A | C | D | E | F | G | H | I | J | K | L | M | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | R-Track - reporting issuse and status | ||||||||||||
2 | |||||||||||||
3 | # | LB | Stage1: Data Collection from the field by Surveyors Stage2: Verification of collected data in the field with the map by Surveyors themselves Stage3: Verification of tracked data jointly by Assistant Engineer along with ward members Stage4: Random cross check of the tracked data in the field by Assistant Executive Engineer Stage5: Renumbering / Renaming of the road by Considering the connectivity, ownership, etc For Approval by LSGI Committee / Board. Publication of the tracked map details. | Issues | Remarks | ||||||||
4 | Stage 1 % completed | Stage 2 % completed | Stage 3 % completed | Stage 4 % completed | Stage 5 % completed | Login Issues - (Access denied for AE) | Verification Issues | ||||||
5 | reasons | others | reasons | others | |||||||||
6 | Kilimanoor BP | 0 | 0 | 0 | 0 | 0 | ​ | 0 | ​ | 0 | 0 | ||
7 | Pazhayakunnummel GP | ​ | ​ | ||||||||||
8 | Kilimanoor GP | ​ | ​ | ||||||||||
9 | Madavoor GP | ​ | ​ | ||||||||||
10 | Pallikkal GP | ​ | ​ | ||||||||||
11 | Pulimath GP | ​ | ​ | ||||||||||
12 | Nagaroor GP | ​ | ​ | ||||||||||
13 | Navaikulam GP | ​ | ​ | ||||||||||
14 | Karavaram GP | ​ | ​ | ||||||||||
15 | |||||||||||||
16 | |||||||||||||
17 | Chirayinkeezhu BP | ​ | ​ | ||||||||||
18 | Chirayinkeezhu GP | ​ | ​ | ||||||||||
19 | Kizhuvillam GP | 100 | ​ | ​ | |||||||||
20 | Vakkom GP | 100 | ​ | ​ | |||||||||
21 | Anchuthengu GP | ​ | ​ | ||||||||||
22 | Kadakkavur GP | 100 | 100 | 100 | ​ | Application getting crashed with or without message | |||||||
23 | Mudakkal GP | 100 | ​ | ​ | Survey has been done using Rtrack and by Grameena Patana kendram. Request has been given to use the shape file from Grameena patana kendram. The shape file has not been uploaded to ksrec server, hence survey activities are on hold. | ||||||||
24 | |||||||||||||
25 | |||||||||||||
26 | Vellanad BP | others | ​ | ||||||||||
27 | Kattakkada GP | 100 | 15 | Specific software / mobile issue | The app crashes befoe saving the edited data | Access denied issues . Not able to edit the ownership details. Rtrack app logs out and crashes automatically | |||||||
28 | Poovachal GP | ​ | ​ | ||||||||||
29 | Vellanad GP | 100 | 10 | 0 | ​ | ​ | |||||||
30 | Tholikkode GP | 100 | 100 | 60 | ​ | ​ | |||||||
31 | Uzhamalakkal GP | 100 | 10 | 0 | ​ | ​ | In the online at field- The tracked road is unable to be loaded to edit | ||||||
32 | Aryanad GP | 100 | 50 | ​ | ​ | ||||||||
33 | Kuttichal GP | 100 | ​ | ​ | Survey conducted by Grameena padana kendram, Shape file uploaded, But roads not shown in rtrack app | ||||||||
34 | Vithura GP | 100 | 10 | 3 | Specific software / mobile issue | The app crashes befoe saving the edited data | Rtrack app logs out automatically | ||||||
35 | |||||||||||||
36 | |||||||||||||
37 | Vamanapuram BP | ​ | ​ | ||||||||||
38 | Vamanapuram GP | 100 | 25 | 5 | ​ | Application getting crashed with or without message | |||||||
39 | Nellanad GP | 100 | ​ | ​ | The shape file of the Roads mapped by Grameena Padana Kendram has been uploaded.as the number of roads including those on R track is doubling, request submitted to exclude other roads. | ||||||||
40 | Nanniyode GP | 100 | 25 | 5 | ​ | Application getting crashed with or without message | Also tracked roads are not loading for verification and at editing time, road details changing | verification ongoing | |||||
41 | Pangode GP | 100 | 100 | 20 | 0 | 0 | ​ | others | |||||
42 | Kallara GP | ​ | ​ | ||||||||||
43 | Manikkal GP | 100 | 10 | 2 | 0 | 0 | ​ | ​ | |||||
44 | Pullampara GP | 100 | 100 | others | ​ | The shape file of the Roads mapped by Grameena Padana Kendram has been uploaded. As the number of roads is doubling. Request submitted to exclude roads tracked through R track | |||||||
45 | Peringammala GP | 100 | 5 | others | acess denied for overseer and ae | ​ | |||||||
46 | |||||||||||||
47 | |||||||||||||
48 | Varkala BP | ​ | ​ | ||||||||||
49 | Manambur GP | 100 | 80 | 80 | 0 | 0 | ​ | ​ | Multiple road entry to be deleted | ||||
50 | Vettoor GP | 100 | 100 | 100 | 0 | 0 | ​ | ​ | |||||
51 | Cherunniyoor GP | 100 | 40 | 40 | 0 | 0 | ​ | ​ | Survey conducted by Grameena padana kendram, Shape file uploaded, But roads not shown in rtrack app | ||||
52 | Ottur GP | 100 | 45 | 30 | 0 | 0 | Specific software / mobile issue | Less number of roads is listed than the actually tracked roads | |||||
53 | Chemmaruthy GP | 100 | 90 | 90 | 0 | 0 | ​ | ​ | |||||
54 | Elakamon GP | 100 | 100 | 100 | 0 | 0 | ​ | ​ | AE level Verification through KSREC website ongoing | ||||
55 | Edava GP | 100 | 100 | 100 | 0 | 0 | ​ | ​ | |||||
56 | |||||||||||||
57 | |||||||||||||
58 | Nedumangad BP | ​ | ​ | ||||||||||
59 | Karakulam GP | 100 | Cannot add / relieve surveyors | ​ | |||||||||
60 | Vembayam GP | ​ | ​ | ||||||||||
61 | Anad GP | ​ | ​ | ||||||||||
62 | Panavoor GP | ​ | ​ | ||||||||||
63 | Aruvikkara GP | ​ | ​ | ||||||||||
64 | |||||||||||||
65 | |||||||||||||
66 | Nemom BP | ​ | ​ | ||||||||||
67 | Kalliyoor GP | 100 | 100 | 100 | 0 | 0 | Specific software / mobile issue | ​ | |||||
68 | Balaramapuram GP | 100 | 100 | 100 | 0 | 0 | ​ | ​ | |||||
69 | Pallichal GP | 100 | 100 | 0 | 0 | 0 | ​ | ​ | Tracking done through external agency | ||||
70 | Maranalloor GP | 100 | 100 | 0 | 0 | 0 | others | ​ | |||||
71 | Malayinkeezhu GP | 100 | 100 | 100 | 0 | 100 | Invalid PEN | ​ | enable option not working .informed the authority | ||||
72 | Vilappil GP | 100 | 100 | 20 | others | The offline method is taking more than 5 minties to 30 minutes in some areas | |||||||
73 | Vilavoorkal GP | 100 | 100 | 100 | ​ | ​ | |||||||
74 | |||||||||||||
75 | |||||||||||||
76 | Pothencode BP | ​ | ​ | ||||||||||
77 | Andoorkonam GP | 80 | 60 | 0 | others | unable to add surveyors | ​ | Road survey is going on | |||||
78 | Pothencode GP | ​ | ​ | ||||||||||
79 | Kadinamkulam GP | 100 | 100 | 100 | ​ | ​ | Currently no issues regarding the R-track | ||||||
80 | Mangalapuram GP | 100 | 100 | 90 | ​ | ​ | |||||||
81 | Azhoor GP | 100 | 100 | 85 | Specific software / mobile issue | In the online at field- The tracked road is unable to be loaded to edit | In the online at field- The tracked road is unable to be loaded to edit | ||||||
82 | |||||||||||||
83 | |||||||||||||
84 | Perumkadavila BP | ​ | ​ | ||||||||||
85 | Perumkadavila GP | 100 | 50 | 0 | 0 | 0 | others | ​ | currently verification cannot be done, editing not possible,App is automatically closing after some seconds of login | ||||
86 | Kunnathukal GP | 100 | 95 | 0 | 0 | 0 | ​ | ​ | Cuurrently Verification cannotbe done Newly tracked roads not showing in roads with in 25km | ||||
87 | Kollayil GP | 100 | 40 | 40 | ​ | ​ | Currently no issues regarding the R-track | ||||||
88 | Vellarada GP | 100 | 100 | 0 | 0 | 0 | ​ | ​ | survey done by external agency.Hence shape file provided to KSREC, but only few tracked roads are being shown(under process as informed) | ||||
89 | Aryancode GP | ​ | ​ | ||||||||||
90 | Amboori GP | 100 | 30 | 10 | 0 | 0 | ​ | ​ | The app gets stuck while doing verification. Net work issue on various places. | ||||
91 | Kallikadu GP | 100 | 100 | 10 | 0 | 0 | Cannot add / relieve surveyors | ​ | 1 .Surveyed road within 25km is not showing in the appwhile checking the actual site 2 . App is automatically closing after some seconds of login 3 . Hence the details of the existing(survyed) roads can't be verified and approved | ||||
92 | Ottasekharamangalam GP | 100 | 100 | 10 | others | Less number of roads is listed than the actually tracked roads | 1. Tracking of all roads have been completed, but showing only few of them. Whether there roads need to be tracked again???, 2.The app keeps on getting stuck while doing verification process. | ||||||
93 | |||||||||||||
94 | |||||||||||||
95 | Parassala BP | ​ | ​ | ||||||||||
96 | Parassala GP | ​ | ​ | ||||||||||
97 | Chenkal GP | ​ | ​ | ||||||||||
98 | Kulathoor GP | ​ | ​ | ||||||||||
99 | Karode GP | ​ | ​ | ||||||||||
100 | Poovar GP | 100 | 100 | 50 | ​ | Less number of roads is listed than the actually tracked roads | IN Verification by the Assistant Engineer PAGE SOME ROADS ARE UNABLE TO EDIT ( LOCKED ) |