FDP Form 7 - 20% Component of IRA Utilization
2
20% COMPONENT OF THE IRA UTILIZATION
3
FOR THE THIRD QUARTER, CY 2021
4
5
Province, City or Municipality:
Buhi, Camarines Sur
6
7
Program or ProjectLocationTotal CostDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
8
% of CompletionTotal Cost Incurred to Date
9
SOCIAL DEVELOPMENT
10
2017 Fund:
11
1. Improvement of Rural Health Unit Building (RHU II) San Jose (Baybayon), Buhi, Camarines SurP/ 1,000,000.00 25-Jan-2119-Apr-21100%P/ 999,515.62 -100% Completed
12
13
14
15
2018 Fund:
16
1. Barangay Assistance for Social Development ProjectsBuhi, Camarines Sur 1,500,000.00 Oct. 2018-80% 960,633.78 -On-going
17
18
2. Site Development of Rural Health Unit Building (Phase II)Infront of Office on Agricultural Services (OAS), San Buena, Buhi, Camarines Sur 1,000,000.00 13-Jan-20-70% 694,487.51 -Suspended due to lot boundary negotiation
19
20
21
22
23
3. Rehabilitation of Existing Buhi Public MarketBuhi, Camarines Sur 1,000,000.00 27-Oct-2003-Feb-21100% - -100% Completed
24
25
26
2019 Fund:
27
1. Barangay Assistance for Social Development Projects to 19 Barangay BeneficiariesBuhi, Camarines Sur 1,900,000.00 Mar. 2020-50%--On-going
28
29
30
2. Construction of Multi-Purpose Technical Building (Phase I)Old Municipio Building, Sta. Elena, Buhi, Camarines Sur 4,000,000.00 23-Sep-2018-May-21100% 2,597,799.42 - 100% Completed
31
32
33
34
Page 1 of 5 Pages
35
FDP Form 7 - 20% Component of IRA Utilization
36
20% COMPONENT OF THE IRA UTILIZATION
37
FOR THE THIRD QUARTER, CY 2021
38
39
Province, City or Municipality:
Buhi, Camarines Sur
40
41
Program or ProjectLocationTotal CostDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
42
% of CompletionTotal Cost Incurred to Date
43
3. Installation of Solar Powered Streetlighting FacilitiesPoblacion Area, Buhi, Camarines SurP/ 999,928.80 23-Mar-21-80%P/ 751,056.60 - On-going
44
45
46
47
4. Rehabilitation of 36 units Existing StreetlightsAlong Iriga - Buhi Road, Sta. Justina (Zone 1 & Portion of Zone 2), Buhi, Camarines Sur 1,000,000.00 11-Jan-2123-Mar-21100% 738,655.40 - 100% Completed
48
49
50
51
5. Construction / Rehabilitation / Extension of Existing LGU - Owned Potable Water Supply SystemDe La Fe & Salvacion, Buhi, Camarines Sur 1,650,000.00 22-Feb-21-90% 1,155,562.51 - On-going
52
53
54
55
6. Construction / Rehabilitation / Extension of Existing LGU - Owned Potable Water Supply SystemSan VIcente, Buhi, Camarines Sur 469,399.00 01-Feb-2118-Feb-21100% 458,709.65 - 100% Completed
56
57
58
59
7. Construction / Rehabilitation / Extension of Existing LGU - Owned Potable Water Supply SystemLabawon, Buhi, Camarines Sur 663,052.84 07-Jun-2115-Jul-21100% - - 100% Completed
60
61
62
63
8. Construction / Rehabilitation / Extension of Existing LGU - Owned Potable Water Supply SystemCabugkot Spring, Monte Calvario, Buhi, Camarines Sur 399,596.88 23-Apr-2121-May-21100% 199,668.00 -100% Completed
64
65
66
67
68
Page 2 of 5 Pages
69
FDP Form 7 - 20% Component of IRA Utilization
70
20% COMPONENT OF THE IRA UTILIZATION
71
FOR THE THIRD QUARTER, CY 2021
72
73
Province, City or Municipality:
Buhi, Camarines Sur
74
75
Program or ProjectLocationTotal CostDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
76
% of CompletionTotal Cost Incurred to Date
77
9. Repair / Rehab. Of Water SystemTambo - Burocbusoc, Buhi, Camarines SurP/ 828,082.00 07-Jun-21-50%P/ - - On-going
78
79
80
81
82
2020 Fund:
83
1. Replacement / Rehabilitation of 144 units Existing StreetlightsAlong Buhi - Iriga Road, Sta. Justina (Portion of Zone 2, Zone 3, 5 & 6), Lourdes (Zone 1 & 3), Sagrada (Zone 3 & 4) & San Jose (Baybayon), Portion of Zone 1, Buhi, Camarines Sur 4,000,000.00 01-Mar-2117-Sep-21100% 2,954,621.60 - 100% Completed
84
85
86
87
88
89
90
91
92
93
94
2. Construction / Installation of Potable Water SystemLabawon, Buhi, Camarines Sur 300,000.00 07-Jun-2128-Jun-21100% - - 100% Completed
95
96
97
3. Installation of Level 2 Potable Water Supply SystemTambo - Burocbusoc, Buhi, Camarines Sur 150,000.00 28-Jun-21-80% 114,680.00 - On-going
98
99
100