A | B | D | E | G | H | N | O | |
---|---|---|---|---|---|---|---|---|
1 | Division 3 | |||||||
2 | Auburn University | |||||||
3 | Building Science Department | |||||||
4 | Contractor: BSCI 3450-002 | |||||||
5 | Project: Auburn Building Science Demo Lab Slab | |||||||
6 | SS | Material | ||||||
7 | Ref | Item | No | Unit | Unit Cost | Extension | Total | |
8 | 310 | Concrete Formwork | ||||||
9 | 2'x4' Forms @ Exterior | 144 | LF | $2.17 | $39.06 | $39.06 | ||
10 | 2'x4' Forms @ Keyway | 80 | LF | $2.17 | $21.70 | $21.70 | ||
11 | 2'x4' @Splice | 24 | LF | $2.17 | $6.51 | $6.51 | ||
12 | 2'x4' Stakes | 24 | LF | $2.17 | $6.51 | $6.51 | ||
13 | Metal Stakes | 100 | EA | $3.97 | $99.25 | $99.25 | ||
14 | Drywall Screws | 2 | EA | $22.00 | $44.00 | $44.00 | ||
15 | Layout String (400LF) | 1 | EA | $10.37 | $10.37 | $10.37 | ||
16 | String Level | 1 | EA | $2.57 | $2.57 | $2.57 | ||
17 | Wood Half Round | 80 | LF | $0.41 | $32.80 | $32.80 | ||
18 | Wood Blade | 1.00 | EA | $10.99 | $10.99 | $10.99 | ||
19 | Hammer | 2.00 | EA | $27.68 | $55.36 | $55.36 | ||
20 | Sledge Hammer- 8lb double face | 1.00 | EA | $42.00 | $42.00 | $42.00 | ||
21 | Drill- Black & Decker 12volt 5/8 in. | 1.00 | EA | $43.00 | $43.00 | $43.00 | ||
22 | Extension Chord- 50ft | 1.00 | EA | $32.00 | $32.00 | $32.00 | ||
23 | Finishing Nails - 3in galvanized | 1.00 | EA | $5.00 | $5.00 | $5.00 | ||
24 | Concrete Formwork Totals | $451.12 | $451.12 | |||||
25 | ||||||||
26 | 320 | Concrete Reinforcing | ||||||
27 | ||||||||
28 | #3 Rebar @ 24" O.C | 1200 | LF | $0.38 | $460.20 | $460.20 | ||
29 | Rebar Chairs @ 5' | 240 | EA | $0.50 | $120.00 | $120.00 | ||
30 | Tie Wire (400 ft rolls) | 1 | EA | $6.00 | $6.00 | $6.00 | ||
31 | Wire Cutters | 2 | EA | $13.00 | $26.00 | $26.00 | ||
32 | Rebar Cutter | 1 | EA | $160.00 | $160.00 | $160.00 | ||
33 | Concrete Reinforcing Totals | $626.20 | ||||||
34 | ||||||||
35 | 330 | Cast-in Place Concrete | ||||||
36 | ||||||||
37 | 4000 psi Concrete @ S.O,G w/ 10% waste | 17.00 | CY | $88.24 | $1,500.08 | $1,500.08 | ||
38 | Bull Float (float, handle, bracket) | 1.00 | EA | $117.00 | $117.00 | $117.00 | ||
39 | Trowels- 14"x4" | 2.00 | EA | $19.00 | $38.00 | $38.00 | ||
40 | Edgers- 6"x4" | 2.00 | EA | $8.00 | $16.00 | $16.00 | ||
41 | Finish Trowel- 4in Steel | 3.00 | EA | $18.00 | $54.00 | $54.00 | ||
42 | Concrete Broom w/ handle | 1.00 | EA | $104.00 | $104.00 | $104.00 | ||
43 | 2'x12' Wood Screed (Spruce) | 1.00 | EA | $6.00 | $6.00 | $6.00 | ||
44 | Wheel Barrow | 1.00 | EA | $55.00 | $55.00 | $55.00 | ||
45 | Quikrete Cure & Seal- (200 sf/gal) | 6.00 | Gal | $26.00 | $156.00 | $156.00 | ||
46 | Garden Sprayer- for curing compound | 1.00 | EA | $18.00 | $18.00 | $18.00 | ||
47 | Skill Saw- inccluding 1 blade | 1.00 | EA | $98.00 | $98.00 | $98.00 | ||
48 | Come-along | 2.00 | LF | $30.00 | $60.00 | $60.00 | ||
49 | ||||||||
50 | Cast-in-place Concrete Totals | $2,258.08 | $2,222.08 | |||||
51 | ||||||||
52 | 335 | Miscellaneous Tools | ||||||
53 | 100 ft Tape Measure= Lufkin | 1.00 | EA | $18.00 | $18.00 | $18.00 | ||
54 | Hose | 50.00 | LF | $0.60 | $30.00 | $30.00 | ||
55 | Shovel= 48" steel blade round point (rent) | 2.00 | EA | $16.00 | $32.00 | $32.00 | ||
56 | Chalk Line (Blue)- 100ft | 1.00 | EA | $8.50 | $8.50 | $8.50 | ||
57 | Concrete Rake | 1.00 | EA | $30.00 | $30.00 | $30.00 | ||
58 | 5 gallon buckets | 5.00 | EA | $2.60 | $13.00 | $13.00 | ||
59 | ||||||||
60 | ||||||||
61 | Personal Protective Equipment | $131.50 | $131.50 | |||||
62 | ||||||||
63 | Hard Hats | |||||||
64 | Safety Glasses | 20.00 | EA | $3.00 | $60.00 | $60.00 | ||
65 | Gloves | 20.00 | EA | $2.50 | $50.00 | $50.00 | ||
66 | Concrete Boots | 3.00 | EA | $18.00 | $54.00 | $54.00 | ||
67 | Safety Vests | 2.00 | EA | $5.00 | $10.00 | $10.00 | ||
68 | Gatorade(76.5oz mix)- makes 9gal. (Including Ice) | 1.00 | EA | $17.00 | $17.00 | $17.00 | ||
69 | -use water from site for water/gatorade | |||||||
70 | Snack Allowance | 20.00 | EA | $5.00 | $100.00 | $100.00 | ||
71 | PPE Totals | $191.00 | $291.00 | |||||
72 | ||||||||
73 | Total Price | $3,721.90 | ||||||
74 | Price Less Accounted Items (Red) | $2,913.23 | ||||||
75 | ||||||||
76 | ||||||||
77 | No. | Additive Alternate | No. | Unit | Material | |||
78 | Unit cost | |||||||
79 | ||||||||
80 | 1 | Metal Screed | 1 | EA | $155.84 | |||
81 | 2 | Mock-Up Slab (10'x10' material) | 1.22 | CY | $350.00 | |||
82 | 3 | Gravel (3 trucks) | 3 | EA | $1,950.00 | |||
83 | 4 | Demo Hill- (Bobcat Rental) | 1 | CY | $350.00 | |||
84 | 5 | New Jobsite Sign- (custom sign) | 1 | EA | $328.70 | |||
85 | -Could contact University for possible new sign | |||||||
86 | 6 | Engraving Plate | 1 | EA | $38.56 | |||
87 | ||||||||
88 | ||||||||
89 |