| A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | AA | AB | AC | AD | AE | AF | AG | AH | AI | AJ | AK | AL | AM | AN | AO | AP | AQ | AR | AS | AT | AU | AV | AW | AX | AY | AZ | BA | BB | BC | BD | BE | BF | BG | BH | BI | BJ | BK | BL | BM | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Filter Daerah | DATA GARDU INDUK | DATA JALUR TRANSMISI | DATA TENAGA KERJA | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 | KALIMANTAN 1 | DATA GARDU INDUK UNIT PELAKSANA KALIMANTAN 1 | DATA JALUR TRANSMISI UNIT PELAKSANA KALIMANTAN 1 | DATA TENAGA KERJA TRANSMISI UNIT PELAKSANA KALIMANTAN 1 | MONITORING ALAT KERJA UNIT PELAKSANA KALIMANTAN 1 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
4 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
5 | 1 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
6 | No | UPT | ULTG | NAMA GARDU INDUK | JML OPGI | JML HARGI | TAHUN KONTRAK | No | UPT | ULTG | JENIS (SKTT/SUTT*) | JALUR TRANSMISI | TEGANGAN (70kV/150kV/275kV*) | TOTAL KMS | JML PETUGAS | TAHUN KONTRAK | No | NIP | Nama | Status (PKWT/PKWTT*) | Jabatan | Penempatan (Kantor/GI/Jalur Transmisi*) | Project | Tanggal Mulai Bekerja | Sertifikasi Kompetensi (Sudah/Belum*) | Tanggal Akhir Masa Berlaku Sertifikat Kompetensi (jika sudah serkom) | No | UP | Project | Uraian | Qty | Sat | Masa Pakai | Kondisi (Baik/Rusak) | |||||||||||||||||||||||||||||||
7 | 1 | UPT Pontianak | ULTG Ketapang | GI Kendawangan | 1 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Sei Raya - Siantan 1 | 150 | 18.18 | 1997 | 1 | 1 | Kal 1 | GP PNK | Helm Safety | 1 | bh | /thn | |||||||||||||||||||||||||||||||||||||||||||||
8 | 2 | UPT Pontianak | ULTG Ketapang | GI Ketapang | 2 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Sei Raya - Siantan 2 | 150 | 18.18 | 1997 | 2 | 2 | Kal 1 | GP PNK | Seragan Kerja @2 set/ tahun | 2 | set | /thn | |||||||||||||||||||||||||||||||||||||||||||||
9 | 3 | UPT Pontianak | ULTG Ketapang | GI SANDAI | 3 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Siantan - Parit Baru | 150 | 16.73 | 1998 | 3 | 3 | Kal 1 | GP PNK | Jas Hujan | 1 | bh | /thn | |||||||||||||||||||||||||||||||||||||||||||||
10 | 4 | UPT Pontianak | ULTG Ketapang | GI MERAU | 4 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Siantan - Cendana | 150 | 34.37 | 2021 | 4 | 4 | Kal 1 | GP PNK | Sepatu Safety | 2 | set | /thn | |||||||||||||||||||||||||||||||||||||||||||||
11 | 5 | UPT Pontianak | ULTG Ketapang | GI Sukadana | 5 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Parit Baru - Kota Baru | 150 | 24.04 | 2015 | 5 | 5 | Kal 1 | GP PNK | Sepatu Boots | 1 | set | /thn | |||||||||||||||||||||||||||||||||||||||||||||
12 | 6 | UPT Pontianak | ULTG Ketapang | GI Marau (eks.Air Upas) | 6 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Kota Baru - Cendana | 150 | 07.02 | 2021 | 6 | 6 | Kal 1 | GP PNK | Mandau Golok | 1 | set | /thn | |||||||||||||||||||||||||||||||||||||||||||||
13 | 7 | UPT Pontianak | ULTG Pontianak | GI Cendana | 7 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Parit Baru - Senggiring 1 | 150 | 42.81 | 2004 | 7 | 7 | Kal 1 | GP PNK | Tas Ransel Lapangan | 1 | bh | /thn | |||||||||||||||||||||||||||||||||||||||||||||
14 | 8 | UPT Pontianak | ULTG Pontianak | GI Kota Baru | 8 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Parit Baru - Senggiring 2 | 150 | 42.81 | 2004 | 8 | 8 | Kal 1 | GP PNK | Handphone Android A25 (Samsung) Minimal Kamera 50mp, RAM 8 GB, ROM 256 GB + Pelindung layar + Casing | 1 | bh | /2 thn | |||||||||||||||||||||||||||||||||||||||||||||
15 | 9 | UPT Pontianak | ULTG Pontianak | GI Parit Baru | 9 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Tayan - Siantan 1 | 150 | 103.05 | 2018 | 9 | 9 | Kal 1 | GP PNK | Sewa Motor Petugas | 1 | bh | /bln | |||||||||||||||||||||||||||||||||||||||||||||
16 | 10 | UPT Pontianak | ULTG Pontianak | GI Sei Raya | 10 | UPT PONTIANAK | ULTG PONTIANAK | SUTT | Tayan - Siantan 2 | 150 | 103.05 | 2018 | 10 | 10 | Kal 1 | GP PNK | Powerbank 10.000 mAh | 1 | bh | /thn | |||||||||||||||||||||||||||||||||||||||||||||
17 | 11 | UPT Pontianak | ULTG Pontianak | GI Siantan | 11 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Ngabang - Tayan 1 | 150 | 46.80 | 2018 | 11 | 11 | Kal 1 | OPGI PNK | Jas Hujan | 12 | set | /bln | |||||||||||||||||||||||||||||||||||||||||||||
18 | 12 | UPT Pontianak | ULTG Pontianak | GI Ambawang | 12 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Ngabang - Tayan 2 | 150 | 46.80 | 2018 | 12 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
19 | 13 | UPT Pontianak | ULTG Sanggau | GI Tayan | 13 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Tayan - Sanggau 1 | 150 | 77.58 | 2020 | 13 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
20 | 14 | UPT Pontianak | ULTG Sanggau | GI Ngabang | 14 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Tayan - Sanggau 2 | 150 | 77.58 | 2020 | 14 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
21 | 15 | UPT Pontianak | ULTG Sanggau | GI Sanggau | 15 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Senggiring - Singkawang | 150 | 70.73 | 2010 | 15 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
22 | 16 | UPT Pontianak | ULTG Sanggau | GI Sekadau | 16 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Senggiring - PLTU Bengkayang | 150 | 67.96 | 2018 | 16 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
23 | 17 | UPT Pontianak | ULTG Sanggau | GI Sintang | 17 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Singkawang - PLTU Bengkayang | 150 | 22.53 | 2018 | 17 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
24 | 18 | UPT Pontianak | ULTG Sanggau | GI Badau | 18 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Singkawang - PLTU Kalbar1 1 | 150 | 22.22 | 2020 | 18 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
25 | 19 | UPT Pontianak | ULTG Sanggau | GI Nanga Pinoh | 19 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Singkawang - PLTU Kalbar1 2 | 150 | 22.22 | 2020 | 19 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
26 | 20 | UPT Pontianak | ULTG Sanggau | GI Kota Baru - 2 | 20 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Singkawang - Sambas 1 | 150 | 59.00 | 2015 | 20 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
27 | 21 | UPT Pontianak | ULTG Sanggau | GI Entikong | 21 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Singkawang - Sambas 2 | 150 | 59.00 | 2015 | 21 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
28 | 22 | UPT Pontianak | ULTG Sanggau | GI Putussibau | 22 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Singkawang - Bengkayang 1 | 150 | 70.00 | 2015 | 22 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
29 | 23 | UPT Pontianak | ULTG Singkawang | GI Senggiring | 23 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Singkawang - Bengkayang 2 | 150 | 70.00 | 2015 | 23 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
30 | 24 | UPT Pontianak | ULTG Singkawang | GI Bengkayang | 24 | UPT PONTIANAK | ULTG SINGKAWANG | SUTET | Bengkayang - Mambong 1 | 275 | 81.37 | 2015 | 24 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
31 | 25 | UPT Pontianak | ULTG Singkawang | GI PLTU Bengkayang | 25 | UPT PONTIANAK | ULTG SINGKAWANG | SUTET | Bengkayang - Mambong 2 | 275 | 81.37 | 2015 | 25 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
32 | 26 | UPT Pontianak | ULTG Singkawang | GI Sambas | 26 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Bengkayang - Ngabang 1 | 150 | 95.66 | 2017 | 26 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
33 | 27 | UPT Pontianak | ULTG Singkawang | GI Singkawang | 27 | UPT PONTIANAK | ULTG SINGKAWANG | SUTT | Bengkayang - Ngabang 2 | 150 | 95.66 | 2017 | 27 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
34 | 28 | UPT Pontianak | ULTG Singkawang | GIS PLTU Kalbar1 | 28 | UPT PONTIANAK | ULTG KETAPANG | SUTT | Ketapang - Sandai | 150 | 127.45 | 2020 | 28 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
35 | 29 | UPT Pontianak | ULTG Singkawang | GITET Bengkayang | 29 | UPT PONTIANAK | ULTG KETAPANG | SUTT | Sandai - Sukadana | 150 | 75.46 | 2020 | 29 | ||||||||||||||||||||||||||||||||||||||||||||||||||||
36 | 30 | 30 | UPT PONTIANAK | ULTG KETAPANG | SUTT | Ketapang - Sukadana 2 | 150 | 73.51 | 2020 | 30 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
37 | 31 | 31 | UPT PONTIANAK | ULTG KETAPANG | SUTT | Ketapang - Kendawangan 1 | 150 | 65.74 | 2020 | 31 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
38 | 32 | 32 | UPT PONTIANAK | ULTG KETAPANG | SUTT | Ketapang - Kendawangan 2 | 150 | 65.74 | 2020 | 32 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
39 | 33 | 33 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Sanggau - Sekadau 1 | 150 | 46.61 | 2022 | 33 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
40 | 34 | 34 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Sanggau - Sekadau 2 | 150 | 46.61 | 2022 | 34 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
41 | 35 | 35 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Sekadau - Sintang 1 | 150 | 65.35 | 2022 | 35 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
42 | 36 | 36 | UPT PONTIANAK | ULTG SANGGAU | SUTT | Sekadau - Sintang 2 | 150 | 65.35 | 2022 | 36 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
43 | KALIMANTAN 2 | DATA GARDU INDUK UNIT PELAKSANA KALIMANTAN 2 | DATA JALUR TRANSMISI UNIT PELAKSANA KALIMANTAN 2 | DATA TENAGA KERJA TRANSMISI UNIT PELAKSANA KALIMANTAN 2 | MONITORING ALAT KERJA UNIT PELAKSANA KALIMANTAN 2 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
44 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
45 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
46 | 1 | 1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
47 | No | UPT | ULTG | NAMA GARDU INDUK | JML OPGI | JML HARGI | TAHUN KONTRAK | No | UPT | ULTG | JENIS (SKTT/SUTT*) | JALUR TRANSMISI | TEGANGAN (70kV/150kV/275kV*) | TOTAL KMS | JML PETUGAS | TAHUN KONTRAK | No | NIP | Nama | Status (PKWT/PKWTT*) | Jabatan | Penempatan (Kantor/GI/Jalur Transmisi*) | Project | Tanggal Mulai Bekerja | Sertifikasi Kompetensi (Sudah/Belum*) | Tanggal Akhir Masa Berlaku Sertifikat Kompetensi (jika sudah serkom) | No | UP | Project | Uraian | Qty | Sat | Masa Pakai | Kondisi (Baik/Rusak) | |||||||||||||||||||||||||||||||
48 | 1 | UPT Palangkaraya | ULTG Pangkalan Bun | GI BAGENDANG | 4 | 1 | UPT BANJARBARU | ULTG BANJAR & ULTG BANDARMASIH | SUTT | ASAM ASAM - MANTUIL | 150 | 199.3 | 18 | 2011 | 1 | 8019048KST | KUSWANTO | PKWTT | OPERATOR GI | GI BAGENDANG - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 1-June-2019 | 22/11/2022 | 22-Nov-2025 | 1 | Kal 2 | GP BJB & PKY | Helm Safety | 1 | bh | /thn | ||||||||||||||||||||||||||||||||||
49 | 2 | UPT Palangkaraya | ULTG Muara Teweh | GI BANGKANAI | 4 | 2 | UPT BANJARBARU | ULTG BANJAR | SUTT | ASAM ASAM - PELAIHARI | 150 | 117.5 | 10 | 2000 | 2 | 9319037KST | BACHRUL ILMI | PKWTT | OPERATOR GI | GI BAGENDANG - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 1-June-2014 | 22/11/2022 | 22-Nov-2025 | 2 | Kal 2 | GP BJB & PKY | Seragan Kerja @2 set/ tahun | 2 | stel | /thn | ||||||||||||||||||||||||||||||||||
50 | 3 | UPT Palangkaraya | ULTG Muara Teweh | GI BUNTOK | 4 | 3 | UPT BANJARBARU | ULTG BATULICIN | SUTT | ASAM ASAM - SATUI | 150 | 106.3 | 8 | 2012 | 3 | 9420069KST | JELLY RENALDY | PKWTT | OPERATOR GI | GI BAGENDANG - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 17-February-2020 | 10-Jun-2023 | 06 October 2026 | 3 | Kal 2 | GP BJB & PKY | Jas Hujan | 1 | stel | /thn | ||||||||||||||||||||||||||||||||||
51 | 4 | UPT Palangkaraya | ULTG Palangkaraya | GI KASONGAN | 4 | 4 | UPT BANJARBARU | ULTG BANJAR | SUTT | BANDARA - MANTUIL | 150 | 34.7 | 3 | 2000 | 4 | 9720033KST | KHOLIS ROMAYUDIN | PKWTT | OPERATOR GI | GI BAGENDANG - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 17-February-2020 | 10-Jun-2023 | 06 October 2026 | 4 | Kal 2 | GP BJB & PKY | Sepatu Safety | 1 | stel | /thn | ||||||||||||||||||||||||||||||||||
52 | 5 | UPT Palangkaraya | ULTG Palangkaraya | GI KUALA KURUN | 4 | 5 | UPT BANJARBARU | ULTG BARABAI | SUTT | BARIKIN - AMUNTAI | 150 | 85 | 7 | 2011 | 5 | 1919004KST | APRILLIAWAN | PKWTT | OPERATOR GI | GI BANDARA - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Mar-2024 | 3-Sep-2027 | 5 | Kal 2 | GP BJB & PKY | Sepatu Boots | 1 | stel | /thn | ||||||||||||||||||||||||||||||||||
53 | 6 | UPT Palangkaraya | ULTG Palangkaraya | GI Kuala Pembuang | 4 | 6 | UPT BANJARBARU | ULTG BARABAI | SUTT & SKTT | BARIKIN - TANJUNG | 150 | 120.3 | 9 | 2010 | 6 | 7119007KST | FATHURAHMAN | PKWTT | OPERATOR GI | GI BANDARA - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | 6 | Kal 2 | GP BJB & PKY | Pisau Sabit Rumput | 1 | set | /thn | ||||||||||||||||||||||||||||||||||
54 | 7 | UPT Palangkaraya | ULTG Palangkaraya | GI MINTIN | 4 | 7 | UPT BANJARBARU | ULTG BANJAR | SUTT | BATI BATI - CEMPAKA | 150 | 35.9 | 1 | 2021 | 7 | 8719022KST | SURYADI | PKWTT | OPERATOR GI | GI BANDARA - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | 7 | Kal 2 | GP BJB & PKY | Tas Ransel Lapangan | 1 | bh | /thn | ||||||||||||||||||||||||||||||||||
55 | 8 | UPT Palangkaraya | ULTG Muara Teweh | GI MUARA TEWEH | 4 | 5 | 8 | UPT BANJARBARU | ULTG BATULICIN | SUTT | BATULICIN - ITP | 150 | 85.3 | 6 | 2022 | 8 | 8919020KST | AHMAD SYARIF | PKWTT | OPERATOR GI | GI BANDARA - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 10-June-2019 | 22/11/2022 | 22-Nov-2025 | 8 | Kal 2 | GP BJB & PKY | Handphone Android A25 (Samsung) Minimal Kamera 50mp, RAM 8 GB, ROM 256 GB + Pelindung layar + Casing | 1 | bh | /2 thn | |||||||||||||||||||||||||||||||||
56 | 9 | UPT Palangkaraya | ULTG Pangkalan Bun | GI Nangabulik | 4 | 9 | UPT BANJARBARU | ULTG BATULICIN | SUTT | BATULICIN - PULAU LAUT | 150 | 83.7 | 7 | 2019 | 9 | 8219017KST | RENDRA HAIRIN TOMY | PKWTT | OPERATOR GI | GI ARANIO - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | 9 | Kal 2 | OPGI BJB | Jas Hujan | 12 | stel | /bln | ||||||||||||||||||||||||||||||||||
57 | 10 | UPT Palangkaraya | ULTG Palangkaraya | GI PALANGKARAYA | 4 | 1 | 10 | UPT BANJARBARU | ULTG BATULICIN | SUTT | BATULICIN - SILO | 150 | 235.8 | 6 | 2022 | 10 | 8719023KST | RAHMAN ARSAID | PKWTT | OPERATOR GI | GI ARANIO - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-July-2015 | 12-Sep-2022 | 09 December 2025 | 10 | Kal 2 | OPGI PKY | Jas Hujan | 12 | stel | /bln | |||||||||||||||||||||||||||||||||
58 | 11 | UPT Palangkaraya | ULTG Pangkalan Bun | GI PANGKALAN BANTENG | 4 | 11 | UPT BANJARBARU | ULTG BANJAR | SUTT | CEMPAKA - BANDARA | 150 | 23.2 | 2 | 2000 | 11 | 9020008KST | MUHAMMAD HERRY KHAIRIYADI | PKWTT | OPERATOR GI | GI ARANIO - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 15-January-2020 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
59 | 12 | UPT Palangkaraya | ULTG Pangkalan Bun | GI PANGKALAN BUN | 4 | 1 | 12 | UPT BANJARBARU | ULTG BANJAR & ULTG BARABAI | SUTT | CEMPAKA - RANTAU | 150 | 120.4 | 11 | 1997 | 12 | 9619008KST | MUHAMMAD SOFYAN AZHARI | PKWTT | OPERATOR GI | GI ARANIO - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 10-June-2019 | 12-Sep-2022 | 09 December 2025 | ||||||||||||||||||||||||||||||||||||||||
60 | 13 | UPT Palangkaraya | ULTG Palangkaraya | GI PARENGGEAN | 4 | 13 | UPT BANJARBARU | ULTG BANJAR & ULTG BANDARMASIH | SUTT | CEMPAKA - ULIN | 70 | 63.3 | 4 | 1973 | 13 | 8019011KST | ERSUMADI | PKWTT | OPERATOR GI | GI ASAM-ASAM - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||
61 | 14 | UPT Palangkaraya | ULTG Palangkaraya | GI PLTU SLK | 3 | 14 | UPT BANJARBARU | ULTG BANJAR | SUTT | INCOMER BANDARA | 150 | 0.7 | 1 | 2018 | 14 | 8719021KST | AGUS SETIAWAN | PKWTT | OPERATOR GI | GI ASAM-ASAM - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Mar-2024 | 3-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||
62 | 15 | UPT Palangkaraya | ULTG Palangkaraya | GI PULANG PISAU | 4 | 15 | UPT BANJARBARU | ULTG BANJAR | SUTT | INCOMER BATI BATI | 150 | 22.5 | 1 | 2021 | 15 | 9519022KST | KHAIRUL ARIFIN | PKWTT | OPERATOR GI | GI ASAM-ASAM - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 12-Sep-2022 | 09 December 2025 | |||||||||||||||||||||||||||||||||||||||||
63 | 16 | UPT Palangkaraya | ULTG Muara Teweh | GI PURUK CAHU | 4 | 16 | UPT BANJARBARU | ULTG BARABAI | SUTT | INCOMER KANDANGAN | 150 | 7.5 | 1 | 2023 | 16 | 9719006KST | DIAN ADI WIBOWO | PKWTT | OPERATOR GI | GI ASAM-ASAM - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 15-January-2017 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
64 | 17 | UPT Palangkaraya | ULTG Pangkalan Bun | GI SAMPIT | 3 | 4 | 17 | UPT BANJARBARU | ULTG BARABAI | SUTT | INCOMER PARINGIN | 150 | 1.2 | 1 | 2021 | 17 | 1919005KST | AHMAD RIFANI | PKWTT | OPERATOR GI | GI BATI-BATI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-July-2015 | 31/08/2023 | 31 August 2026 | ||||||||||||||||||||||||||||||||||||||||
65 | 18 | UPT Palangkaraya | ULTG Palangkaraya | GI SEBANGAU | 4 | 18 | UPT BANJARBARU | ULTG BANJAR | SUTT | INCOMER PELAIHARI | 150 | 3.3 | 1 | 2004 | 18 | 9419025KST | MADI WIYONO | PKWTT | OPERATOR GI | GI BATI-BATI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 13-August-2014 | 13/10/2022 | 13 October 2025 | |||||||||||||||||||||||||||||||||||||||||
66 | 19 | UPT Palangkaraya | ULTG Palangkaraya | GI SUDAN | 4 | 19 | UPT BANJARBARU | ULTG BARABAI | SUTT | KAYUTANGI - BARIKIN | 150 | 315.3 | 17 | 2019 | 19 | 9519024KST | LEO ABDUL JABAR | PKWTT | OPERATOR GI | GI BATI-BATI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 15-January-2017 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
67 | 20 | UPT Palangkaraya | ULTG Pangkalan Bun | GI Sukamara | 4 | 20 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | KAYUTANGI - MARABAHAN | 150 | 63.7 | 4 | 2019 | 20 | 9619012KST | MARIO CHANDRA BUANA | PKWTT | OPERATOR GI | GI BATI-BATI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 15-January-2017 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
68 | 21 | UPT Banjarbaru | ULTG Barabai | GI AMUNTAI | 4 | 21 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | KAYUTANGI - SEI TABUK | 150 | 47.3 | 4 | 2020 | 21 | 0220005KST | RAMADAN | PKWTT | OPERATOR GI | GI BARIKIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 15-January-2020 | 18/10/2023 | 18 October 2026 | |||||||||||||||||||||||||||||||||||||||||
69 | 22 | UPT Banjarbaru | ULTG Banjar | GI ASAM ASAM | 4 | 22 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | MANTUIL - TRISAKTI | 150 | 30.3 | 2 | 2001 | 22 | 8119021KST | MUHAMMAD ZAINI | PKWTT | OPERATOR GI | GI BARIKIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||
70 | 23 | UPT Banjarbaru | ULTG Banjar | GI BANDARA | 4 | 23 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | MARABAHAN - BARIKIN | 150 | 1.1 | 1 | 2019 | 23 | 9520021KST | MUHAMMAD YUSHALDI NUGROHO | PKWTT | OPERATOR GI | GI BARIKIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 10-February-2020 | 16/10/2023 | 16 October 2026 | |||||||||||||||||||||||||||||||||||||||||
71 | 24 | UPT Banjarbaru | ULTG Barabai | GI BARIKIN | 4 | 5 | 24 | UPT BANJARBARU | ULTG BANJAR | SUTT | PELAIHARI - BATI BATI | 150 | 52.6 | 2 | 2021 | 24 | 03221334BJM | M. RIFKI ANWAR | PKWTT | OPERATOR GI | GI BARIKIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 15-November-2022 | 27/03/2023 | 27 March 2026 | ||||||||||||||||||||||||||||||||||||||||
72 | 25 | UPT Banjarbaru | ULTG Banjar | GI BATI BATI | 4 | 25 | UPT BANJARBARU | ULTG BANJAR | SUTT | PLTA - CEMPAKA | 70 | 38.2 | 2 | 1973 | 25 | 7920072KST | PARLIN HALOMOAN HASIBUAN | PKWTT | OPERATOR GI | GI BATULICIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 17-February-2020 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
73 | 26 | UPT Banjarbaru | ULTG Batulicin | GI BATULICIN | 4 | 3 | 26 | UPT BANJARBARU | ULTG BARABAI | SUTT | RANTAU - BARIKIN | 150 | 91.4 | 8 | 1997 | 26 | 96200390BJM | ROMY ABDILLAH | PKWTT | OPERATOR GI | GI BATULICIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-July-2020 | 10-Jun-2023 | 06 October 2026 | ||||||||||||||||||||||||||||||||||||||||
74 | 27 | UPT Banjarbaru | ULTG Banjar | GI CEMPAKA 150 | 4 | 5 | 27 | UPT BANJARBARU | ULTG BATULICIN | SUTT | SATUI - BATULICIN | 150 | 195.3 | 8 | 2012 | 27 | 97200391BJM | YUDI GUNTARA | PKWTT | OPERATOR GI | GI BATULICIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-July-2020 | 10-Jun-2023 | 06 October 2026 | ||||||||||||||||||||||||||||||||||||||||
75 | 28 | UPT Banjarbaru | ULTG Barabai | GI Kandangan | 4 | 28 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | SEBERANG BARITO - KAYUTANGI | 150 | 37.7 | 3 | 2012 | 28 | 94231903BJM | MADI WIYANTO | PKWTT | OPERATOR GI | GI BATULICIN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 9-October-2023 | 30/05/2024 | 30 May 2027 | |||||||||||||||||||||||||||||||||||||||||
76 | 29 | UPT Banjarbaru | ULTG Bandarmasih | GI KAYUTANGI | 4 | 29 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | SEBERANG BARITO - SELAT | 150 | 83.5 | 7 | 1996 | 29 | 0020027KST | MALIK MAULANA | PKWTT | OPERATOR GI | GI BANGKANAI - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 10-February-2020 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
77 | 30 | UPT Banjarbaru | ULTG Banjar | GI MANTUIL | 4 | 30 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | SELAT - MINTIN | 150 | 59 | 4 | 1999 | 30 | 1919015KST | SUPERMAN | PKWTT | OPERATOR GI | GI BANGKANAI - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 2-August-2016 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
78 | 31 | UPT Banjarbaru | ULTG Bandarmasih | GI MARABAHAN | 4 | 31 | UPT BANJARBARU | ULTG BARABAI | SUTT | TANJUNG - BUNTOK | 150 | 157.4 | 6 | 2017 | 31 | 00201135BJM | ALVIN HIDAYAT | PKWTT | OPERATOR GI | GI BANGKANAI - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 11-January-2020 | 9-Mar-2024 | 3-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||
79 | 32 | UPT Banjarbaru | ULTG Barabai | GI PARINGIN | 4 | 32 | UPT BANJARBARU | ULTG BARABAI | SUTT | TANJUNG - KOMAM | 150 | 116.5 | 7 | 32 | 96221347BJM | MUHAMMAD PAHRIZA | PKWTT | OPERATOR GI | GI BANGKANAI - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 22-December-2022 | 27/03/2023 | 27 March 2026 | ||||||||||||||||||||||||||||||||||||||||||
80 | 33 | UPT Banjarbaru | ULTG Banjar | GI PELAIHARI | 4 | 33 | UPT BANJARBARU | ULTG BARABAI | SUTT | TANJUNG - TPI | 150 | 9.5 | 1 | 2021 | 33 | 8019014KST | MUHAMMAD NOOR | PKWTT | OPERATOR GI | GI BUNTOK - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 2-August-2016 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
81 | 34 | UPT Banjarbaru | ULTG Banjar | GI PLTA /Aranio | 4 | 34 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | TRISAKTI - SEBERANG BARITO | 150 | 10.7 | 1 | 1993 | 34 | 8819017KST | FAUZAN ZIKRI | PKWTT | OPERATOR GI | GI BUNTOK - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 2-August-2016 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
82 | 35 | UPT Banjarbaru | ULTG Batulicin | GI PULAU LAUT | 4 | 35 | UPT BANJARBARU | ULTG BANDARMASIH | SUTT | TRISAKTI - ULIN | 150 | 22.1 | 2 | 1994 | 35 | 9319035KST | MOCH NUR FUAD HASYIM | PKWTT | OPERATOR GI | GI BUNTOK - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 15-January-2017 | 10-Jun-2023 | 06 October 2026 | |||||||||||||||||||||||||||||||||||||||||
83 | 36 | UPT Banjarbaru | ULTG Barabai | GI RANTAU | 3 | 36 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Selat - Mintin 1 | 150 | 33.47 | 2016 | 36 | 01231890BJM | DWI SAIZ IRSYAD DATURANTE | PKWTT | OPERATOR GI | GI BUNTOK - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 1-October-2023 | 30/05/2024 | 30 May 2027 | ||||||||||||||||||||||||||||||||||||||||||
84 | 37 | UPT Banjarbaru | ULTG Batulicin | GI SATUI | 4 | 37 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Selat - Mintin 2 | 150 | 33.47 | 2016 | 37 | 99242063BJM | MUHAMMAD RADI | PKWTT | OPERATOR GI | GI KUALA KURUN - 150KV | 0040.Pj/HKM.02.01/F49000000/2024 | 2-May-2024 | 27/09/2024 | 27-Sep-2027 | ||||||||||||||||||||||||||||||||||||||||||
85 | 38 | UPT Banjarbaru | ULTG Bandarmasih | GI SEBERANG BARITO | 4 | 38 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Tanjung - Buntok 1 | 150 | 116.42 | 2017 | 38 | 02252160BJM | RIAN HABIBIE | PKWTT | OPERATOR GI | GI MUARA TEWEH - 150KV | 0040.PJ/HKM.02.01/F49000000/2024 | 2-January-2025 | ON PROGRESS | ON PROGRESS | ||||||||||||||||||||||||||||||||||||||||||
86 | 39 | UPT Banjarbaru | ULTG Bandarmasih | GI SEI TABUK | 4 | 39 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Tanjung - Buntok 2 | 150 | 116.42 | 2017 | 39 | 05242148BJM | FAHRI | PKWTT | OPERATOR GI | GI SKS - 150KV | 0040.PJ/HKM.02.01/F49000000/2024 | 23-December-2024 | ON PROGRESS | ON PROGRESS | ||||||||||||||||||||||||||||||||||||||||||
87 | 40 | UPT Banjarbaru | ULTG Barabai | GI TANJUNG | 4 | 40 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Buntok - Muara Teweh 1 | 150 | 117.04 | 2016 | 40 | 8619016KST | HERMAN | PKWTT | OPERATOR GI | GI KAYUTANGI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 2024-03-09 | 3-Sep-2027 | ||||||||||||||||||||||||||||||||||||||||||
88 | 41 | UPT Banjarbaru | ULTG Batulicin | GI Tarjun | 4 | 41 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Buntok - Muara Teweh 2 | 150 | 117.04 | 2016 | 41 | 8719019KST | RAHMAT ILHAMSYAH | PKWTT | OPERATOR GI | GI KAYUTANGI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 12-Sep-2022 | 09 December 2025 | ||||||||||||||||||||||||||||||||||||||||||
89 | 42 | UPT Banjarbaru | ULTG Bandarmasih | GI TRISAKTI 150 kV | 4 | 42 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Muara Teweh - Bangkanai 1 | 150 | 44.43 | 2016 | 42 | 9019018KST | DIMAS PRILIAN BUDHY | PKWTT | OPERATOR GI | GI KAYUTANGI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2027-09-02 | ||||||||||||||||||||||||||||||||||||||||||
90 | 43 | UPT Banjarbaru | ULTG Bandarmasih | GI TRISAKTI 70 kV | 4 | 43 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Muara Teweh - Bangkanai 2 | 150 | 44.43 | 2016 | 43 | 9719005KST | MUHAMMAD SAUKANI | PKWTT | OPERATOR GI | GI KAYUTANGI - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 10-June-2019 | 12-Sep-2022 | 09 December 2025 | ||||||||||||||||||||||||||||||||||||||||||
91 | 44 | UPT Banjarbaru | ULTG Bandarmasih | GIS ULIN/GI ULIN | 4 | 5 | 44 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Muara Teweh - Puruk Cahu 1 | 150 | 49.41 | 2020 | 44 | 1919001KST | SIGIT SATRIO AMIJOYO | PKWTT | OPERATOR GI | GI MANTUIL - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||
92 | 45 | UPT Banjarbaru | ULTG Batulicin | GI Sebuku | 45 | UPT PALANGKARAYA | ULTG MUARA TEWEH | SUTT | Muara Teweh - Puruk Cahu 2 | 150 | 49.41 | 2020 | 45 | 7219008KST | HUSIN | PKWTT | OPERATOR GI | GI MANTUIL - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||||
93 | 46 | UPT Banjarbaru | ULTG Batulicin | GI Sei Durian | 46 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Mintin - Sebangau | 150 | 84.47 | 2016 | 46 | 7719008KST | SUKRAN MAKMUN | PKWTT | OPERATOR GI | GI MANTUIL - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 7-Jul-2023 | 07 July 2026 | |||||||||||||||||||||||||||||||||||||||||||
94 | 47 | UPT Banjarbaru | ULTG Batulicin | GI Selaru | 47 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Mintin - Pulang Pisau | 150 | 13.04 | 1998 | 47 | 9419019KST | EKO PRASETYO | PKWTT | OPERATOR GI | GI MANTUIL - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 9-Feb-2024 | 2-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||||
95 | 48 | UPT Banjarbaru | ULTG Bandarmasih | GI SELAT | 4 | 48 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Pulang Pisau - Palangkaraya | 150 | 88.74 | 1998 | 48 | 1919006KST | HERI RAHMAN | PKWTT | OPERATOR GI | GI MARABAHAN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 22/11/2022 | 22-Nov-2025 | ||||||||||||||||||||||||||||||||||||||||||
96 | 49 | UPT Banjarbaru | ULTG Batulicin | GI BATULICIN 2 (baru) | 49 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Sebangau - Palangkaraya | 150 | 14.58 | 2016 | 49 | 7919012KST | ISWANDI | PKWTT | OPERATOR GI | GI MARABAHAN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 02/09/2024 | 2-Sep-2027 | |||||||||||||||||||||||||||||||||||||||||||
97 | 50 | 177 | 29 | 50 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Palangkaraya - Kasongan 1 | 150 | 66 | 2013 | 50 | 8520081KST | AKHMAD LAILI RAMADHAN | PKWTT | OPERATOR GI | GI MARABAHAN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 17-February-2020 | 10-Jun-2023 | 06 October 2026 | ||||||||||||||||||||||||||||||||||||||||||||
98 | 51 | 51 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Palangkaraya - Kasongan 2 | 150 | 66 | 2013 | 51 | 9620075KST | AHMAD SAFII | PKWTT | OPERATOR GI | GI MARABAHAN - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 17-February-2020 | 10-Jun-2023 | 06 October 2026 | ||||||||||||||||||||||||||||||||||||||||||||||
99 | 52 | 52 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Kasongan - Sudan | 150 | 64.11 | 2014 | 52 | 7619011KST | HARUN | PKWTT | OPERATOR GI | GI SEBERANG BARITO - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 27/03/2023 | 27 March 2026 | ||||||||||||||||||||||||||||||||||||||||||||||
100 | 53 | 53 | UPT PALANGKARAYA | ULTG PALANGKARAYA | SUTT | Sudan - Sampit | 150 | 42.96 | 2022 | 53 | 7719009KST | HAIRADI | PKWTT | OPERATOR GI | GI SEBERANG BARITO - 150KV | 0041.Pj/HKM.02.01/F49000000/2024 | 1-March-2014 | 09/12/2022 | 09 December 2025 | ||||||||||||||||||||||||||||||||||||||||||||||