1 of 9

SAP Plant Maintenance

PLM322

Capacity Planning and Scheduling

in Maintenance Projects

Unit 02 Identifying the Work

Preparing and Planning Maintenance Projects

A power plant boiler needs to be taken down for routine maintenance and repair. We have to prepare and plan the maintenance work to be carried out. To do this, we will use a series of task list recorded in the task hiearchy. The starting point is the notification to plan the maintenance measures to be carried out via several maintenance order.

2 of 9

Note Hierarchy Task List

3 of 9

Notice the Task list with Work Center PF-00 (note this is the generic work center, it will be replaced by a final reponsibility work center when the MO is generated, this is done via a conversion rule… see next)

4 of 9

If T-ME20 is entered as the main work center in the MEB revision (not the task list header), and if the task list operation is assigned with work center PF-00, it will be replace with final work center PF-20

Original Work Center in the General Task List

Final Resulting Work Center in the Maintenance Order planned via MEB

Main Work Center to be entered in the Revision in the MEB

5 of 9

Hierarchy Task List

Call object Notification

6 of 9

Note

Main Work Center ‘MECHANIK’

7 of 9

Schedule the Maintenance Plan MEB20

8 of 9

Notification created with Hierarchy Task List for MEB processing

9 of 9