A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Submittal date | Fiscal Year | Component | Project type | State or Country | State or country title | Installation | Project number | Project Title | Solicitation/ advertise date | Award date | Contract recipient | Original contract amount ($000) | Current contract obligation ($000) | Start date | Occupancy date | Original completion date | Current completion date | % complete | Funds diverted ($000) (if applicable) | Remarks | |
6 | 4/15/2013 | 2011 | WHS | Major Construction | PA | PENNSYLVANIA | RRMC | POWER PLANT MODERNIZATION PHASE 3 WEST POWER PLANT | 09-Dec-11 | 09-Apr-13 | Grunley Construction Company, Inc | $43,594 | $43,594 | 22-Apr-13 | 11-May-16 | 11-May-16 | 0 | |||||
1914 |