziyarat Sharief, incl. Nagbal Chowk via Rangil upto Darul Uloom | 30-06-2022 | 1 | 1 | 30/06/2022 01:09:08 | In Progress | |||||||||||||||
90 | Ganderbal | CnT | rnbganderbal786@gmail.com | Pandach to Gulab Bagh | 18-06-2022 | 0.7 | 0.7 | 30/06/2022 06:24:19 | In Progress | |||||||||||||||
91 | Vailoo | NABARD | executiveengineerrnbdiv.vailoo@gmail.com | Construction / Upgradation of Ashram road including Links at Ashram (Agg length 1.00 Kms) | 15-07-2022 | 0 | 17/07/2022 00:28:54 | |||||||||||||||||
92 | Vailoo | NABARD | executiveengineerrnbdiv.vailoo@gmail.com | Construction / Upgradation of Pushroo Waldraman road (Agg length 2.00 Kms) | 14-07-2022 | 0 | 17/07/2022 02:21:19 | |||||||||||||||||
93 | Vailoo | NABARD | executiveengineerrnbdiv.vailoo@gmail.com | Construction / Upgrdation of inertior link roads of Cherapora | 17-07-2022 | 0 | 17/07/2022 01:40:19 | |||||||||||||||||
94 | Vailoo | NABARD | executiveengineerrnbdiv.vailoo@gmail.com | Construction of Deethu Sonach road | 13-07-2022 | 0 | 17/07/2022 02:32:18 | |||||||||||||||||
95 | Vailoo | CRIF_LANGUISHING | executiveengineerrnbdiv.vailoo@gmail.com | Construction of road along old Brengi Canal | 09-07-2022 | 0 | 0 | 0 | 0 | 17/07/2022 01:59:16 | ||||||||||||||
96 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of nterior roads of Kakapora for 1.00 km and Macadamization of IR of Lelhara for 1.00 km | 01-07-2022 | 0.2 | 0.2 | 01/07/2022 01:16:12 | In Progress | |||||||||||||||
97 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of town roads of Awantipora | 01-07-2022 | 0.2 | 01/07/2022 04:28:23 | In Progress | ||||||||||||||||
98 | Bandipora | CRIF_LANGUISHING | xenrnbbandipora@gmail.com | Impvt/upgrd of Athwatoo Bunkote Sonawair road | 04-07-2022 | 0.45 | 2.8 | 04/07/2022 04:59:19 | In Progress | |||||||||||||||
99 | Pulwama | CnT | techrbpul786@gmail.com | Macadamization of Iqbal colony road at Tumlahal incl. Ziyarat Sharif link road for 0.7 km and Mac. of main road to Chandipora for 0.4 km | 01-07-2022 | 0.3 | 0.15 | 01/07/2022 04:58:25 | In Progress | |||||||||||||||
100 | Ganderbal | NABARD | rnbganderbal786@gmail.com | Strengthening/upgradation of inner roads at Lar Town | 04-07-2022 | 0.6 | 04/07/2022 08:39:49 | In Progress |