Lakeshore East West Corridor Expansion: Early Work

Construction Liaison Committee Meeting

September 7, 2021

More info: metrolinx.com/lakeshoreeastrailcorridor/

Contact: TorontoEast@Metrolinx.com

2 of 18

LAND ACKNOWLEDGMENT

Let us take a moment to acknowledge that we are on the traditional territory of Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples.

We are all Treaty people. Many of us have come here as settlers and immigrants…in this generation or generations past.

Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples.

We acknowledge the historic and continued impacts of colonialization and the need to work towards meaningful reconciliation with the original caretakers of this land.

We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct business in a manner that is built on the foundation of trust, respect and collaboration.

2

3 of 18

Terms of Reference

The CLC will provide a communication forum for the Lakeshore East-West (Package B) construction project team and community representatives of area residents and businesses to proactively and regularly communicate and discuss construction activities and community impacts. The committee is designed to enable regular access to construction-related information, including schedule and timing information for local business owners, community groups and residents, through CLC representatives and discussions.

The Lakeshore East-West Team will:

  • Provide accurate, understandable and timely information.
  • Be open to feedback, give careful consideration to ideas, and report back to the larger project team.
  • Adhere to all aspects of the Terms of Reference and Code of Conduct.

Community Representatives or Area Residents and Businesses will:

  • Participate actively in regular meetings.
  • Be open and receptive to ideas.
  • Liaise and act as a representative of pre-identified organization/community/business or stakeholder group by providing feedback to the project team and formally communicating relevant information back to their respective groups.
  • Adhere to all aspects of the Terms of Reference and Code of Conduct.

3

4 of 18

SAFETY MOMENT

Project safety measures in place:

  • Weekly safety meetings and safety talk
  • Safety stand-down scheduled for August
  • Bi-weekly rapid testing suspended at the end of July
  • MX general safety audit conducted with no identified issues

4

5 of 18

Project Overview

Expanding the Lakeshore East Corridor for the Future

The Lakeshore East GO corridor is Metrolinx’s second busiest rail line. We’re transforming this corridor to bring more trips along the line for those traveling from and to Toronto. Frequent GO rail service will offer more service with faster trains and seamless connections to a regional rapid transit network.

5

What’s Happening Now?

Metrolinx contractors, LS Lakeshore Constructors, are conducting preparatory work to widen the corridor and infrastructure to allow for a forth track installation between Pape Avenue and Warden Avenue.

6 of 18

What are the benefits of this work?

6

7 of 18

Project Update – Package C�Pape Avenue to Woodbine Avenue��Nicole Dewar�Construction Communication Liaison, LS Lakeshore Constructors

7

September 7, 2021

8 of 18

PROJECT CONSTRUCTION MILESTONES

8

Package C Milestones

Retaining Wall 6 (Pile and Lagging)

Retaining Wall 7 (Pile and Lagging)

Retaining Wall 4 (T Wall)

Small's Creek Culvert

Retaining Wall 12 (T Wall)

Retaining Wall 13 (T Wall)

Substantial Completion

9 of 18

Project Update – Package C�Progress Update��Nicole Dewar�Construction Communication Liaison, LS Lakeshore Constructors

9

September 7, 2021

10 of 18

LAKESHORE EAST WEST CORRIDOR EXPANSION – PACKAGE C

Package C

Construction Update:

  • No progress this month
  • Early Works Completed
    • Installation of Tree Protection Fence
    • Ongoing surveying and locates
    • Partial clearing and grubbing

10

11 of 18

Project Update – Package C�Upcoming Work��Nicole Dewar�Construction Communication Liaison, LS Lakeshore Constructors

11

September 7, 2021

12 of 18

UPCOMING WORK: LAKESHORE EAST WEST CORRIDOR EXPANSION – PACKAGE C

Upcoming Overnight Construction Activities:

  • Hours: 7:00 p.m. and 7:00 a.m.
  • Five (5) days per week (Monday to Friday)
  • Between Jones Ave and Coxwell Ave
  • Will include:

1. Tree and vegetation removal

2. Excavation

3. Grading

  • Residents can expect to see construction vehicles and equipment in the rail corridor and the surrounding areas, including pile driving equipment, dozer, crane, excavator, concrete trucks, and dump trucks.
  • Noise, vibration, dust and site lighting can be anticipated.

12

13 of 18

UPCOMING WORK: UNITY ROAD ACCESS

Starting September 2021

  • Knotweed Removal
  • Vegetation removal, clearing, grubbing, chipping and disposal
  • Installing temporary access roads
  • Installing concrete barriers
  • Retaining Wall 6 & 7
  • Noise & vibration monitoring set-up
  • Pile Installation 

13

14 of 18

UPCOMING WORK: CORRIDOR EXPANSION – RETAINING WALL 6

  • Pile and lagging wall
  • Greenwood Avenue to Valifor Place
  • Night Work
  • Construction staging

1) Excavation

2) Pile and caisson install

3) Install lagging and backfill

4) Install fence

5) Grounding and bonding

14

15 of 18

UPCOMING WORK: CORRIDOR EXPANSION – RETAINING WALL 7

  • Pile and lagging wall
  • Greenwood Ave to Jones Avenue
  • Night work
  • Construction staging

1) Excavation

2) Pile and caisson install

3) Install lagging and backfill

4) Install fence

5) Grounding and bonding

15

16 of 18

UPCOMING WORK: SMALL’S CREEK

  • Expected start October 2021
  • South side of corridor
  • Construction staging

Stage 1: Preparatory work (Clearing and grubbing, installation of temporary access roads)

Stage 2: Passive By-Pass Installation & Granular Pad Construction 

Stage 3: Install 2000mm dia. culvert via. Trenchless Method. Stage 4: Headwall/Retaining wall installation

Stage 5: Decommissioning of old Culvert/Restoration

16

17 of 18

Questions & Discussion