Facilities Project Status List
2
Measure G Projects
3
Date: 01/27/2021Color: Green - On time, Yellow - Delay, Orange - On Hold, White - Completed
4
School% CompleteProjectStatus
5
Alma Preschool80%ModernizationDrawings are complete for the modernization project. The contractor installed 2nd exit doors for Rooms 2-4, and new wall partitions in Room 5 for counselors. Three of the four retractable awnings were installed to provide shade in play yard. The last awning requires a custom attachment detail and DSA approval. The Facilities staff planned for a shade structure over play structure in lieu of 4th retractable awning. Shade structure installation completed in December 2019.
6
Elementary SchoolsCastro Valley 79%ModernizationInterior renovations for Classroom 5-7 completed December 2019. Interior renovations for Classroom 11-13 completed in Spring 2020. Exterior painting, furniture installation, and interior renovation for Classroom 1-4, 14-18, and admin offices completed Summer 2020. Classroom 8-10 & MPR completed December 2020. Solar array installed and waiting for PG&E connection.
7
Chabot79%ModernizationWork completed Summer 2018: PG&E service upgrade for new HVAC; interior improvements to rooms 1,7, and 27-30; and new play equipment and turf surface installation at the Upper Grade Play Area. The facilities staff put the project out for bid in October 2018 and received one bid that was unresponsive. Project has been re-bid as multi-prime contracts to mitigate delays. Interior improvements for rooms 2-6, and 8 completed spring 2019. Teachers will move from the portables back into their classrooms in June 2019. Work completed for summer 2019 include interior improvements for classrooms 12-15, 17-19, 22-23, office rooms 10-11; kindergarten playground soft fall material replacement; and painting of interior doors in the main office. Interior painting for the restrooms and interior hallway will be completed winter 2019. Interior painting for the MPR planned for spring 2020. Solar array installation and furniture installation completed in summer 2020, waiting for PG&E connection. Currently working on exterior painting. The following scope of work planned for Summer 2021: using the interim housing portables to replace the old classroom portables 24-26, ramp replacements to classrooms 27-29, new covered walkway, and restroom window replacement. Staff is reviewing proposals using lease-leaseback delivery method for the project.
8
Independent68%ModernizationInterior renovations for Classroom 24-27 completed in December 2019. Interior removations for classrooms 9-12 completed Spring 2020. Exterior painting, technology infrastructure upgrade, furniture installation, and interior renovations for Classrooms 19-23 completed summer 2020. HVAC installation and electrical service upgrade completed October 2020. Solar array installed and waiting for PG&E connection. Currently working on MPR flooring.
9
Marshall73%ModernizationThe architect submitted plans to DSA on 1/24/18. The architect split the modernization project into two project increments in order to expedite the DSA approval process. Increment one calls for the modernization of the kindergarten wing (A) and was approved by DSA in August 2018. Increment two calls for the expansion of the Multipurpose Room, was rejected by DSA due to an incomplete submittal process. DSA required additional documentation for the new fire hydrant and structural upgrades for the MPR building expansion which made the project cost increase beyond project budget. The architect has revised the scope of work for increment two based on the 6/28/18 board meeting to design an outdoor multipurpose area in lieu of the MPR expansion. The facilities staff put the incremement one project out for bid in October 2018 and received one bid that was unresponsive. The facilities staff bid interior painting, flooring, and window shades for Kindergarten wing separately to expedite work. This work finished mid February, and staff moved in 1st weekend of March. Classrooms 9-13 have moved into the interim housing portables, and construction for interior improvements began during spring break and finished in June 2019. Teachers moved from the portables back into classrooms before summer vacation. Interior improvements for Classrooms 14-17, and painting of MPR and Library completed August 2019. Flooring replacement for MPR and interior renovations for Classrooms 19-21 completed summer 2020. HVAC installation completed October 2020. Exterior painting of MPR completed December 2020. Solar array installed in December 2020 and waiting for PG&E connection.
10
Palomares90%ModernizationModernization work completed include: security camera replacement; exterior and interior painting, installation of flooring in the office, library, science, and room 1 & 5; upgrades to the play structure safety surfacing, and re-paving staff parking lot. Electrical switchgear installed in September, and final inspection has been completed. PG&E scheduled to power up switchgear end of December 2019. HVAC upgrades completed Spring 2020. Technology infrastructure upgrade and furniture installation completed summer 2020.
11
Elementary SchoolsProctor 80%ModernizationInterior renovation for Classroom 1-7 completed Winter 2019. Exterior painting, technology infrastructure upgrade, furniture installation, and interior renovations for Classrooms 8-14 and library completed summer 2020. HVAC installation completed September 2020. Electrical service upgrade will be complete by November 2020. Interior renovations for Classrooms 21, 22A, & 22B completed Fall 2020. Solar array installed in December 2020 and waiting for PG&E connection. Currently working on interior renovations, exterior repair and painting, site drainage for Classrooms 16-20. Future planned scope includes: shade structure, amphitheather, and replacing old classroom portables with interim housing portables. Staff is reviewing proposals using lease-leaseback delivery method for the project.
12
Stanton74%ModernizationThe project received DSA approval in July 2018. The facilities staff put the project out for bid in October 2018 and received one bid that was unresponsive. The facilities staff bid interior painting, flooring, and window shades for classrooms 6-10 separately to expedite work. Construction for interior improvements on classrooms 6-10 started during spring break and finished June 2019 for teachers to move back into their classrooms before summer vacation. Work completed for summer 2019 include: interior improvements for classrooms 4-5, & 11-13, and kindergarten playground soft fall material replacement. Interior renovations for Classroom 17-21 completed December 2019. Technology infrastructure upgrade, furniture installation, and interior renovations for classrooms 3, 22, & MPR completed summer 2020. HVAC installation and electrical service upgrade completed September 2020. Solar array installed in December 2020 and waiting for PG&E connection. Currently working on exterior painting.
13
Vannoy 70%Interim Housing & AmphitheaterCalifornia Geological Survey (CGS) recently revised maps of the school site, and the review indicated the site to be in a liquefaction zone. With further investigations, the geotechnical engineer reported, contrastingly, that the areas of work are not in a liquefaction zone. The Mobile Modular interim housing classroom delivery and set up was completed in early October. Site work and utility connection project for interim housing was grouped with the outdoor multi-purpose area as one DSA submittal package to utilize the same ADA access points. DSA submittal was on April 2019, and project approval was received in August 2019. Staff had bid project and received 1 bid which was 51% over budget. Staff worked with contractor on value engineering cost to get it closer to budget. Staff has recommended board approved to proceed with project because re-bidding would not have produced favorable results. Construction is planned to start November 2019 and completed for December 2020.
14
ModernizationClassroom 3 & 9 completed summer 2019. HVAC installation, exterior painting, and interior renovations for Classroom 4-8 completed summer 2020. Concrete and asphalt paving in front of school completed Fall 2020. Solar array installed in December 2020 and waiting for PG&E connection.
15
Jensen Ranch68%ModernizationContractor completed additional HVAC upgrades to classrooms. Technology infrastructure upgrade completed summer 2020. Exterior painting completed September 2020. Solar array installed in December 2020 and waiting for PG&E connection.
16
Middle SchoolsCanyon 50%ModernizationDSA approval was received 1/5/18. Project was first bid in February and received 5 bids. There was a bid protest that lead to questions of whether the lowest bidder was responsive and responsible. The District decided to reject all bids and re-bid the project. The project has now been awarded to a contractor. Work completed includes modernization in Wing H, & I; interior improvements to Wing G and Library; ADA pathway improvements; and exterior painting. Modernization of Wing B, and HVAC installation on Wing G & Library is complete. Phase 3 of modernization planned for summer 2021. Staff is reviewing proposals using lease-leaseback delivery method for the project.
17
Sports FieldCVUSD (Castro Valley Unified School District) is in negotiations with HARD (Hayward Area Recreation District.) CVUSD & HARD staffs had met to review final schematic design plans and cost estimates from the architects. Community and Joint Board meetings were held in October 2017. CVUSD & HARD board approved of schematic design during October 2017 meeting. HARD proposed $7 million in property taxes would be used to help the District renovate fields. HARD applied for a $4 million grant from the Wayne and Gladys Valley Foundation that required a $4 million (can not use bond funds) match. Staff is also looking at grant opportunities for additional funding.
18
Creekside90%Sports FieldSurvey demonstrated CVUSD owns nearly three additional acres between the park and the Creekside fields. School board approved of grant to fund design for athletic field expansion into unused district parcels. Additional space to upgrade fields, add parking, improve drop off/pickup and add restrooms at Creekside. District is partnering with the Priem Family Foundation to renovate the fields at Creekside. Architect submitted to DSA for plan check review on 6/25 but was rejected. Design team addressed DSA comments on first submittal and resubmitted to DSA mid-August for review. Design team is working on a re-design to meet the new budget.
19
ModernizationThe architect submitted Phase 1 drawings to DSA for plan check 5/16/18 and received approval 10/4/18. The project received bids in late November 2018, and contract was approved by school board in January 2019. Modernization work started February 2019 and was completed summer 2019 in A & B Wing. Phase 2 modernization drawing was submitted to DSA on 4/18/19. Architect has received DSA approval in September. Contractor completed punch list items and project close out.
20
High SchoolsCVHS45%200 & 300 Building ModernizationDrawings received DSA plan check approved 4/21/20 and planned for construction start summer 2021. Staff is reviewing proposals using lease-leaseback delivery method for General Contractor on the project.
21
Redwood 59%ModernizationThe architect submitted to DSA on 1/18/18 and approval was received in July of 2018. Interior improvements for Room 15 and pathway improvements from lower campus to parking lot was completed summer 2019. HVAC upgrades completed Spring 2020. Interior renovations on classrooms 6-14 completed summer 2020.