1
TaskEngineerEst. Time (hrs.)Actual Time (hrs.)Est. Comp. DateActual Comp. DateJan-15Jan-22Jan-29Feb-5Feb-12Feb-19Feb-26Mar-4Mar-11Mar-18Mar-25Apr-1Apr-8Apr-15Apr-22Apr-29May-6
2
Parts & Materials
3
Call for donationsPerro0.5116 Jan.17 Jan.
4
Done
5
Order Hardware / Purchased PartsFaloon1123 Jan.30 Jan.
6
Done
7
Order Matl's for fabricationFaloon1123 Jan.30 Jan.
8
Done
9
Obtain PolystyreneCurran1112 Mar.1 Mar.
10
Done
11
Obtain Clear PanelsCurran1112 Mar.8 Mar.
12
Done
13
Obtain all bicycle related partsStefano21.531 Jan.28 Jan.
14
Done
15
Fabrication
16
Manufacture FrameSwanson / Perro233 Feb.10 Feb.
17
Done
18
Machine Motor MountFaloon / Perro223 Feb.13 Feb.
19
Done
20
Machine motor mount standFaloon113 Feb.5 Mar.
21
Done
22
Machine Gear Mount FlangePerro113 Feb.13 Feb.
23
Done
24
Fabricate wooden bottomStefano0.50.53 Feb.16 Feb.
25
Done
26
Machine Top Lift Unit BraceStefano / Sturrup0.50.510 Feb.23 Feb.
27
Done
28
Machine Top Slot PieceStefano / Sturrup0.50.510 Feb.23 Feb.
29
Done
30
Machine Top Slot MountStefano / Sturrup0.50.510 Feb.23 Feb.
31
Done
32
Machine Gear Hub SpacersStefano10.2510 Feb.12 Mar.
33
Done
34
Fabricate Ski Lift Upper SupportsStefano / Sturrup10.510 Feb. 23 Feb.
35
Done
36
Fabricate Magnetic ExtensionSwanson2217 Feb.12 Mar.
37
Done
38
Assemble Ski Lift and InstallAll2417 Feb. 12 Mar.
39
Done
40
Wire Electric MotorPerro0.5117 Feb.23 Mar.
41
Done
42
Machine Mag. Elevator PlatesPerro / Swanson1124 Feb.28 Feb.
43
Done
44
Machine Mag. Elevator ShaftStefano / Perro0.5124 Feb. 6 Mar.
45
Done
46
Manufacture Mag. Elevator CoverStefano / Perro21.512 Mar.12 Mar.
47
Done
48
Machine/Fabricate Mag. Elevator Top BracePerro / Stefano1124 Feb.1 Mar.
49
Done
50
Attach Magnets to ChainPerro10.524 Feb.6 Mar.
51
Done
52
Assemble Magnetic ElevatorPerro / Stefano10.524 Feb.1 Mar.
53
Done
54
Manufacture Track Start 1Perro / Swanson0.522 Mar.10 Feb.
55
Done
56
Manufacture Vertical Option SwitchPerro112 Mar.13 Feb.
57
Done
58
Manufacture Top Track After SwitchSturrup0.512 Mar.14 Feb.
59
Done
60
Manufacture Snow Track SpiralPerro / Faloon119 Mar.18 Feb,
61
Done
62
Machine Stair Blocks and SupportsSturrup / Curran0.522 Mar.12 Mar.
63
Done
64
Manufacture Bowl CatchFaloon119 Mar.14 Feb.
65
Done
66
Manufacture Ball Trap EntranceFaloon229 Mar.9 Mar.
67
Done
68
Manufacture Ball Stair / SupportsSwanson / Sturrup0.519 Mar.9 Mar.
69
Done
70
Manufacture Bowl Track StartSwanson119 Mar.16 Feb.
71
Done
72
Manufacture Mountain Spirals Perro219 Mar.18 Feb.
73
Done
74
Manufacture Ball Catch Return TrackSwanson119 Mar.26 Mar.
75
Done
76
Manufacture Mag. Elevator Track StartStefano 0.519 Mar.5 Mar.
77
Done
78
Manufacture Magnetic Elevator Exit RampSwanson0.50.59 Mar.9 Mar.
79
Done
80
Fabricate MountainCurran0.5216 Mar.21 Mar.
81
Done
82
Manufacture Ski Patrol BuildingSturrup223 Mar.
83
84
Manufacture WheelStefano / Perro226 Apr.6 Apr.
85
Done
86
Sand Blast BallsPerro / Stefano1123 Mar.7 Mar.
87
Done
88
Paint All ElementsSwanson2430 Mar.16 Apr.
89
Done
90
Install Plastic PanelsStefano1230 Mar.20 Apr.
91
Done
92
Manufacture StandPerro2030 Mar.16 Feb.
93
Done
94
Install finish wood on StandSturrup4620 Apr.23 Apr.
95
Done
96
Maine Day PresentationAll4425 Apr.25. Apr.
97
Done
98
Install in MuseumAll4426 Apr.26 Apr.
99
Done
100
Testing