GANTT CHARTNote: Task dependencies are based on PERT and CPM principles. All phases are to be completed in order. Certain tasks within each phase will need to be completed based on what other tasks they are dependent on in that phase.
3
4
PROJECT TITLETraffic and Tribulations: How Hoboken Traffic Laws Have Impacted Road SafetyDesign VI Group:Group 1
5
PROJECT MEMBERSAlex Beke, Victoria Beke, Zoe Casten, Jason Pinga, Alejandro SchnettlerDATE4/29/23
6
7
8
TASK NUMBERTASK TITLETASK DEPENDENCIESSTART DATEDUE DATEDURATIONPCT OF TASK COMPLETEPHASE ONEPHASE TWOPHASE THREEPHASE FOUR
9
WEEK 1WEEK 2WEEK 3WEEK 4WEEK 5WEEK 6WEEK 7WEEK 8WEEK 9WEEK 10WEEK 11WEEK 12
10
MTWRFMTWRFMTWRFMTWRFMTWRFMTWRFMTWRFMTWRFMTWRFMTWRFMTWRFMTWRF
11
1
Project Conception and Initiation
12
1.1Project Charter and Mission Statement1.2-1.59/22/2310/6/23140%
13
1.1.1Project Charter Revisions1.110/6/2312/22/23760%
14
1.2Problem Formulation--9/1/239/8/2370%
15
1.3Project Goals1.29/8/239/15/2370%
16
1.4Stakeholders1.29/8/239/15/2370%
17
1.5Guidelines--Project Framework1.39/15/2309/22/202370%
18
1.6Project Initiation1.1-1.510/6/2310/13/2370%
19
2Project Definition and Planning
20
2.1Meeting Schedules and Establishing Communication Channels--9/1/239/8/2370%
21
2.2Project Scope--Refine Problem and Goals110/13/2310/20/2370%
22
2.3Solution Development2.210/20/2310/27/2370%
23
2.4Risk Identification and Mitigation2.310/27/2311/4/2370%
24
2.5Budget2.1-2.411/4/2311/11/2370%
25
3Project Synthesis / Analysis
26
3.1Refine Solution Statement211/11/2311/18/2370%
27
3.2Information Gathering110/13/233/8/241450%
28
3.2.1Independent Investigations--10/13/233/8/241450%
29
3.3Specific Project Milestones211/11/2311/18/2370%
30
3.3.1Completion Projections--11/11/2305/02/20241710%
31
3.4Project Documentation--11/11/2305/02/20241710%
32
3.4.1Document Gathered Information3.210/13/233/8/20241450%
33
3.4.2Data Analysis and Visualization3.4.13/8/243/29/24210%
34
3.4.3Project Updates--11/11/2305/02/20241710%
35
3.4.4Design Diagrams and Analysis3.13/8/244/12/24340%
36
4
Project Performance / Monitoring
37
4.1Project Objectives311/11/2305/02/20241710%
38
4.2Data Model Verification and Validation3.4.13/29/2405/02/2024330%
39
4.3Cost Tracking2.511/11/2305/02/20241710%
40
4.4Project Performance3.1, 3.3, 3.4.411/11/2305/02/20241710%
41