CCTT/TT Meetings Action Log (last updated 7 April 2023)
2
2915
3
ActionDate Raised ActioneeOpen/Closed (as noted by CCTT FEB23)CommentTram Team ResponseNew Status (as noted by TTN MAR23)CCTT Comment on new status
7
Tram traffic modelling - provide responses and final modeling resultsFeb-21TT/SJOpenList of questions regarding modelling TBD March meetingOpen
12
Noise and vibration impact of traffic on diversion streets - investigate and report backApr-21TT/RAOpenTBD March meetingOpen
18
Access to APOG minutes - investigate and report backMay-21TT/CWOpenTBD March meetingOpen
19
Traffic modelling - arrange presentation of resultsAug-21TT/SJ/RAOpenAlso raised at Sept 2021, Oct 2021, Nov 2021 and May 2022 meetingsTBD March meetingOpenSuggest close as duplicate action
20
Issue final drawings of public realm along Trams routeSep-21TT/RLOpenAlso raised at November 2021 meetingLandscaping drawings are on the ETYN websiteClosedAgreed complete - this action related to the distribution of hard copy versions of plans which has been completed
21
TRO Melrose Drive junction - raise traffic management concerns with TMRPSep-21TT/RAOpenCompleted and no concerns from TMRP, LB or emergency servicesClosedAgreed complete - do you have a date or confirmation that these concerns were included in approval of TRO?
22
Noise and Vibration surveys - arrange for CCTT to meet with ETSep-21TT/RLOpenTo be arranged once operations plannedTBD March meetingOpen
26
Width of loading bays along Leith Walk - provide technical note justifying designs Oct-21TT/RAOpenPreviously providedClosedAgreed complete - are you able to provide copy of the technical note?
27
Pavement widths - provide table for Leith Links areaOct-21TT/RAOpenNote issued showing where pavements were less than 2m wide for whole routeFootpath widths attachedClosedAgreed complete
28
Provide list of planned repairs of potholes and other damage to diversion routesOct-21TT/RAOpenIncorrecty shown in the minutes to be actioned by CC/MBCEC Roads team and can be reported via usual routes on CEC websiteClosedDo not agree that this can be closed. There was an action on RA to compile list based on reports submiutted to trams team
29
Need to establish register of legacy issuesFeb-22TT/RLOpenCCTT TrackerClosedDo not agree that this can be closed. Has CCTT tracker been populated?
32
Confirm location/design of communal bin hubs within Tram project boundariesApr-22TT/RAOpenProvided to HT previously and hub locations on landscaping plans on ETYN websiteClosedAgreed complete
33
Contact BT to seek improvements toretained phone boxesApr-22CC/HTOpenPhone boxes removed as part of site clearanceClosedAgreed complete - do we have a list of the phone boxes that wil be removed and those that will be retained?
34
Clarify agreed design for active travel elements of Trams projectMay-22TT/RAOpenMore detail required to answer questionOpenSuggest close unless further detail can be provided
36
Location of planned bus shelters along the route - provide drawings Jul-22TT/RAOpenAlso raised at October and December 2022 meetingsDrawings providedClosedAgreed complete
37
Commitments Register - provide copy and dashboard when available Sep-22TT/RLOpenAdvised by RL at Oct 2022 meeting this was still outstanding. Update provided at Nov 2022 meeting TBD March meetingOpen
38
Bus Shelter at Croall Place - provide details for location decision Sep-22TT/RAOpen
Response given does not provide requested detail
Response previously provided and does not change, location agreed with Public Transport and JCDClosedAgreed complete
39
Follow up with Lothian Buses regarding delays to buses in LeithOct-22CC/HTOpen
CCTT to raise issues direct with Lothian Busses
OpenSuggest close as no further action from TT expected
40
Confirm location of trees in planters along the Trams route during walk throughsOct-22CCTT/TTOpenTBD March meetingOpen
41
Confirm schedule for handover of sections of Trams routeOct-22TT/RAOpenSC2 providedClosedDo not agree that this can be closed. The original schedule for SC2 handover has not been met. Do you have an updated schedule?
42
Improve reporting of quality issues and their closureOct-22TT/RAOpenIncluded on dashboardClosedAgreed complete
43
Arrange walk throughs of Trams Routes with CC membersOct-22TT/RAOpenNTBCC, LHNCC and LCCC complete Completed last yearClosedAgreed complete
44
Provide response to the isues highlighted in walk throughsNov-22TT/RAOpenAlso raised at December 2022 meeting. Response provided to be discussed at March 2023 meeting CompletedOpenSuggest close as final CCTT comment now provided
45
Contact CEC Lighting regarding lack of lighting on Ocean DriveDec-22TT/RAOpen
Completed - ETYN street lighting installation ongoing
ClosedDo not agree that this can be closed. CC/JM to provide additional detail
46
Provide copy of TT response to Road Safety Audit (and if possible the RSA)Dec-22TT/RAOpenTBD March MeetingOpen
47
Provide summary fo discussions from meeting about defect management, etc. Dec-22CC/HTOpenTBD March MeetingOpen
48
Follow up with Lothian Buses regarding continued use of diversionsDec-22TT/RLOpenCompletedOpenSuggest close as no further action from TT expected
49
Include reporting of hard landscaping progress in CCTT reportsDec-22TT/CWOpenTBD March meetingOpen
50
Provide copy of Commitments Register Feb-23TT/RAOpen
RL/TT to determine if GDPR would prevent sharing register
Open
51
Improve reporting of progress on landscaping work on dashboard Feb-23TT/CWOpen TBD March meetingOpen Suggest close as duplicate action
52
Arrange lessons learned meeting for CCTT members Feb-23
TT/RL, CC HT
Open TBD March meetingOpen Doodle poll to be issued to confirm date for lessons learned meeting
53
Issue overall timeline for Project showing key milestonesFeb-23TT/CWOpen TBD March meetingOpen Suggest close: timeline provided by Rob Leech by email
54
Investigate options for mitigation of "Authority to Work" costs Feb-23TT/CWOpen TBD March meetingOpen Suggest close as no further action from TT expected
55
Provide update on progress of section completion handoversFeb-23TT/RAOpen SC2 providedClosedDo not agree that this can be closed. The original schedule for SC2 handover has not been met. Do you have an updated schedule?
56
Check reasons for missing lights on some OLE polesMar-23TT/RAOpen
57
Investigate track slab mastic issuesMar-23TT/SJOpen
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118