1 of 17

Del Valle ISD Project Updates October 2022

2 of 17

Smith Elementary Opened August 2022

Smith Elementary Updates (Oct 2022)

  • Final punch list is being developed
  • Parking lot is in final phase for opening
  • Canopies for the playground are pending
  • Door hardware and replacement doors scheduled for October to December (After hours work and non-school days)
  • Access control programming and camera installation is ongoing
  • Graphics are being completed

3 of 17

Concrete being poured, final road complete, and playground.

4 of 17

Hornsby Dunlap Elementary Opening January 2023

Hornsby Dunlap Updates (Oct 2022)

  • Inspections are continuing to secure stocking and occupancy permits
  • Interior finishing processes are underway
  • Final polishing of the floors is continuing
  • Canopies for the playground are pending
  • Access control programing and camera installation are underway

5 of 17

New logo and progress photos

6 of 17

Del Valle Middle School (Opening Fall 2023)

Del Valle MS Update (Oct 2022)

  • Roofing and vertical walls are underway
  • Concrete slab with crawl space complete
  • Steel structure is being installed
  • Windows are being installed
  • Main utility connections are underway

7 of 17

Photos of campus

8 of 17

Child Development Center - Central (Opening Fall 2023)

CDC - Central Updates (Oct 2022)

  • Site work excavation is underway
  • Inspections for the site work are daily
  • Dust mitigation and overflow parking are working well

9 of 17

Administration Building Addition (Opening Late Fall 2023)

Admin Building Addition Updates (Oct 2022)

  • Site work excavation is underway
  • Inspections for the site work are daily
  • Dust mitigation and overflow parking are working well

10 of 17

Site work photos

11 of 17

Operations Facility (Opening Fall 2023)

Operations Facility Updates (Oct 2022)

  • Site work excavation is underway
  • 35 foot deep piers are drilled
  • Concrete work is beginning onsite
  • Inspections for the site work are daily
  • Dust mitigation and overflow parking are working well

12 of 17

Site work photos

13 of 17

Hillcrest Front Entrance Renovation (Winter 2023)

Hillcrest Front Entrance Update (Oct 2022)

  • Site work and new stone is complete
  • Canopy is expected to be completed during the Winter break 2023
  • Front counter and tile is complete
  • Added access control is underway
  • Flooring is complete

14 of 17

Hillcrest Photos

15 of 17

Del Valle HS Front Entrance Renovation (Winter 2023)

Del Valle HS Front Entrance Update (Oct 2022)

  • Canopy is expected to be completed during the Winter break 2023
  • Front counter and tile is complete
  • Added access control is underway
  • Flooring is complete
  • Pending technology connections

16 of 17

DVHS Photos

17 of 17

Del Valle HS Educational Excellence Village

Del Valle HS Educational Excellence Village

  • 95 % complete with all items
  • Request for added picnic tables
  • Canopies and turf installed