Procurement Schedule
3
4
Key:
5
Project:Insert Name HereOnly update the green cells
6
When do we expect the SOW to be completed?Wed, 2/15/2023
7
8
1) Planning Phase (Develop SOW + RFP)
Finish DateDuration
(days)
Duration
(weeks)
Duration
(months)
Comments
9
1Planning Meeting with Procurement / Supply ChainTue, 2/7/20233041.0
10
2Compile the Statement of Work (SOW)Wed, 2/8/2023100.0assumes ~1mo to compile the SOW
11
3Full SOW is ready for releaseWed, 2/15/2023710.2assumes ~1 week compilation before advertise
12
Total:385.41.2
13
14
2) Selection Phase (Solicit & Evaluate Proposals)
Finish DateDuration
(days)
Duration
(weeks)
Duration
(months)
Comments
15
1RFP(s) released to vendorsWed, 2/22/2023710.2
16
2Pre-Proposal Information Session(s) / Site WalkWed, 3/1/2023710.2schedule for roughly 1 wk after RFP release
17
3Vendor proposals are dueFri, 3/24/20232430.8assumes ~4-5wk for proposal response
18
4Evaluate vendor written proposalsFri, 4/7/20231420.5can go as fast as evaluators are available
19
5Lead time for Interviews and/or Product DemosMon, 4/17/20231010.3
give 1-2wk notice for SL vendors to attend Int/Demos
20
6Interviews and/or Product DemonstrationsMon, 4/24/2023710.2assumes 1wk window for Int/Demos
21
7Final Selection ResultsWed, 4/26/2023200.1should be quick to assemble!
22
8Internal approvals & executive briefingsWed, 5/10/20231420.5depends on internal approvals process
23
Total:8512.12.8
24
25
3) Execute Contract
Finish DateDuration
(days)
Duration
(weeks)
Duration
(months)
Comments
26
1Notification & PreparationWed, 5/17/2023710.21 wk to orient, train, and prep
27
2Contracting Kickoff Meeting(s)Wed, 5/24/2023710.21wk window for Kickoff Meeting
28
3Contracting Activities - detailed planning & documentationFri, 6/23/202330.541.0highly variable…
29
4Contracting Summary MeetingFri, 6/30/2023710.21wk window
30
5Contract SignatureMon, 7/3/2023200.1work on contract in parallel with clarification!!!
31
6Notice to ProceedWed, 7/5/2023200.1how quickly should vendors expect to mobilize?
32
Total:55.57.91.8driven by internal SME availability & # vendors
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100