ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
2
HARGA POKOK PEKERJAAN
3
4
PEKERJAAN : Renovasi Toilet Gedung Widya Graha Lantai 1 dan Lantai 2
5
LOKASI : BRIN KS GATOT SUBROTO, JAKARTA
6
TAHUN : 2025
7
8
NOURAIANSATUANVOLUME HARGA SATUAN JUMLAH HARGA HARGA TOTAL
9
(Rp) (Rp) (Rp)
10
IPERSIAPAN
11
1Sewa Scafoldingset6 270.000 1.620.000
12
2Banner SEDANG ADA RENOVASIBh2 150.000 300.000
13
3Terpal PlastikM210 35.000 350.000
14
4Buang PuingRitase4 350.000 1.400.000
15
5Karung BekasBh100 1.500 150.000
16
17
JUMLAH I 3.820.000
18
IIPEMASANGAN HOMOGENOUS TILE
19
1HT Lantai 60 x 60 Sandimas PIANMO MATTDus41 220.580 9.043.780
20
2HT Dinding 60 x 60 Sandimas SATURIO WHITEDus128 207.795 26.597.760
21
3Granit Meja Wastafel ( Mas Bagong )M111 1.400.000 15.400.000
22
23
JUMLAH II 51.041.540
24
IIIPEMASANGAN PLAFON
25
1Gypsum Board 9 mmLbr14 66.000 924.000
26
2Hollow 4 x 4Btg30 32.000 960.000
27
3Hollow 2 x 4Btg15 37.000 555.000
28
4Kassa GypsumRol5 8.000 40.000
29
5Skrub GypsumDus4 65.000 260.000
30
6Paku BetonDus1 45.000 45.000
31
7Compound Sak3 65.000 195.000
32
8Metal StudBtg20 32.000 640.000
33
34
JUMLAH III 3.619.000
35
IVSANITARY
36
1Closet Duduk CW421JW/FUnit2 2.425.000 4.850.000
37
2Urinoir Type Muslim U57MW/FUnit6 2.083.000 12.498.000
38
3Wastafel LW 625 JUnit3 4.435.560 13.306.680
39
4Jet Washer THX20MCRBUnit6 330.000 1.980.000
40
5Floor Drain TX1DBUnit7 353.000 2.471.000
41
6Tempat TissueUnit9 214.000 1.926.000
42
7Handryer TYC322WFUnit3 4.329.000 12.987.000
43
8Tempat SabunUnit5 118.800 594.000
44
9CerminUnit8 545.000 4.360.000
45
11SealtapeRol10 5.000 50.000
46
12T Join THX58Bh6 105.000 630.000
47
48
JUMLAH IV 55.652.680
49
VPARTISI KACA TEMPERET
50
1Pemasangan Kaca Temperet (Pa Tino )m222 2.245.000 49.390.000
51
2Sticker Sunblasm222 95.000 2.090.000
52
53
JUMLAH V 51.480.000
54
VIELEKTRIKAL
55
1Lampu down Light Philips 9 watt Type eridaniBh16 95.000 1.520.000
56
2Exaust FanBh6 450.000 2.700.000
57
3Stop Kontak PanasonikBh3 35.000 105.000
58
4Kabel NYM 3x1,5Rol1 1.800.000 1.800.000
59
5SolasiRol5 10.000 50.000
60
6LasdopBks2 35.000 70.000
61
7T dusBh25 3.500 87.500
62
8Pipa KonduitBtg30 12.000 360.000
63
64
JUMLAH VI 6.692.500
65
VIIMATERIAL LAIN LAIN
66
1Pasirengkel1 800.000 800.000
67
2Semen PortlandSak50 48.000 2.400.000
68
3Mortar Pasang keramikSak75 110.000 8.250.000
69
4Nat keramikKg10 15.000 150.000
70
5Paku BetonDus1 80.000 80.000
71
6Potong GerindaBh2 120.000 240.000
72
7Fleksibel BilimaBh10 15.000 150.000
73
8Troli SorongUnit 400.000 -
74
9Sika TopSak 350.000 -
75
10Cat Eco Emulsion Propan PutihPail1 760.000 760.000
76
11KuasBH4 15.000 60.000
77
12Rol CatBh2 25.000 50.000
78
79
JUMLAH VII 12.940.000
80
81
VIIIJASA TUKANG
82
1JASA BORONG PAK DARMANTOLs2 12.000.000 24.000.000
83
84
JUMLAH VIII 24.000.000
85
86
REKAPITULASI
87
1JUMLAH TOTAL 185.245.720
88
2BIAYA OVER HEAD5% 9.262.286
89
3JASA TUKANG 24.000.000
90
SUB TOTAL 218.508.006
91
92
93
94
95
96
97
98
99
100