ABCDEFGHIJKLMNOPQR
1
Raw NumbersCosts per unit
2
NovemberMarchNovemberMarchIADB Budget Changes
3
laptops1700013700Connectivity/school$3,000$2,848.00
4
servers070laptop$188$188.43Given cost totalsNovMarDifference
5
communities4040server$0$1,144.29Materials370,000258,100(111,900)
6
schools6060Creole Content190,000133,500(56,500)
7
students1900013200Didactic Materials180,000124,600(55,400)
8
teachers500500Training326,336232,643(93,693)
9
Immersion Training80,10080,100
10
Number calcsSummer Camp137,505137,505
11
Students/teacher3826.4Community Awareness4,0054,005
12
students/school316.7220Process Management11,03311,033
13
Implementation & Eval720,0001,096,064376,064
14
Cost CalulationsProject Coordinator200,000(200,000)
15
NovemberNov per-laptopMarchMar per-laptopMar*5yrJon1yrJon*5yrLaunch Team209,328209,328
16
Training and content$696,336$40.96$490,743.00$35.82$35.82$27.60$138.00Pedagogical and ICT advisors100,000108,9368,936
17
setup/implementation costs$735,664$43.27$1,355,827.00$98.97$98.97$108.00$108.00Local Distribution100,000100,000
18
maintenance$100,000$5.88$71,200.00$5.20$25.99$7.40$37.00Field Observation200,000100,000(100,000)
19
Hardware$3,568,000$209.88$3,182,230.00$232.28$282.17$149.00$689.00Qualatative assessment200,000100,000(100,000)
20
...connectivity$180,000$10.59$170,880.00$12.47$62.36$1.00$541.00Audit60,00060,000
21
...Laptops$3,196,000$209.88$2,581,480.00$188.43$188.43$148.00$148.00Coordination & Tech Assist400,000400,000
22
...non-laptop hardware costs$192,000$11.29$429,870.00$31.38$31.38$0.00$0.00Sampling Consultant20,00017,800(2,200)
23
Sum$5,100,000$300.00$5,100,000.00$372.26$442.94$292.00$972.00Repair/Maint100,00071,200(28,800)
24
$431.00Hardware3,568,0003,182,230(385,770)
25
$11.94Energy Systems0267,000267,000
26
Security Installation016,02016,020
27
Connectivity180,000170,880(9,120)
28
Servers080,10080,100
29
Alternative Power066,75066,750
30
Laptops3,196,0002,581,480(614,520)
31
Other?192,000(192,000)
32
Contingencies15,664259,763244,099
33
TOTAL5,100,0005,100,0000