Prop D TNC Tax Project List (FY 2020/21 - FY 2024/25)Prop D TNC Tax Project List (FY 2020/21 - FY 2024/25)
2
Programming and AllocationsCash Flow (Maximum Annual Reimbursement)
3
Approved July 22, 2025 BoardApproved July 22, 2025 Board
4
ResolutionAgencyProject NamePhaseStatusFiscal YearTotalProject NamePhaseFiscal YearTotal
5
2020/20212021/222022/232023/242024/252025/262020/20212021/222022/232023/242024/252025/262026/27
6
2021-016SFMTAVision Zero Quick-Build Program FY211, 2PS&EAllocated$410,000 $410,000 Vision Zero Quick-Build Program FY211, 2PS&E$0 $389,661 $15,339 $5,000 $410,000
7
2021-016SFMTAVision Zero Quick-Build Program FY211, 2CONAllocated$2,095,686 $2,095,686 Vision Zero Quick-Build Program FY211, 2CON$661,212 $1,094,385 $340,088 $2,095,686
8
2022-020SFMTAFY22 Vision Zero Quick Build Program Implementation1, 3PS&EAllocated$1,340,000 $1,340,000 FY22 Vision Zero Quick Build Program Implementation1, 3PS&E$1,000,000 $340,000 $1,340,000
9
2022-020SFMTAFY22 Vision Zero Quick Build Program Implementation1, 3CONAllocated$1,660,000 $1,660,000 FY22 Vision Zero Quick Build Program Implementation1, 3CON$1,660,000 $1,660,000
10
2023-032SFMTAFY23 Vision Zero Quick Build Program Implementation (Part 1)1, 4PS&EAllocated$1,495,000 $1,495,000 FY23 Vision Zero Quick Build Program Implementation (Part 1)1, 4PS&E$300,000 $659,400 $535,600 $1,495,000
11
2023-032SFMTAFY23 Vision Zero Quick Build Program Implementation (Part 1)1, 4CONAllocated$505,000 $505,000 FY23 Vision Zero Quick Build Program Implementation (Part 1)1, 4CON$505,000 $505,000
12
2023-043SFMTAFY23 Vision Zero Quick Build Program Implementation (Part 2)5, 6CONAllocated$2,451,857 $2,451,857 FY23 Vision Zero Quick Build Program Implementation (Part 2)5, 6CON$2,451,857 $2,451,857
13
2023-049SFMTAFY24 & FY25 Application-Based Residential Traffic Calming Program5, 7PLAN/ CERAllocated$200,000 $200,000 FY24 & FY25 Application-Based Residential Traffic Calming Program5, 7PLAN/ CER$100,000 $100,000 $200,000
14
2023-049SFMTAFY24 & FY25 Application-Based Residential Traffic Calming Program5, 7PS&EAllocated$225,000 $225,000 FY24 & FY25 Application-Based Residential Traffic Calming Program5, 7PS&E$112,500 $112,500 $225,000
15
2023-049SFMTAFY24 & FY25 Application-Based Residential Traffic Calming Program5, 7CONAllocated$3,845,000 $3,845,000 FY24 & FY25 Application-Based Residential Traffic Calming Program5, 7CON$1,075,000 $2,155,000 $615,000 $3,845,000
16
2023-043SFMTAFY24 Vision Zero Quick-Build Program5,9,13TBDProgrammed$0 $0 FY24 Vision Zero Quick-Build Program5,9,13TBD$0 $0
17
2024-023SFMTAVision Zero Quick-Build Program Implementation FY245, 8PS&EAllocated$700,000 $700,000 Vision Zero Quick-Build Program Implementation FY245, 8PS&E$350,000 $350,000 $700,000
18
2024-023SFMTAVision Zero Quick-Build Program Implementation FY245, 8CONAllocated$5,300,000 $5,300,000 Vision Zero Quick-Build Program Implementation FY245, 8CON$2,650,000 $2,650,000 $5,300,000
19
2023-043SFMTAFY22 Application-Based Residential Traffic Calming Program5, 10CONAllocated$1,215,000 $1,215,000 FY22 Application-Based Residential Traffic Calming Program5, 10CON$1,215,000 $1,215,000
20
2025-011SFMTAVision Zero Quick-Build Implementation FY259PS&EAllocated$295,000 $295,000 Vision Zero Quick-Build Implementation FY259PS&E$147,500 $147,500 $295,000
21
2025-011SFMTAVision Zero Quick-Build Implementation FY259CONAllocated$3,198,000 $3,198,000 Vision Zero Quick-Build Implementation FY259CON$1,599,000 $1,119,300 $479,700 $3,198,000
22
2025-025SFMTAFY25 Vision Zero Quick-Build Program10PS&EAllocated$1,237,000 $1,237,000 FY25 Vision Zero Quick-Build Program10PS&E$309,000 $620,000 $308,000 $1,237,000
23
2025-025SFMTAFY25 Vision Zero Quick-Build Program10CONAllocated$2,948,000 $2,948,000 FY25 Vision Zero Quick-Build Program10CON$737,000 $1,474,000 $737,000 $2,948,000
24
2026-006SFMTAApplication-Based Traffic Calming Program - FY21 Cycle Additional Funds11PS&EAllocated$56,569 $56,569 Application-Based Traffic Calming Program - FY21 Cycle Additional Funds11PS&E$56,569 $56,569
25
2026-006SFMTAApplication-Based Traffic Calming Program - FY21 Cycle Additional Funds11CONAllocated$199,333 $199,333 Application-Based Traffic Calming Program - FY21 Cycle Additional FundsCON$174,333 $25,000 $199,333
26
2026-006SFMTAApplication-Based Traffic Calming - FY22 Cycle11CONAllocated$5,141,670 $5,141,670 Application-Based Traffic Calming - FY22 Cycle11CON$4,785,000 $356,670 $5,141,670
27
2026-006SFMTAApplication-Based Traffic Calming - FY23 Cycle11PS&EAllocated$274,933 $274,933 Application-Based Traffic Calming - FY23 Cycle11PS&E$274,933 $274,933
110
111
Total Programmed$2,505,686 $3,000,000 $8,721,857 $7,215,000 $7,678,000 $5,672,505 $34,793,048 Cash Flow Programmed$0 $2,710,873 $2,622,224 $5,631,988 $11,439,957 $10,481,635 $1,906,370 $34,793,048
112
Total Allocated and Pending$2,505,686 $3,000,000 $8,721,857 $7,215,000 $7,678,000 $5,672,505 $34,793,048 Total Cash Flow Allocated and Pending$0 $2,710,873 $2,622,224 $5,631,988 $11,439,957 $10,481,635 $1,906,370 $34,793,048
113
Total Programmed and Unallocated$0 $0 $0 $0 $0 $0 $0 Total Cash Flow Unallocated$0 $0 $0 $0 $0 $0 $0 $0
114
115
Pending Allocation/AppropriationPending Allocation/Appropriation
116
Board Approved Allocation/AppropriationBoard Approved Allocation/Appropriation
117
118
119
FOOTNOTES:
120
1Programming: $2,505,686 to SFMTA’s FY21 Vision Zero Quick-Build Program; and $5,000,000 to SFMTA's FY22 Vision Zero Quick-Build Program (Resolution 2021-015, 10/27/2020).
121
2Allocation: $2,505,686 to Vision Zero Quick-Build Program FY21 (Resolution 2021-016, 10/27/2020).
122
3Allocation: $3,000,000 to FY22 Vision Zero Quick-Build Program Implementation (Resolution 2022-020, 12/14/2021).
123
4Allocation: $2,000,000 from SFMTA’s FY22 Vision Zero Quick-Build Program to FY23 Vision Zero Quick-Build Program Implementation (Part 1) (Resolution 2023-032, 2/28/2023).
124
5Programming: $2,451,857 to SFMTA's FY23 Vision Zero Quick-Build Program; $9,493,883 to SFMTA's FY24 Vision Zero Quick-Build Program; $5,400,000 to SFMTA's FY22 Application-Based Residential Traffic Calming; and $4,270,000 to SFMTA's FY24 & FY25 Application-Based Residential Traffic Calming Program (Resolution 2023-042, 4/25/2023).
125
6Allocation: $2,451,857 to FY23 Vision Zero Quick-Build Program (Part 2) (Resolution 2023-043, 4/25/2023).
126
7Allocation: $4,270,000 to FY24 & FY25 Application-Based Residential Traffic Calming Program (Resolution 2023-049, 5/23/23).
127
8Allocation: $6,000,000 to Vision Zero Quick-Build Program Implementation FY24 (Resolution 2024-023, 12/12/23).
128
9Allocation: $3,493,000 to Vision Zero Quick-Build Implementation FY25 (Resolution 2025-011, 9/24/24).
129
10Amendment to reprogram $4,185,000 from the FY22 Application-Based Residential Traffic Calming Program to the FY25 Vision Zero Quick-Build Program, with concurrent allocation of funds (Resolution 2025-0xx, 12/17/24).
130
FY22 Application-Based Residential Traffic Calming Program: Reduced from $5,400,000 to $1,215,000 in FY23/24
131
FY25 Vision Zero Quick-Build Program: Added project in FY24/25 with $1,237,000 for design and $2,948,000 for construction
132
11Allocation: $255,902 to SFMTA's Application-Based Traffic Calming Program - FY21 Cycle Additional Funds; $5,442,000 to SFMTA's Application-Based Traffic Calming - FY22 Cycle; and $274933 to Design Only for SFMTA's Application-Based Traffic Calming - FY23 Cycle (Resolution XX, 7/22/2025).
133
12Cash flow reduced in FY 23/24 from $1,215,000 to $0.
134
13Amendment to reprogram $883 from FY24 Vision Zero Quick-Build Program to the Application-Based Traffic Calming - FY22 Cycle to Remaining Programming Capacity
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167