Completed Projects 2012-2014Last Updated: 7.17.14 by YH

.

Project ID #Project TitleDescriptionDate Requested:Requested By:Target Date: Type:Date Completed:Month Completed:Funding SourceCurrent PhaseProject Leader(s)StaffNotes:

.

Infrastructure and System Integration Projects:

.

.

142In Your ClassOIT participated in the meetings regarding the rollout of In Your Class as well as promotional aspects of the launchFall 2012CUNYFall 2012System Integration November 2012November 2012No CostCompletedMark Kam, Youssef ElhajjiDeputy CIO, ISS

.

.

139Wingate Hall WiFi ImprovementWi-i improvement for the Wingate 112 suite-Networking group installed and tested the APs
08.30.13Mario Crescenzo, Director of Business and Finance12.30.12Infrastructure 12.30.12December 2012Funded by the Finance Dept. CompletedJonathan ZhaoISS

.

.

106Campus-Wide Lab Upgrades Cabling, new data/voice portsStarting Summer 2012VariousOngoingInfrastructure VariousFebruary 2013VariousCompletedYoussef Elhajji, Marta BialekISS, PMO

.

.

138Live@CCNY/CitymailNew student email systemAugust 2012Praveen Panchal, OIT, VP and CIO01.28.13System Integration 01.28.13January 2013Tax LevyCompletedMark KamPMO, ISS, CSS

.

.

136Wingate Cabling UpgradeMario Crescenzo requested additional network ports in the inner offices (Wingate 112)
February 2013Mario Crescenzo, Director of Business and Finance03.06.13Infrastructure 03.06.13March 2013Funded by the Finance Dept. CompletedJoe DengISS

.

.

132NextBus for the TowersNextBus display for the Towers11.05.12Kern Williams, Director of Housing & Residence LifeSpring 2013System Integration 04.03.13April 2013Tax LevyCompletedMark KamISS, PMO

.

.

133Research Administration-Active DirectoryActive Directory deployment in the office of Research AdministrationNovember 2012Adam Greenberg, Research Administration, Acting DirectorApril 2013Infrastructure 04.04.13April 2013No CostCompletedYoussef Elhajji, Vern BallardISS, CSS

.

.

113Bomgar Appliance Test and research the appliance which allows remote web login. Setup devices and apply licenses February 2013Praveen Panchal, OIT, VP and CIOSpring 2013Software Upgrade05.31.13May 2013Tax LevyCompletedYoussef ElhajjiISSCompleted. Bomgar agents will be installed campus wide

.

.

108Harris Hall 06 Student LoungeNetworking and cabling upgrade for HH 06, new hardware and software installations/recommendations07.16.12Sophie Davis SchoolSpring 2013Infrastructure June 2013June 2013Funded by the Sophie Davis SchoolCompletedYoussef Elhajji, Marta BialekISS, PMO

.

.

143Encase ImplementationE-Discovery setupFall 2012Praveen Panchal, OIT, VP and CIOSpring 2013Infrastructure 07.22.13July 2013Tax LevyCompletedYoussef ElhajjiISS07.22.13-4 hr setup/training with Encase completed

.

.

107Graduate Lab UpgradeHardware-12 new PCs, networking and cabling upgrade done by OIT's cabling unit03.15.13President's OfficeSpring 2013Infrastructure 06.01.13June 2013Tax LevyCompletedYoussef ElhajjiISS, ITBS, PMOCabling by OIT-TBD

.

.

146President's Conference Room-AV UpgradeAudio-visual system upgradeMay 2013President's Conference Room08.09.13System Integration 08.16.13August 2013President's OfficeCompletedNana AbeyieITMSS08.16.13 Facilities has been informed to move the old display and touch-up painting, move furniture back into place

.

.

151NAC 7/312-AV SetupNew audio-visual equipment for NAC 7/312. Room is being converted into a classroom07.15.13Debbie Hartnett, Senior Advisor to the President and Chief of Staff08.15.13System Integration 08.20.13August 2013President's OfficeCompletedNana AbeyieITMSS, PMO08.20.13 Vendor replaced the pipe, PMO informed Facilities to install a ceiling quad power outlet.

.

.

125Fishbowl Computer LabComputer lab upgrade. Hardware, software. VDI solutionFall 2012President's OfficeFall 2013Infrastructure 09.09.13September 2013Tax LevyCompletedYoussef ElhajjiISS, CSS112 PCs have shipped. VDI solution has been implemented. Waiting for locks to be delivered and installed 09.06.13

.

.

102Sys AidCampus-Wide Ticketing System, Reporting July 2013Praveen Panchal, OIT, VP and CIOFall 2013System Integration 10.21.13October 2013Tax Levy CompletedVern BallardCSS, ISS, PMOSysAid has launched on 09.23.13

.

.

124Crossroads Network Upgrade, Phase llAdditional upgrade following Phase l 7.24.3Florian LengyelFall 2013System Integration 10.31.13October 2013Tax Levy CompletedYoussef ElhajjiISS2 switches shipped

.

.

156Engineering Adjunct Training for Fall 2013Train engineering students to improve their teaching skills.
Workshops are being developed specifically for Engineering adjuncts. Blackboard site will created
April 2013The Engineering DepartmentNovember 2013Training/Hybrid Learning12.12.13December 2013No CostCompletedNatalia KapliCETLDeveloping workshops. Creating Blackboard site

.

.

169Career Center/Fast TrackExpansion of the City College Careers and Professional Development Institute10.25.13President Lisa S CoicoFall 2013Infrastructure12.20.13December 2013TBDCompletedYoussef Elhajji ISS4 computers were setup, phones were moved

.

.

165Welcome Center / ID OfficeRelocating the ID office to the Welcome Center in 1/205 Sept 2013O'Lanso GabbidonSpring 2014Infrastructure3.27.14March 2014Student AffairsCompletedOtto MarteISS, PMO

.

.

147Shepard 107 Webcast SystemData and phone for the new center. Webcasting system for SH 10706.21.13Robert Santos, VP for Campus Planning & FacilitiesSpring 2014System Integration 5.16.14May 2014FacilitiesCompletedNana AbeyieITMSS, PMO5.16.14, ENO board installed and projectors setup

.

.

149Marshak 117 Audio Visual UpgradeImplement an Audio Visual system 06.26.13Praveen Panchal, OIT, VP and CIO08.23.13System Integration 8.27.14August 2014Tax Levy CompletedNana AbeyieITMSS, PMO

.

.

129Campus Wide Classroom Phones155 phones are needed to supply each classroom on campus with a phone. Survey was done by OIT's cabling unit.Fall 2012Praveen Panchal, OIT, VP and CIOTBDInfrastructure10.16.14October 2014TBDCompletedJoe DengISS

.

.

150NAC 6/105Implement an Audio Visual system. Cabling and networking aspects07.02.13Shakila Merchant, NOAA CREST, Assistant DirectorWinter 2014System Integration 01.13.15January 2015NOAA CRESTCompletedNana AbeyieITMSS, ISS, PMO