0. OVERVIEW
2
PROJECT PHASEELEMENTSOWNER(S)LOCATION
3
1Setup & Admin
Secure necessary approvals and setup all systems and logistics for the project
Project code createdStaffing Manager10K
4
Lock budget Project Principal, Lead and Manager
5
Project folders (Dropbox and Drive) set up with naming conventionProject ManagerDropbox - 06 Projects
Google Drive
6
Project code entered for expensesFinanceNexonia
7
If required, partner / client deck templateProject ManagerFrom client, saved on Dropbox
8
2Internal Kickoff
Convene the full project team for briefing and alignment on the project, roles, and work plan
Project Background Briefing:
Partner / Client (org overall and contacts)
Issue
Project Scope
Budget & Work Plan
Full Team, led by Project Principal and Project ManagerInternal Kickoff Meeting
9
Team Composition:
Roles, Allocation, Expertise, PD Goals
Norms/Styles
Meeting Schedule
Flag any planned PTO
Special Internal Goals: IP, BD, Issue Areas, Racial Equity
Full Team, led by Project Principal and Project ManagerInternal Kickoff Meeting
10
Project Goals/Client Success:
Identify purpose and opportunities connected to the work (for later reference in client kickoff deck)
Full Team, led by Project Principal and Project ManagerInternal Kickoff Meeting
11
3External Kickoff
Convene the client and full Purpose team to formally kick off the project, re-align on key aspects of the SOW, and align on how Purpose and the client will work together moving forward
Team Introduction:
Who and roles, areas of expertise as applicable
Deck led by Project Manager with
work/input/meeting attendance from relevant team lead(s) providing key input (e.g. project principal, strategy lead, campaigns lead etc.)
Client Kickoff meeting
Client Kickoff deck on Dropbox
12
Define project success: From internal kickoff, align on what project success looks like as a group. Purpose brings our perspective and solicits client's input and feedbackDeck led by Project Manager with
work/input/meeting attendance from relevant team lead(s) providing key input (e.g. project principal, strategy lead, campaigns lead etc.)
Client Kickoff meeting
Client Kickoff deck on Dropbox
13
Workplan: Timeline and key deliverables, and likely more detailed workplan on first workstreamDeck led by Project Manager with
work/input/meeting attendance from relevant team lead(s) providing key input (e.g. project principal, strategy lead, campaigns lead etc.)
Client Kickoff meeting
Client Kickoff deck on Dropbox
14
Logistics: Align on check-in cadence, key decision-makers, review/presenting preferences (depending on the client, may be done separately)Deck led by Project Manager with
work/input/meeting attendance from relevant team lead(s) providing key input (e.g. project principal, strategy lead, campaigns lead etc.)
Client Kickoff meeting
Client Kickoff deck on Dropbox
15
Initial project conversation: If appropriate, use the opportunity to begin work on key initial project questions with key client stakeholders (can range from aligning on key stakeholders for interviews to going into deeper questions about their mission and goals)Deck led by Project Manager with
work/input/meeting attendance from relevant team lead(s) providing key input (e.g. project principal, strategy lead, campaigns lead etc.)
Client Kickoff meeting
Client Kickoff deck on Dropbox
16
Key next stepsDeck led by Project Manager with
work/input/meeting attendance from relevant team lead(s) providing key input (e.g. project principal, strategy lead, campaigns lead etc.)
Client Kickoff meeting
Client Kickoff deck on Dropbox
17
4Mid-project check-inReview how finances are evolving, how the team is doing, map out renewal possibilitiesProject Principal, Lead and Manager
18
5Project close
Formally close out project, including filing of necessary deliverables, end-of-project debriefs, and creation of BD materials
Written client confirmation of final deliverables acceptedProject Lead and/or project manager
19
Archive final deliverables in project Dropbox folderProject Manager
20
Internal team debrief/feedbackProject Manager and Project Lead
21
Client debrief/feedback survey and interview + request permission to use project for promotion (reference; and case study, blog post, and/or list on website)Agency MD
22
Follow-up client conversation on potential renewalProject Principal/Lead
23
Client giftProject Manager
24
Post-project Leadership Team debriefProject Principal, Lead and Manager
25
Case studyProject team member
26
Project report-back at staff meeting/pod-builderProject team
27
Archive new/additions to our IPProject team member
28
Blog postProject team member