1 | ||||||||||||||
2 | PROGRES HARIAN PELAYANAN TEKNIK UPJ MENGANTI | |||||||||||||
3 | MARET 2012 | |||||||||||||
4 | ||||||||||||||
5 | TGL | INSPEKSI | RABAS POHON | UKUR TRAFO | HARDUDU | TGL | KETERANGAN | |||||||
6 | TARGET : | 43.53 | TARGET : | 861 | TARGET : | 74 | TARGET : | 74 | DAFTAR NOMOR GARDU | |||||
7 | (Kms) | AKUMULASI | POHON | AKUMULASI | UNIT | AKUMULASI | UNIT | AKUMULASI | PENGUKURAN GARDU | INSPEKSI & PEMELIHARAAN GARDU | ||||
8 | 1 | 0 | 0 | 1 | - | - | ||||||||
9 | 2 | 0 | 0 | 0 | 0 | 0 | 2 | - | - | |||||
10 | 3 | 0 | 0 | 0 | 0 | 0 | 3 | - | - | |||||
11 | 4 | 0 | 0 | 0 | 0 | 0 | 4 | - | - | |||||
12 | 5 | 0 | 0 | 0 | 0 | 0 | 5 | - | - | |||||
13 | 6 | 0 | 0 | 0 | 0 | 0 | 6 | - | - | |||||
14 | 7 | 0 | 0 | 1 | 1 | 0 | 7 | '442 | - | |||||
15 | 8 | 0 | 0 | 0 | 1 | 0 | 8 | - | - | |||||
16 | 9 | 0 | 0 | 8 | 9 | 0 | 9 | 362;428;246;311;344;345;462;510 | - | |||||
17 | 10 | 0 | 0 | 0 | 9 | 0 | 10 | - | - | |||||
18 | 11 | 0 | 0 | 0 | 9 | 0 | 11 | - | - | |||||
19 | 12 | 0 | 0 | 9 | 18 | 0 | 12 | 390;225;266;267;268;297;461;601;615 | - | |||||
20 | 13 | 0 | 0 | 6 | 24 | 0 | 13 | 579;535;354;289;290;658 | - | |||||
21 | 14 | 0 | 0 | 0 | 24 | 0 | 14 | - | - | |||||
22 | 15 | 0 | 0 | 0 | 24 | 0 | 15 | - | - | |||||
23 | 16 | 0 | 0 | 0 | 24 | 0 | 16 | - | - | |||||
24 | 17 | 0 | 0 | 0 | 24 | 0 | 17 | - | - | |||||
25 | 18 | 0 | 0 | 0 | 24 | 0 | 18 | - | - | |||||
26 | 19 | 0 | 0 | 0 | 24 | 0 | 19 | - | - | |||||
27 | 20 | 0 | 0 | 1 | 25 | 0 | 20 | - | - | |||||
28 | 21 | 0 | 0 | 25 | 2 | 2 | 21 | - | RB453;RB300 | |||||
29 | 22 | 0 | 0 | 12 | 37 | 5 | 7 | 22 | RB;903;RB856;RB799;RB732;RB574;RB545;RB436;RB407;RB377;RB321;RB285;RB258; | RA452;RA227;RA231;RA283;RA285 | ||||
30 | 23 | 0 | 0 | 37 | 7 | 23 | - | - | ||||||
31 | 24 | 0 | 0 | 37 | 7 | 24 | - | - | ||||||
32 | 25 | 0 | 0 | 37 | 7 | 25 | - | - | ||||||
33 | 26 | 0 | 0 | 37 | 7 | 26 | - | - | ||||||
34 | 27 | 0 | 0 | 37 | 7 | 27 | - | - | ||||||
35 | 28 | 0 | 0 | 37 | 7 | 28 | - | - | ||||||
36 | 29 | 0 | 0 | 37 | 7 | 29 | - | - | ||||||
37 | 30 | 0 | 0 | 37 | 7 | 30 | - | - | ||||||
38 | 31 | 0 | 0 | 37 | 7 | 31 | - | - | ||||||
39 | JUMLAH | 0 | 0.00% | 0 | 0.00% | 37 | 50.00% | 7 | 9.46% | JUMLAH | ||||
40 | ||||||||||||||
41 | Progres Pekerjaan | |||||||||||||
42 | ||||||||||||||
43 | PROGRES | INSPEKSI | RABAS POHON | UKUR GARDU | HARDUDU | |||||||||
44 | 26 - 29 FEB | 0 | 0 | 0 | 0 | |||||||||
45 | 01 - 25 MAR | 0 | 0 | 37 | 7 | |||||||||
46 | JUMLAH | 0 | 0.00% | 0 | 0.00% | 37 | 50.00% | 0 | 0.00% |