Project
https://www.youtube.com/watch?v=F6KxWU4HRrQ
Defining and organizing projects
Earned value management
Network planning model
Implementation
Project management
Types of projects
Organizing the project
Organizing the project
Organizing the project
Organizing project tasks
Work break down structure
The work breakdown structure (WBS) defines the hierarchy of project tasks, sub-tasks, and work packages. Completion of one or more work packages results in the completion of a subtask; completion of one or more subtasks results in the completion of a task; and, finally, the completion of all tasks is required to complete the project.
Project management (monitoring)
Project management (monitoring)
Earned value management
EVM is a technique that combines measures of scope, schedule, and cost for evaluating project progress.
Essential features of any EVM implementation include the following:
Earned value management charts
EVM Exercise
Based on the figure presented here determine the Budgeted Cost of Work Scheduled at the end of period X and The Budgeted Cost of Work Performed (shown in red shading).
Actual cost = 45K
MID Syllabus
Till here
Network planning model
FINAL Syllabus
STARTS here
CPM example
Network diagram
CPM Exercise
Three time estimates (PERT)
Three estimates for an activity time are:
a = Optimistic time: the minimum reasonable period of time in which the activity can be completed. (There is only a small probability, typically assumed to be 1 percent, that the activity can be completed in less time.)
m = Most likely time: the best guess of the time required. Since m would be the time thought most likely to appear, it is also the mode of the beta distribution discussed in step 4.
b = Pessimistic time: the maximum reasonable period of time the activity would take to be completed. (There is only a small probability, typically assumed to be 1 percent, that it would take longer.)
Calculate expected time (ET) and variance of activity time
Determine the probability of completing the project on a given date
Three time estimates (PERT) example
Determine the probability of completing the project in 35 weeks.
Cost time trade-off
Time cost trade-off example
Assume that the indirect costs remain constant at $10 per day if the project takes eight days or less and then increases at the rate of $5 per day.
Cost time trade-off
Cost time trade-off
Project Management Information System
Practice Exercise
Calculate cost performance index of the project using earned value management techniques. It is currently day 20 of the project and the following table summarizes the current status of the project.
Practice Exercise
Practice Exercise
Practice Exercise
Here are the precedence requirements, normal and crash activity times, and normal and crash costs for a construction project:
What are the critical path and the estimated completion time?
To shorten the project by three weeks, which tasks would be shortened and what would the final total project cost be?
Project Management Exercise
Annual EMBA meet!
Project description
Objective
Team and sub-teams and team structure, delegation of responsibilities
Activities
Activity of Time line (gantt chart)
Resources needed
Activity wise budget