A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | 2003 TMP lists as required by 2013 and not | |||||||||||
2 | .. yet built or planned for by 2015 (2012 view) | |||||||||||
3 | …the cost estimates were from a 2003 | |||||||||||
4 | ...document used as input to 2003 TMP | |||||||||||
5 | ||||||||||||
6 | Road Description | Needed By | Needed By | Completed | 2003 Cost | Act Cost | Inside | Outside | ||||
7 | (2003 TMP | (2008 TMP | Estimate | Greenbelt | Greenbelt | |||||||
8 | View) | View) | ||||||||||
9 | ||||||||||||
10 | Richmond (Carling-Golden) 2/3->4 | By 2008 | By 2031 | 20 | 20 | |||||||
11 | Carling (Richmond-Acres) 4->6 | By 2008 | not in plan | 15 | 15 | |||||||
12 | Albert (Empress-Booth) 4->6 | By 2008 | not in plan | 1.4 | 1.4 | |||||||
13 | Strandherd (Greenbank-RideauR) 2->4 | By 2008 | 21 | 21 | ||||||||
14 | …shortened to (Woodroffe-PoW) - 4-lanes | By 2008 | By 2015 | |||||||||
15 | … & Greenbank-Woodroffe | By 2031 | ||||||||||
16 | New East-West Rd (RideauR to 417E) | By 2008 | - | ?? | ?? | |||||||
17 | AVC (Nicholas-Riverside) | by 2013 | By 2022 | 30 | 30 | |||||||
18 | Armstrong (Limebank-Albion) 2->4 | By 2013 | By 2031 | 37 | 37 | |||||||
19 | Armstrong (Albion-Bank) 2 | By 2013 | By 2031 | 13 | 13 | |||||||
20 | Hunt Club (416-RideauR) 4->6 | By 2013 | By 2031 | 27 | 27 | |||||||
21 | Hunt Club (RideauR-Bank) 4->6 | By 2013 | By 2031 | 18 | 18 | |||||||
22 | Hunt Club (Hawthorne-417E) 4->6 | By 2013 | not in plan | 35 | 35 | |||||||
23 | New East-West Rd (RideauR to 416) | By 2013 | - | ?? | ?? | |||||||
24 | Innes-Walkley Connection - 2lanes | By 2013 | 6 | 6 | ||||||||
25 | ….delayed and extended to 417/HuntClub | By 2022 | ||||||||||
26 | BlackburnHamlet Bypass 4->6 | By 2013 | By 2031 | 9.3 | 9.3 | |||||||
27 | Coventry Rd (Belfast-StLaurent) 2->4 | By 2013 | By 2031 | 2.6 | 2.6 | |||||||
28 | PoW (Merivle-Woodroffe) 2->4 | By 2013 | By 2022 | 44 | 100 | 100 | PoW from Strandherd to Merivale appears in 2015 plan | |||||
29 | Riverside Dr (Heron to Brookfield) 4->6? | By 2013 | not in plan | ?? | ?? | |||||||
30 | ||||||||||||
31 | 69 | 266.3 | <- 2003 view of Roads needed by 2013 but not | |||||||||
32 | ...built or in the 2012-2014 plan as of 2011 | |||||||||||
33 | Not listed in 2003 TMP as needed but is | |||||||||||
34 | ...listed as needed in 2008 TMP by 2015 | |||||||||||
35 | ...but is not in 2012-2015 plan (2012 view) | |||||||||||
36 | ||||||||||||
37 | …no cost estimates available for these roads | |||||||||||
38 | ||||||||||||
39 | Belcourt Blvd 2->4 lanes + extend to Mer Bleue | not in plan | By 2015 | |||||||||
40 | Blackburn Hamlet Bypass: Navan-10thline-Trim | not in plan | By 2015 | |||||||||
41 | Portobello Blvd (Charest to BHBypass) 2->4 | not in plan | By 2015 | |||||||||
42 | Trim Rd (Innes-BHBP) 2->4 | not in plan | By 2015 | |||||||||
43 | Golf Club Way (Jinkinson-Dwyer Hill) 2 lanes | not in plan | By 2015 | |||||||||
44 | Chapman Mills (Woodroffe-Strandherd) 4 lanes | not in plan | By 2015 | |||||||||
45 | Longfield extension to Jock R. 2 lanes | not in plan | By 2015 | |||||||||
46 | ||||||||||||
47 | 2003 TMP view of Roads needed 2013-2021 | |||||||||||
48 | ...OR new in 2008 TMP (ie were not | |||||||||||
49 | ... mentioned in 2003 TMP) and 2008 TMP | |||||||||||
50 | ... says needed 2023-2031 | |||||||||||
51 | skip to bottom of document for a detailed | |||||||||||
52 | ... listing of road projects in this category | |||||||||||
53 | ||||||||||||
54 | The following sections detail roads built since | |||||||||||
55 | ...2003 and those planned for 2012 to 2015 | |||||||||||
56 | Needed | Needed | Completed | 2003 Cost | Act Cost | InsideGB | OutsideGB | |||||
57 | (2003 TMP) | (2008 TMP) | ||||||||||
58 | 2013-2015 Planned Construction (2012 View) | |||||||||||
59 | 2012Cost | |||||||||||
60 | View | |||||||||||
61 | Greenbank (Malvern-Nep S.) 2->4 | by 2013 | By 2015 | 2013 | 20 | 20 | ||||||
62 | Mer Bleue (Innes-Navan) 2->4 | by 2021 | By 2015 | 2013/2014 | 5 | 5 | ||||||
63 | Earl Grey/Centrum underpass | not in plan | By 2022 | 2013 | 4 | 4 | Not in 2011 plan, added in 2012 | |||||
64 | 10th Line Rd (Innes-FutureSt 31) | not in plan | completed? | 2013/14 | 9 | 9 | <--By 2011 8M had already been spent | |||||
65 | BHBP Ext (Navan to 10th Line) 2 lanes | not in plan | By 2015 | 2014 | 17 | 17 | ||||||
66 | Campeau (Huntmar-Kanata) 2 lanes | not in plan | By 2015 | 2014 | 32 | 32 | ||||||
67 | Fallowfield (CedarView-Greenbank) 2->4 | by 2013 | completed? | 2014 | 13 | 13 | ||||||
68 | Kanata Ave/Goulbourn Forced Rd EA only? | not in plan | By 2015 | 2014 | 12 | 12 | ||||||
69 | Strandherd (fallowfield-Jockvale) | notinplan | By 2022 | 2014 | 11 | 11 | Not in 2011 plan, added in 2012 | |||||
70 | Hope Side Rd (Richmond-Moodie) | by 2021 | ?? | 2015 | 17 | 17 | Not in 2011 plan, added in 2012 | |||||
71 | Jockvale Rd (JockR-PoW) | by 2021 | By 2022 | 2015 | 13 | 13 | in 2011 plan as 2013, in 2012 plan as 2015 | |||||
72 | Prince of Wales (Strandherd-Merivale) | not in plan | not in plan? | 2015 | 45 | 45 | Not in 2011 plan, added in 2012 | |||||
73 | Greenbank (S. of Cambrian for 1.7km) | not in plan | By 2022 | 2015 | 5.8 | 5.8 | Not in 2011 plan, added in 2012 | |||||
74 | 174 (Split to Trim) | by 2021 | by 2022 | 2015 | 5.1 | 5.1 | Not in 2011 plan, added in 2012 | |||||
75 | Limebank (Spratt to EarlArmstrong) | not in plan | By 2015 | ?? | 8 | 8 | <--Got money in 2010 but project not started as of 2011 | |||||
76 | Rideau St Reconstruction | 2012/13 | 2.6 | 2.6 | Assumed 20% of total sewer/water project | |||||||
77 | On The Move - Accelerated Road (Sewer) rehabs | 2014 | 36 | 36 | Assumed 20% of total sewer/water project | |||||||
78 | On the Move - Accelerated repaving, bridge repairs | 2014 | 89 | 20 | 69 | Assumed some bridge repairs inside greenbelt | ||||||
79 | 58.6 | 285.9 | <-Roads in the plan for 2011-2014 | |||||||||
80 | ||||||||||||
81 | ||||||||||||
82 | Needed | Needed | Completed | 2003 Cost | Act Cost | InsideGB | OutsideGB | |||||
83 | (2003 TMP) | (2008 TMP) | ||||||||||
84 | Partially Built as of 2011 | |||||||||||
85 | ||||||||||||
86 | Greenbank (NepS. To Cambrian) 2->4 | Pre2013 | 36 | 36 | <- to be completed as far as Malvern by 2013 | |||||||
87 | Strandherd (RideauR to Woodroffe) 4 | Pre2008 | 13.3 | 13.3 | <- Completed from Woodroffe to PoW by 2009 | |||||||
88 | Strandherd (Woodroffe-Greenbank) 2->4 | Pre2013 | 10 | 10 | <_ Completed from Longfields to Woodroffe by 2009 | |||||||
89 | ||||||||||||
90 | 2012 | |||||||||||
91 | Altavista Corridor - Hospital Link | 2005 | 2012 | 30 | 65 | 65 | ||||||
92 | Trim Road (174-Innes) | by 2021 | by 2015 | 2012 | 24 | 24 | ||||||
93 | St Joseph (10th line to Dairy Rd) 2->4 | by 2021 | by 2022 | 2012 | 6.5 | 6.5 | ||||||
94 | ||||||||||||
95 | ||||||||||||
96 | 2011 | |||||||||||
97 | Hunt Club interchange with 417E | 2005 | 2011 | 72 | 72 | |||||||
98 | ||||||||||||
99 | ||||||||||||
100 | 2010 |