ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
DATEDESCRIPTIONAMOUNT
2
3
FFE
4
8/1/2022FFE Equipment Purchases$12,367.46
5
7/21/2022FFE Equipment Purchases$1,645.09
6
6/14/2022FFE Equipment Purchases$1,493.99
7
5/31/2022Studio Lighting Deposit$33,000.00
8
6/14/2022Lighting Infrastructure Final payment$8,750.00
9
5/10/2022ECO Tints - Detinting Windows$750.00
10
5/13/2022FFE Equipment Purchases$2,508.85
11
2/7/2022Lighting Infrastructure Deposit$25,000.00
12
2/7/2022Security System Deposit$4,410.00
13
Total FFE$89,925.39
14
15
Building Contract
16
6/1/2022APPL 9 May 2022$133,877.15
17
5/1/2022APPL 8 April 2022$273,280.18
18
4/12/2022APPL 7 March 2022$121,785.40 *
19
4/6/2022APPL 6 February 2022$480,893.10
20
3/30/2022APPL 5 January 2022$167,598.62
21
1/24/2022APPL 4 December 2022$220,456.71
22
12/22/2021APPL 3 November 2021$209,439.22
23
12/1/2021APPL 2 October 2021$130,238.22
24
11/5/2021APPL 1 Sept 2021$66,353.65
25
Total Building Contract paid $1,803,922.25
26
27
Outstanding Billing
28
29
7/1/2022APPL 10 June 2022$69,784.96
30
31
Total Change Orders
32
PCO 1 - Material escalation$27,221.25
33
PCO 2 - Roof Replacement$29,735.00
34
PCO 3 - 2 Structural LVL Posts$2,531.00
35
PCO 4 - Roof Abatement$11,259.00
36
PCO 5 - New Water Service$20,229.00
37
PCO 6 - Rot Repair$23,306.48
38
PCO 8 - 4 Structural LVL Posts$4,950.00
39
PCO 10 - Roof Rot Repair$9,500.00
40
PCO 12 - Door for Studio$6,789.20
41
PCO 13 - Rot Repair$5,998.80
42
PCO 15 - Credit, Quiet Floor System
($3,346.00)
43
PCO 16 - Roof Rot Repair($6,320.00)
44
PCO 18 - Insulation Upgrade $979.00
45
PCO 20 - Control 115 Track Lighting
$1,254.00
46
PCO 21 - Added Power Requirements
$2,662.00
47
PCO 22 - Studio beam wraps$4,790.76
48
PCO 23 - Added header 2nd
floor
$4,771.00
49
PCO 24 - Reception Millwork$3,152.00
50
PCO 25 - Concrete Utility Pad$2,514.00
51
PCO 26 - Masonry Repointing$1,210.55
52
PCO 27 - BDA closet Framing$3,640.00
53
PCO 28 - Materials$13,069.47
54
PCO 29 - Temp Sub-Panels$1,320.00
55
PCO 34 - Painting additions$2,362.80
56
Total Aproved COs$173,579.31
57
58
59
Outstanding Change Orders
60
PCO 11 - Framing Materials Overage
$16,347.58
61
PCO 14 - Revision to PCO 11($1,551.00)
62
PCO 17 - Rot Repair$9,930.80
63
Total Outstanding COs$24,727.38
64
65
Remaining Costs
66
67
68
Building Contract$1,820,778.00
69
Change Orders$198,306.69
70
Total Building$2,019,084.69
71
72
Payments$1,803,922.25
73
Balance Remaining$215,162.44
74
75
76
Additional Building Costs Due
77
Security System and Installation$4,410.00
78
Architect$1,144.00 *
79
OPM$17,333.80
80
FFE Budget$148,000.00
81
Lighting$32,000.00
82
Sign$7,000.00
83
Total Additional Costs$209,887.80
84
85
Total Project Cost Remaining$425,050.24
86
87
Building account balance$242,027.88
88
89
Loan Expendatures
90
5/2/2022Closing Costs$15,510.25
91
92
Construction Loan
93
5/2/2022Draw 1$100,000.00
94
5/12/2022Draw 2$212,790.43
95
6/27/2022Draw 3$133,877.15
96
Total Loan
$462,177.83
97
98
99
100