Project management
Project is a temporary ,complex and connected activities having a single goal or purpose that must be completed with in the time and cost and according to the specification
Project management is the process of application of skills , knowledge ,tools that must be used to complete the project objectives ,with in the time and cost and according to the specification
What is a network?
Any system of interconnected linear features
What is network analysis?
Network Diagram
Network diagram is a graphical / pictorial representation of a series or a sequence of activities in the logical order of their performance, such that we establish the inter relation and interdependence of one activity on all other activities of the project.
Network Diagram comprises of two basic elements:
Elements of Network Diagram
It signifies the deployment of finite resources over a finite period of time. The tail of the arrow signifies the commencement of the activity and the head signifies the completion of the activity.
It signifies the status of the project at a point of time. It indicates the start & completion of an activity.
i
Tail
Head
where, i={1,2,3,4…. and so on}
Slide 7
A-O-A Convention (i-j convention)
i
j
A
tij
i < j
Activity A or Activity i-j
Tail event signifies commencement status of the activity.
Head Event signifies completion status of the activity
Arrow signifies deployment of finite resources over a finite period of time.
tij is the duration of the activity
Tail Event
Head Event
Slide 8
Good practices of drawing a Network Diagram
Slide 9
Types of events
Event
Activity
Draw network diagram from the following data
Activity | Preceding activity |
A | ---- |
B | A |
C | A |
D | B |
E | C |
F | D,E |
1
4
2
5
6
3
A
C
B
F
D
E
Draw network diagram from the following data
Activity | Preceding activity |
A | ---- |
B | ---- |
C | A |
D | B |
E | C,D |
F | E |
G | F |
1
4
2
3
6
5
7
A
B
C
D
E
F
G
Draw network diagram from the following data
Activity | Preceding activity |
A | ---- |
B | --- |
C | ---- |
D | A |
E | B |
F | C |
G | D,E |
H | F,G |
1
4
5
4
3
2
6
A
D
E
G
F
H
B
C
Draw network diagram from the following data
Activity | Preceding activity |
A | ---- |
B | --- |
C | A |
D | A |
E | B |
F | C,D |
G | D |
H | D,E |
I | F,G,H |
1
2
3
4
5
6
8
7
A
B
C
D
E
G
F
H
I
CPM
CPM BASIC TERMINOLOGY
slack = LFT-EFT
EFT= EST+ Duration of activity
Latest finish time (LFT): It is latest time by which
The activity must be completed .so that the scheduled date for the completion of the project may not delayed .it is calculated by moving backwards.
Float and types of float
Type of float
The following are the activities identified in a small project with time days
Activity | Preceding activity | Time |
A | - | 2 |
B | A | 5 |
C | B | 1 |
D | A | 3 |
E | C,D | 6 |
F | E | 1 |
G | F | 1 |
H | E | 4 |
I | G,H | 2 |
Draw the network diagram,
Identify the critical path
Calculate project duration
1
3
2
6
5
4
7
8
A(2)
B(5)
D(3)
C(1)
E(6)
H(4)
F(1)
G(1)
I(2)
E1=0
L1=0
L3=7
E3 =7
E2=2
L8=20
E8=20
L6=17
E6=15
L5=14
E5=14
L4=8
E4=8
L2=2
E7=18
L7=18
Critical path :
Critical path 1 is
1
2
3
4
7
5
8
A(2)
B(5)
C(1)
E(6)
H(4)
I(2)
Duration of the project is =2+5+1+6+4+2 =20 days
1
2
8
7
5
4
A(2)
D(3)
E(6)
H(4)
I(2)
Duration of the project is =2+3+6+4+2 =17 days
Critical path 2 is
Original critical path is
Duration of the project is 2o days
A small engineering project consists of 6 activities namely ABCDE & F with duration of 4, 6, 5, 4, 3 and 3 days respectively. Draw the network diagram and calculate EST, LST, EFT, LFT and floats. Mark the critical path and find total project duration.
Activity | A | B | C | D | E | F |
Preceding activity | - | A | B | A | D | C,E |
Duration | 4 | 6 | 5 | 4 | 3 | 3 |
B
3
C
6
5
F
1
4
2
5
3
6
A
4
3
D E
4
18
18
15
15
4
4
0
0
LFT
EST
10
10
8 11
Activity | Duration | EST | EFT | LFT | LST | Total float | Free float | Independent float |
A | 4 | 0 | 4 | 4 | 0 | 0 | 0 | 0 |
B | 6 | 4 | 10 | 10 | 4 | 0 | 0 | 0 |
C | 5 | 10 | 15 | 15 | 10 | 0 | 0 | 0 |
D | 4 | 4 | 8 | 12 | 8 | 4 | 0 | 0 |
E | 3 | 8 | 11 | 15 | 12 | 4 | 4 | 0 |
F | 3 | 15 | 18 | 18 | 15 | 0 | 0 | 0 |
Note: LST = LFT – activity duration
EFT = EST + activity duration
Total float = LST – EST or LFT – EFT
Free float = EST of Head Event – EST of Trail Event – Activity duration Independent float = EST of Head event – LFT of Trail event – Activity duration
PERT: It is concerned with estimating the time for different stages in such a Programme or a project and find out what the critical path is, which consumes a maximum resources
PERT planning involve the following steps:
Determine the proper sequence of the activities
Construct a network diagram
Estimate the time require for each activity
Determine the critical path
Identity the specific activity & events
IDENTIFY THE SPECIFIC ACTIVITIES AND MILESTONES. The activities are the tasks required to complete a project. The milestones are the events marking the beginning and the end of one or more activities. It is helpful to list the tasks in a table that in later steps can be expanded to include information on sequence and duration.
DETERMINE THE PROPER SEQUENCE OF THE ACTIVITIES This step may be combined with the activity identification step since the activity sequence is evident for some tasks. Other tasks may require more analysis to determine the exact order in which they must be performed.
CONSTRUCT A NETWORK DIAGRAM. Using the activity sequence information, a network diagram can be drawn showing the sequence of the serial and parallel activities.
Each activity represents a node in the network, and the arrows represent the relation between activities.
Software packages simplify this step by automatically converting tabular activity information into a network diagram.
ESTIMATE THE TIME REQUIRED FOR EACH ACTIVITY Weeks are a commonly used unit of time for activity completion, but any consistent unit of time can be used. A distinguishing feature of PERT is its ability to deal with uncertainty in activity completion time. For each activity, the model usually includes four time estimates: Optimistic time Most likely time Pessimistic time Expected time
TIMES
Optimistic time It is generally the shortest time in which the activity can be completed.
Most likely time – the completion time having the highest probability. Note that this time is different from the expected time.
Pessimistic time – the longest time that an activity might require.
Expected time = (Optimistic + 4 x Most likely + Pessimistic) / 6
This expected time may be displayed on the network diagram.
DETERMINE THE CRITICAL PATH. The critical path is determined by adding the times for the activities in each sequence and determining the longest path in the project.
The critical path determines the total calendar time required for the project.
Normal Deviate If Ts is the schedules time of completionIf Ts is the schedules time of completion & Te is the expected time of completion& Te is the expected time of completion Z = Ts-Te/sigmaZ = Ts-Te/sigma Sigma = (Sum of variances along critical path)Sigma = (Sum of variances along critical path)0.50.5 Variance = (tp-to/6)Variance = (tp-to/6)22
A small engineering project consists of six activities. The three time estimates in number days for each activity are given below.
Activity to tm tp
1-2 2 5 8
2-3 1 1 1
3-5 0 6 18
5-6 7 7 7
1-4 3 3 3
4-5 2 8 14
Find out:
Activity |
to |
tm |
tp | t o + 4tm + t p t e = 6 (Duration) | t - t S.D (s t ) = p o
6 | Varianc(e v) = (SD)2 i |
1-2 | 2 | 5 | 8 | 5 | 1 |
|
2-3 | 1 | 1 | 1 | 1 | 0 |
|
3-5 | 0 | 6 | 18 | 7 | 3 |
|
5-6 | 7 | 7 | 7 | 7 | 0 |
|
1-4 | 3 | 3 | 3 | 3 | 0 | 0 |
4-5 | 2 | 8 | 14 | 8 | 2 | 4 |
From the table value (z = 1.31) = 0.90490 =90.5%
Probability for completing project in 25 days
Z = Ts-Te/sigma
Z = Ts-Te/sigma
Sigma = square root of (Sum of variances along critical path)
Ts = 25 days , Te = 20 days
Standard deviation ( sigma ) = square root of (1 +0+9+0) = 3.16
Z = 25-20
3.18
Z = 5/3.18 = 1.31
CPM | PERT |
|
|
| Estimate of time for activities are not so accurate and definite. |
|
|
|
|
|
|
In CPM, cost optimization is given prime importance. The time for the completion of the project depends upon cost optimization. The cost is not directly proportioned to time. Thus, cost is the controlling factor. |
|
BASIS FOR COMPARISON | CPM | PERT |
Meaning | CPM is a statistical technique of project management that manages well defined activities of a project. | PERT is a project management technique, used to manage uncertain activities of a project. |
What is it? | A method to control cost and time.� | A technique of planning and control of time. � |
Focus on | Activity | Event |
Model | Deterministic Model | Probabilistic Model |
Estimates | One time estimate | Three time estimates |
Management of | Predictable activities | Unpredictable Activities |
Suitable for | Non-research projects like civil construction, ship building etc.� | Research and Development Project |
Project crashing
a) Direct cost: These costs are those, which are directly proportional to the number of activities involved in the project Ex: Raw material cost
b) Indirect cost: In direct cost are those costs that are determined per day. Some of examples for indirect costs are supervisory personnel salary, supplies, rent, interest an borrowings, ads, depreciation. These costs are directly proportional to the number of days of the duration of the project. If the project duration is reduced the indirect cost also comes down.
Normal cost (Nc): It is the lowest cost of completing an activity in the minimum time, employing normal means i.e. not using overtime or other special resource.
Normal time (NT): It is the minimum time required to achieve the normal cost Crash cost (CC): It is the least cost of completing an activity by employing all possible means like overtime, additional machinery, proper materials etc.
Crash time (CT): It is the absolute minimum time associated with the crash cost.
The crash time refers to the shortest possible time to complete an activity with additional resources.
The crashing cost refers to the activity cost under the crashing activity time. This relationship is assumed to be linear. Hence, for each activity a crash cost per period (e.g. per week) can be derived as follows:
crash cost per period = (Crash cost - Normal Cost)/ (Normal time - Crash time)
Crashing of Network: After identifying the critical path, it is necessary to identify the priority to crash the activities by calculating the cost slope.
For reducing the duration extra expenditure to be incurred, but to save resources, organizations keep this extra expenditure at a minimum.
When the direct cost (A) decrease with an increase in time, as the project duration increase, the indirect cost (B) like overheads, depreciation, insurance etc. increases. The total cost (A+B) curve is a flat U-shaped curve, with implies that only up to a particular point (O) the crashing is economical, not beyond. The time duration, which involves the least total cost, is the optimum duration at optimum cost. Crashing the duration of a project may not be possible beyond a particular point.
Steps involved in project crashing
Step 1: Determine the normal project completion time and associated critical path using normal time
Step 2: Identify the critical activates and calculated the cost slope for each of these by using the relationship
Note : The values of cost slope for critical activities indicate the direct cost extra cost required to execute an activity per unit
Step 3: Compare the cost slope with given indirect cost
If cost slope is zero or greater than indirect cost or is equal to indirect cost , don’t crash (reduce ) activities
If cost slope is less than indirect cost ,crash the relevant acitivites
Step 4 : calculate the associated cost and time and critical path
Note : Accept the new critical path along with the existed critical path , if new one arrives Never neglect the original critical path
Step 5 :
Repeat the steps from 2 to 5 until the optimal solution is reached
Associated cost :
Total normal cost +total indirect cost + total crashed cost
Crashing the activities under critical path to reduce the project duration .Identify the critical path for the following network .show how far the project can be crashed also show the extent of increase in normal costs with every stage of crashing
ACTIVITY | Preceding activity | Normal time (DAYS) | Cost (rs) | Crash time (rs) | Cost |
A | -- | 6 | 5000 | 4 | 6200 |
B | -- | 4 | 3000 | 2 | 3900 |
C | A | 7 | 6500 | 6 | 6800 |
D | A | 3 | 4000 | 2 | 4500 |
E | B,C | 5 | 8500 | 3 | 10000 |
Here it is assumed that normal cost is includes overheads
1
3
2
4
A(6)
B(4)
D(3)
C(7)
E(5)
0
0
6
6
18
18
13
13
Critical path is 1-2-3-4 = 6+7+5 = 18 days
Total cost = total normal cost +total indirect cost =27000 +0 = 27000
Calculation of cost slope
ACTIVITY | Normal time (DAYS) | Cost (rs) | Crash time (rs) | Cost | Cost slope CC-NC NT-CT |
A(1-2) | 6 | 5000 | 4 | 6200 | 600 (2) |
B(1-3) | 4 | 3000 | 2 | 3900 | 450 Not under critical path |
C(2-3) | 7 | 6500 | 6 | 6800 | 300 (1) |
D(2-4) | 3 | 4000 | 2 | 4500 | 500 Not under critical path |
E(3-4) | 5 | 8500 | 3 | 10000 | 750 (3) |
1
3
2
4
A(6)
B(4)
D(3)
C(6)
E(5)
0
0
6
6
17
17
12
12
Critical path is 1-2-3-4 = 6+6+5 = 17 days
Total cost = total normal cost +total indirect cost =27000 +0+1*300 = 27300
To start with let us crash activity 2-3 by reducing one day
1
3
2
4
A(4)
B(4)
D(3)
C(6)
E(5)
0
0
4
4
15
15
10
10
Critical path is 1-2-3-4 = 4+6+5 = 15 days
Total cost = total normal cost +total indirect cost =27000 +0+1*300+2*600 =28500
crash activity 1-2 by reducing two day
1
3
2
4
A(4)
B(4)
D(3)
C(6)
E(3)
0
0
4
4
13
13
10
10
Critical path is 1-2-3-4 = 4+6+3 = 13 days
Total cost = total normal cost +total indirect cost + total crashed cost
=27000 +0+(1*300)+(2*600)+(2*750) =30000
crash activity 3-4 by reducing two day
The project duration at every stage of crashing and increase in normal costs can be summarized as below
Project duration | Project cost |
18 days | 27000 |
17 days | 27300 |
15 days | 28500 |
13 days | 30000 |
Hence the optimum duration of the project is 13 days and cost of the project is 30000
From the following particulars
ACTIVITY | Normal time (DAYS) | Cost (rs) | Crash time (rs) | Cost |
1-2 | 3 | 10000 | 2 | 11000 |
1-3 | 6 | 6000 | 3 | 8400 |
2-3 | 9 | 9000 | 3 | 12000 |
2-4 | 7 | 5000 | 4 | 7800 |
3-4 | 3 | 3000 | 2 | 3400 |
1
3
2
4
(3)
(6)
(7)
(9)
(3)
0
0
3
3
15
15
12
12
Critical path is 1-2-3-4 = 3+9+3 = 15 days
Total cost = total normal cost +total indirect cost =33000+15*600 = 42000
ACTIVITY | Normal time (DAYS) | Cost (rs) | Crash time (rs) | Cost | cost slope CC-NC NT-CT |
1-2 | 3 | 10000 | 2 | 11000 | 1000 |
1-3 | 6 | 6000 | 3 | 8400 | 800 |
2-3 | 9 | 9000 | 3 | 12000 | 500 II |
2-4 | 7 | 5000 | 4 | 7800 | 700 |
3-4 | 3 | 3000 | 2 | 3400 | 400 I |
1
3
2
4
(3)
(6)
(7)
(9)
(2)
0
0
3
3
14
14
12
12
Critical path is 1-2-3-4 = 3+9+2 = 14 days
Total cost = total normal cost +total indirect cost+ total crashed cost =33000+14*600+1*400 = 41800
Crashing of 3-4 activity by reducing one day
1
3
2
4
(3)
(6)
(7)
(3)
(2)
0
0
3
3
10
10
6
8
Critical path is 1-2-4 = 3+7 = 10 days
Crashing of 2-3 activity by reducing 6 days its impact on the original critical path then you don’t crash the activity
Crashing of 2-3 activity by reducing 6 day
1
3
2
4
(3)
(6)
(7)
(5)
(2)
0
0
3
3
10
10
8
8
Critical path is 1-2-3-4 = 3+5+2 = 10 days
Total cost = total normal cost +total indirect cost+ total crashed cost =33000+10*600+(1*400)+(4*500)
= 41400
Crashing of 2-3 activity by reducing 4 day
The project duration at every stage of crashing
Project duration | Project cost |
15 days | 42000 |
14 days | 41800 |
10 days | 41400 |
Hence the optimum duration of the project is 10 days and cost of the project is 41400