PC-I�KHYBER PAKHTUNKHWA RURAL INVESTMENT & INSTITUTIONAL SUPPORT PROJECT (KP-RIISP) C&W DEPARTMENT (WORLD BANK ASSISTED)��Sub Head: Construction of Tehsil Building Complex Nawagai, District Bajaur� ADP No. 994/210631 (2025-26)
Planning & Development Department
Government of Khyber Pakhtunkhwa
Government of Khyber Pakhtunkhwa
Check List For Approval of Scheme
S.No | Description | Details |
1. | Sector | Multi Sectoral Development |
2. | ADP/Code # | 994/210631 (2025-26) |
3. | Nomenclature of Project | Construction of Tehsil Building Complex Nawagai |
4. | Status (New/Revised/Non-ADP) | New PC-I |
5. | Location | Nawagai, District Bajaur |
6. | GIS Coordinates recorded �(Yes, No, NA) | Yes |
7. | Executing & Sponsoring Agencies | P&DD World Bank |
Government of Khyber Pakhtunkhwa
Check List For Approval of Scheme
S.No | Description | Foreign | Total |
8. | Cost of the Project as Per ADP | Original: | Original: |
9. | Break up of Cost of PC-I | Capital | Total |
Rs.765 million | Rs.765 million | ||
10. | Allocation (2025-26) | Rs.4200 million (Foreign) | |
11. | Source of Funding :Whether Foreign funding committed in case of Foreign Aided Projects (Yes/No) | Yes | |
Government of Khyber Pakhtunkhwa
Check List For Approval of Scheme
S.No | Description | |
12. | Whether supported by Infrastructure section (Yes, No, NA). | Yes |
13. | Scope/Activities: | B. Repair rehabilitation of existing building
6) 36 Nos. Residential Quarters C. External development works including improvement of 1100 meter road, Septic tank Horticulture, Car Parking, Fire protection, Solar system D. Provisional sum 1) External Water supply, DAAB, ESMP E. Preliminaries 1) Office accommodation along with transportation 2) Office contingency |
14. | In case of Revised PC-I whether M&E has supported the revision (Yes, No, NA) | NA |
A. Tehsil Administration Building | No of floors | No of Office Rooms | Total Area | No of Elevators |
Tehsil Administration Building including SDC, TMA and Line departments | 3 | 24 | 44607 | 0 |
Residential Flats | 2 | 8 Flats | 10643 sft | 0 |
Government of Khyber Pakhtunkhwa
Check List For Approval of Scheme
S.No | Description | Details | |||
15. | Revenue Clearance of Finance Department (Yes, No, NA) | NA | |||
16. | Outcome of Pre-PDWP | Section | # of Total Observations | # of Observations Cleared | # of Pending/ Uncleared Observations |
RD | 0 | 0 | 0 | ||
| | M&E | 0 | 0 | 0 |
17. | Final Approval Forum | PDWP | |||
Government of Khyber Pakhtunkhwa
Scope of work and Cost Breakup
S.No | Description | Cost (PKR in Millions) |
1 | Tehsil Administration including line department, TMA and SDC | 433.49 |
2 | Officers Flat 2BHK (G+1 Floors, 8 Flats) | 115.04 |
3 | External Development Works | 33.74 |
4 | External Electrification | 13.09 |
5 | Renovation of Existing Buildings | 51.33 |
6 | Fire Extinguishers for all buildings | 2.47 |
7 | Solar System 200KvA | 35.44 |
8 | Preliminaries (Accommodation and Transport facilities for consultant at site for 36 months) | 6.00 |
9 | Provisional Sum(Wapda+water supply+DAAB+ESMP) | 30.00 |
10 | Escalation @ 6.5% | 44.50 |
| Total | 765.11 m Say 765.00 |
Government of Khyber Pakhtunkhwa
TEHSIL ADMINISTRATION FRONT ELEVATION
Government of Khyber Pakhtunkhwa
TEHSIL ADMINISTRATION FRONT ELEVATION
Government of Khyber Pakhtunkhwa
TEHSIL ADMINISTRATION FRONT ELEVATION
Government of Khyber Pakhtunkhwa
TEHSIL ADMINISTRATION FRONT ELEVATION
Government of Khyber Pakhtunkhwa
TEHSIL ADMINISTRATION FRONT ELEVATION
Government of Khyber Pakhtunkhwa
TEHSIL ADMINISTRATION FRONT ELEVATION
Government of Khyber Pakhtunkhwa
TEHSIL ADMINISTRATION FRONT ELEVATION
TEHSIL ADMINISTRATION NAWAGAI
Government of Khyber Pakhtunkhwa
Recommendation
PC-I of the project amounting to PKR 765.00 million is recommended for consideration of approval of PDWP.
The PDWP is authorized to Consider / approved scheme under the MSD in accordance with the directions of Planning Commission.