SAP Plant Maintenance
PLM322
Capacity Planning and Scheduling
in Maintenance Projects
Unit 02 Identifying the Work
Preparing and Planning Maintenance Projects
A power plant boiler needs to be taken down for routine maintenance and repair. We have to prepare and plan the maintenance work to be carried out. To do this, we will use a series of task list recorded in the task hiearchy. The starting point is the notification to plan the maintenance measures to be carried out via several maintenance order.
Note Hierarchy Task List
Notice the Task list with Work Center PF-00 (note this is the generic work center, it will be replaced by a final reponsibility work center when the MO is generated, this is done via a conversion rule… see next)
If T-ME20 is entered as the main work center in the MEB revision (not the task list header), and if the task list operation is assigned with work center PF-00, it will be replace with final work center PF-20
Original Work Center in the General Task List
Final Resulting Work Center in the Maintenance Order planned via MEB
Main Work Center to be entered in the Revision in the MEB
Hierarchy Task List
Call object Notification
Note
Main Work Center ‘MECHANIK’
Schedule the Maintenance Plan MEB20
Notification created with Hierarchy Task List for MEB processing