Gray Update
Date
Disaster Damage
25 sites were storm damaged, 30% of PPS Properties
2
Damage Overview
The lower wing sustained extensive damage due to burst pipes and roof leaks.
A total of 15 classrooms and two common areas were impacted.
3
The Abatement Process
Abatement is starting and will take about two weeks to complete.
Work crews have spent weeks removing damaged pipes, flooring, ceiling tiles, and drywall.
The process is slow and incremental. Any time workers encounter what they think might be hazardous material, they have to test and remediate the area. This takes weeks to complete.
4
The Lower Wing Roof
5
The Scope of Work
Workers are making meaningful progress on removing damaged and hazardous materials from the lower wing.
Once abatement is complete, they can begin installing:
6
7
Options to Ease Overcrowding & Noise Issues
8
Thank you for your patience-
I will try to answer a few questions that have come up in the chat