PROJECT (with # days estimated)TARGET DATESSTATUS
2
ONGOING & AS TIME PERMITS
3
Add blazing to trails where needed (Chipmunk, Flying Squirrel)
4
Maintenance projects identified by BAT Comm. members and Trail Adopters
5
MARCH
6
BAT Comm. approve priorities; announce Forum6-MarComplete
7
Confirm trail adopters from 2022 to 2023Complete
8
Assess/close trails for mud season: Pine Bluff, Hemlock Heights, Pikes Creek1-AprComplete
9
APRIL
10
Initiate chainsaw program recruitment & trainingIn progress
11
Recruit and sign up new adopters & volunteers (release forms)Complete (could add co-adopters)
12
MAY
13
Trails Forum: 9 a.m. to noon6-May
14
Continue volunteer recruitment and sign up for sesasonOngoing
15
Complete Adopt-a-Trail monitoring reports15-MayDate extended to June 1 due to snowpack
16
Assess and open trails (post on website & social media)May 15Done
17
JUNE
18
Finish and drainage work on Hatchery to AWB Trail (3 days)TBDSome work completed by Will Krift; additional work deferred to fall
19
Big Ravine Trail maintenance s needed: Gil Larsen, Pine Bluff, Hem. Heights,West Rim6/1 - 6/11Complete
20
Gil Larsen Trail: boardwalk and other repairs between trailhead and platform (4 days) (dates may change)6/16 -6/25Complete plus repaired collapsed stairway on Lower Gil Larsen
21
Siskiwit Preserve: clear orchardJune 15Complete
22
JULY
23
Meme Miikana bridge: clear access to bridge site 7/5 - 7/15Completed on 7/7
24
AUGUST
25
Complete Adopt-a-Trail monitoring reports1-Augsome reports not rec'd as of 8/13
26
School trail hill stabilization & restoration (2-3 days) (contractor)8/14 - 8/16Completed by Bay Area Environmental Consultants
27
Clear encroaching brush on Jerry Jolly Trail8/9BATs volunteers assist County
28
Develop connection to AWB trailhead/parking lot (4 days)August - OctoberApproved by County' To be completed by Doug Olson with machinery
29
Launch Trails Economic & Social Impact Study: recruit volunteers to conduct interviews at trailheadsTBDPaused due to delay in WCMP funding - this could take as long as a year. JEM grant received but also paused awaiting WCMP funds.
30
Big Ravine Headwaters: Build trails and viewing platform (8 days); install directional and interpretive signage; develop connection to the Wineries.8/8 - 12: establish base trail; by 8/19: paint kiosk & install signs; 8/26 -27: build viewing platform; TBD: build boardwalk on pond overlook trail. Completed on 9/9/23. Over 100 volunteer hours from 15 volunteers. Special thanks to Bob Feyen for leading construction of the viewing platform & Kris Wegerson & John Ipsen for leading trail crews and installing signage.
31
Meme Miikana: Anderson Bridges install bridgeinstalled 8/30/23Delayed due to lack of equipment; installed 8/30/23. Further finish work forthcoming in September.
32
Lost Creek Falls: gravel in low areas; build fences in select spots to curtail cutting across switchbacks; install USNG emergency response signs; install benchesTBD
33
SEPTEMBER
34
Meme Miikana: Construct boardwalk across the floodplain, box steps, boardwalk across seep (8 - 10 days)Complete! Bravo volunteers!Ted May & Sean Reagan Lead
35
Siskiwit XC Trails: Fill low spots with gravel/wood chips; Cut select trees; assist county with widening trailsOngoing
36
Siskiwit River Preserve trail improvements: add steps to trail along creek; clear encroaching vegetation; spread gravel.CompleteCompleted 9/5/23
37
Initiate Red Cliff Trails Plan (TAP grant approved)Initiate in SeptemberRFP issued; responses due 10/6/23;
38
OCTOBER
39
Complete Adopt-a-Trail monitoring reports15-Oct
40
Pileated Woodpecker/Meme Miikana: Finish and drainage work on Hatchery to AWB Trail (3 days)Week of 10/23 - 10/28Some work completed by Will Krift in spring; additional work deferred to fall
41
Complete Pikes Bridge installation, including on ramp and stepsBy 11/1/23
42
Brownstone Trail: add gravel and clear ditching near Wild Rice Retreat; augment gravel near steps south of Blue Wing Bay Rd.By mid-November; date TBDNorthland College not available: they have changed their approach to service days.
43
Jerry Jolly Trails: Re-establish the trail connection from the “Overlook” to the Jolly Long; install signage (5 days)Deferred to 2024Consider clearing this year; add footbridge next year with County assistance
44
Add gravel to select locations on upper East Rim TrailDeferred to 2024
45
NOVEMBER
46
Brownstone Trail: Build new "box steps" to replace asphalt ramp at the lower end of 7th St. (tentative)11/1 - 11/3
47
Rehab. access trail to the Pikes Creek bridge and PIlleated Woodpecker/Meme MiikanaBy mid-November
48
Install signs along Pileated Woodpecker/Meme Miikana (1 day)By mid-Novemberinstall when signs are available
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100