T&C Requirement Compliance Sheet
2
Sr. No.Test DescriptionFATSAT
3
SPRINKLER SYSTEM
4
1Physical inspection and specs. Verification - This has to be carried out as per the Pre-Cx check sheet given in the commissioning plan/method statement.
5
2Pressure testing - For Pipe works pressure test to be done at 13.8 kg/cm² for 2hrs. without any pressure drop as per NFPA 13 followed by line flushing.
6
3Flow Switch Operation Verification - Open the drain valve of the system and allow the water to pass from the line and observe the alarm / hooter or water flow status
in BMS system.
7
4Integration with Land lord - Verify the alarms ON BMS status of flow switches and
tamper switches of landlord systems.
8
HYDRANT SYSTEM
9
1Physical inspection and specs. Verification - This has to be carried out as per the Pre-Cx check sheet given in the commissioning plan/method statement.
10
2Pressure testing - For Pipe works pressure test to be done at 13.8 kg/cm² for 2hrs. without any pressure drop as per NFPA 13 followed by line flushing.
11
FIRE-EXTINGUISHERS
12
1Installation Verification as per approved layout
13
14
EXIT SIGNAGES
15
1Installation verification as per approved layout
16
17
NOTE: Factory Acceptance Testing (FAT) and Site Acceptance Testing (SAT)
18
19
Test Instrumentation Required/Considered For SAT
20
Sr. No.DescriptionQty.SAT
21
1True RMS Multi-meter1 No.
22
2Pressure Gauge1 No.
23
3Hydraulic Pump1 No.
24
4dB Meter1 No.
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100