Determine if there is an exposure to a capacitor-stored energy hazard
1
Working Safely with �Hazardous Capacitors
ESM Section 15
11/03/2021
Field Guide 16
Revision 0.02
Capacitors >10 Joules and >100 Volts are considered hazardous at Berkeley Lab.
Capacitor Hazards and Thresholds
Threshold | Shock Hazard |
0.25 J and 400 V | Reflex injury |
10 J and 100 V |
|
Threshold | Short-Circuit Hazard |
100 J | Burns to skin |
1 kJ | Burns + mechanical deformation of metal |
10 kJ | Arc blast |
Threshold | Arc Flash Hazard |
100 J | Hearing damage |
40-120* kJ | Arc-flash hazard |
122 kJ | Lung collapse |
Performing a Shock Risk Assessment
2
Determine the shock hazard using both the voltage and stored energy of the capacitor
3
Determine the total capacitor-stored energy of the system
*Note that the arc-flash threshold may be lower for a capacitor in a box, and there may be an additional contribution to the arc-flash energy from an AC or DC source connected to the capacitor bank.
OTHER HAZARDS
See Electrical Safety Manual Rev2 Section 15 for detailed Capacitor hazard calculation instructions.
Test and Grounding Methods
Determine the required test and grounding method.
Develop a Complex LOTO Procedure or Permit
Hazardous capacitor-stored energy is considered an additional energy source. Therefore, you need an approved complex LOTO procedure or permit for any mode 0/1 work with such equipment.
The complex LOTO procedure or permit should include:
Label the Equipment
Label the equipment with a stored energy hazard warning label, so that qualified persons are made aware of the potential for stored energy and the need for a written discharge procedure. Include the stored energy in Joules, the voltage, and required wait time.
15
5
O. Sowle
August 31, 2021
| Test Method | Grounding Method | ||||
| 0 - 100V | 100 - 1kV | >1kV | 0 - 100V | 100 - 1kV | >1kV |
< 0.25 J | no hazard | no hazard | no hazard | no hazard | no hazard | no hazard |
0.25 - 100J | no hazard | Digital Volt Meter | DVM with HV adapter | no hazard | Hard ground ok | Hard ground ok |
100 - 1kJ | Digital Volt Meter | Digital Volt Meter | HV Utility Grade DC Voltmeter | Hard ground ok | Hard ground ok | Hard ground ok |
1k - 100kJ | Digital Volt Meter | Digital Volt Meter | HV Utility Grade DC Voltmeter | Soft ground then hard ground | Soft ground then hard ground | Soft ground then hard ground |
>100kJ | Engineered Method | Engineered Method | Engineered Method | Remote grounding only | Remote grounding only | Remote grounding only |
Hard grounding: Use an insulating stick with a grounding tip to discharge a capacitor between its two terminals and then to ground.
Soft grounding: Use an insulating stick with a mounted resistor or a Hi-Z point to perform a controlled discharge of the capacitor first. Then, after the prescribed wait time, apply hard grounding.
Wait time: If capacitors are equipped with bleed resistors, or if using a soft grounding system, determine the required discharge wait time, where applicable. After the required discharge time, apply a hard ground stick or hard grounding system.