ADENA LOCAL SCHOOL DISTRICT: �WARRIOR WELLNESS CENTER
1
FEATURES AND SPACES:
HEALTH FACILITY SPACES:
SHARED COMMUNITY SPACES:
ADENA LSD ATHLETIC SPACES:
2
PROJECT PARTNERS:
Adena Local School District
Adena Health Systems
Nationwide Children’s Hospital
Appalachian Children’s Coalition
Governor Mike DeWine
3
Project Budget
PROJECT BUDGET ESTIMATE:
DESIGN MEETINGS
5
3/20/2025
ADENA WARRIOR WELLNESS CENTER
5
BIDDING PROCESS:
Public Advertisement
Pre-Bid Meeting
Addenda Process
Bid Day Opening
Interview of Apparent Low Bidders
Bid Recommendation
6
BID RECOMMENDATIONS:
Combination Bid of 1A – GW&L, 15A – Plumbing, 15B – Mechanical, and 16A – Electrical: JayCar Construction
2A – Site Work: Fillmore Construction
Combination Bid of 15C – Fire Suppression and 17D – Fire Alarm: 1A Sprinkler & Systems Integration
7
Apr. 2025
Site Work begins in April 2025
May 2025
Concrete begins in May 2025
June 2025
Framing Begins in June 2025
Sep. 2025
Pre-Engineered Metal Building begins in September 2025
2025–2026
Interior Finishes, Mechanical, Electrical, Plumbing from Fall 2025-Spring 2026
Summer 2026
Construction Complete in Summer 2026
Additional Considerations:
PROJECT MILESTONES
8