SINGLE FAMILY HOME DEVELOPMENT PROJECT
6
FINANCIAL PRO FORMA SUMMARY
7
8
PROJECT COSTSFINANCIAL SUMMARY
9
10
ACQUISITION COSTSTotalUses of FundsTotal
11
Land cost $ 30,000 Acquisition Costs $ 38,350
12
Broker fees $ 2,500 Hard Costs $ 298,298
13
Survey (ALTA) $ 500 Soft Costs $ 51,150
14
Appraisal $ 350 Total Uses of Funds $ 387,798
15
Closing costs, legal fees, title $ 5,000
16
Total Acquisition Costs $ 38,350 Sources of FundsTotal
17
Construction Loan $ 329,628
18
HARD COSTSTotalEquity Investment $ 58,170
19
Site work and temporary utilities3,800Total Sources of Funds $ 387,798
20
Excavation and foundations26,400
21
Flatwork and slabs14,600
22
Framing, roof, windows and siding48,200
23
Rough plumbing, electrical and HVAC (MEPs)32,300
24
Insulation and drywall18,200
25
Floors, doors and interior trim24,350
26
Kitchen and bathrooms27,480
27
Electrical fixtures8,800
28
Plumbing fixtures2,850
29
Paint and clean7,900
30
Appliances4,300
31
HVAC systems (furnace and air conditioning)5,200
32
Garage (turn-key)28,500
33
Exterior features and lighting6,900
34
Utility connections2,800
35
Read deck and patio6,800
36
Landscaping1,800
37
Contingency (10%)27,118
38
TOTAL HARD COSTS $ 298,298
39
40
SOFT COSTSTotal
41
Architecture & engineering (MEP, struct, landscp)7,500
42
Surveys800
43
Soils reports1,200
44
Permit fees4,500
45
Legal1,200
46
Builders risk and general liability insurance2,500
47
Third-party inspection fees850
48
Property taxes during construction500
49
Accounting and bookkeeping250
50
Municipal impact fees2,200
51
Financing fees and interest reserve25,000
52
Soft Cost contingency (10%)4,650
53
TOTAL SOFT COSTS $ 51,150
54
55
TOTAL PROJECT COST $ 387,798
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
HARD COSTSTotal
87
PROPERTY 1 - SITE WORK
88
Demolition, site clearing and fencing (budget)
89
Earthwork, grading, site work (budget)
90
Temporary utilities
91
Civil and infrastructure
92
General conditions
93
Sub Total - Site Work
94
95
PROPERTY 1 - BUILDINGS "A" & "B" - STUDENT HOUSING
96
Building "A" vertical construction
97
Building "B" vertical construction
98
Parking lot and exterior features (budget)
99
Landscaping, exterior lighting and signage (budget)
100
Contingency