1 of 36

From Russia With Love:

What We Learned from the

Russian Accident History

Jim Baker

August 21, 2025

Page 1 of 36

2 of 36

Objectives:

  • Compare/contrast what we “know” about criticality accidents by adding the Russian experience to ours.
  • Three editions of the Accident Report:
      • LA-3611, Review of Criticality Accidents, 1967 by W.R. Stratton
      • DOE/NCT-04, A Review of Criticality Accidents, 1989, by D. R. Smith
      • LA-13638, A Review of Criticality Accidents, 2000 Revision, by T.P. McLaughlin, et al
  • Highlight key lessons learned and one case study

Page 2 of 36

3 of 36

From the 1989 Revision of the Accident Report:

  • Accident features and causes:
    • Unfavorable geometry vessels
    • All occurred in solution
    • Workers not following procedures
    • Activity or procedures not reviewed by NCS
    • Non-routine operations
    • Poor communications, including material labeling/posting

Page 3 of 36

4 of 36

Parallels in History: The process accidents

  • ~1 to 2 per year, mid 50’s to mid 60’s
    • Height of the Cold War production ramp up
  • ~1 per decade thereafter

Page 4 of 36

5 of 36

Deliberate Parallels in Facilities

  • Mayak = Hanford
  • Tomsk = Savannah River Site / Y-12
  • Arzamas = Los Alamos
  • Semipalatinsk = Nevada Test Site
  • Etc.

  • But: Russia did not separate military and civilian fuel processing and power reactor facilities.

Page 5 of 36

6 of 36

Page 6 of 36

7 of 36

A Historic Opportunity

  • In mid 1980’s “détente” turned to “perestroika” and “glasnost” (openness).
  • By mid 1990’s, FSU collapsed, and Russians announced that they had 13 process criticality accidents.
  • LANL led an effort to reach out to Russian scientists to include their information and publish a revision to the old accident report (Stratton/Smith).
    • One of a number of cooperative projects done at that time
  • In late 1990’s a number of visits and information exchanges occurred to facilitate documenting the information
    • Primary authors: T. McLaughlin, N. Pruvost, S. Monahan (US),V. Frolov, B. Ryazonov, V.Sviridov (Russian Federation)

Page 7 of 36

8 of 36

Challenges for the 2000 Revision to the Accident Report

    • Intense work, challenging travel conditions
  • Accurate translation
  • Lack of good documentation of the events at the time they occurred (sometimes classified reports)
  • Not inventing new facts
  • Culling the available info to the essentials
  • Getting the Russian version published (w/ errata)

Page 8 of 36

9 of 36

13 Russian Process Criticality Accidents

  • Mayak Production Association (comparable to Hanford)
      • 7 Accidents, 5 Fatalities, 2 Amputations
  • Tomsk (comparable to Savannah River/Y-12)
      • 4 Accidents, One Amputation
  • Elektrostal
      • 1 Accident, Insignificant Exposures
  • Novosibirsk
      • 1 Accident, Insignificant Exposures

Page 9 of 36

10 of 36

Special Features

  • Multiple terminated by active intervention
  • Largest estimated first spike yield (~2x1017 fissions): Mayak PA, 2 January 1958
  • Very small excursions (~ 1014 fissions) and multiple unit accident: Novosibirsk, 15 May 1997
  • Metal accident: Tomsk, 13 December 1978
  • Two low enrichment slurry accidents
    • Tomsk, 14 July 1961, U(22.6) Oxide–Oil
    • Electrostal, 3 November 1965, U(6.5) Oxide–Water

Page 10 of 36

11 of 36

Notable Characteristics

  • Several apparently had no first spike (a couple are unknown)
  • Some had very low yield (< 1016 fissions)
    • Problematic for CAAS detection and initiating timely emergency response
  • Small enough mass/system that the accuracy of the data was questioned

Page 11 of 36

12 of 36

Page 12 of 36

13 of 36

Page 13 of 36

14 of 36

Shielding made the difference

Page 14 of 36

20-cm thick

15 of 36

Mayak Production Association, 16 December 1965

  • Residue recovery process area
    • Residues generated from dissolution/precipitation/reduction processes
      • Difficult to recover (dissolution)
  • Dissolution vessel
    • Uranyl Nitrate solution
  • Facility was equipped with a criticality accident alarm system

Page 15 of 36

16 of 36

Page 16 of 36

17 of 36

The Setting

  • Residue dissolution glovebox
    • Three identical sets of process equipment, operated by vacuum transfers
      • Parallel operation
      • Cylindrical dissolution vessel
      • Holding vessel, Filter vessel & Filtrate receiving vessel
  • Dissolution vessels
    • 45 cm in diameter, 100 liters in volume
      • Pulsating mixer
      • Feed hopper with sealable flat cover plate
      • Pressure relief valve
      • 2.5 cm, steam water jacket for heating

Page 17 of 36

18 of 36

Dissolution & Filtration Process

  • Residue introduced via feed hopper
  • Acid and heat were added to the system
  • Normal process
    • 100 ºC
    • 1.5 hours
    • constant mixing
  • Transferred to hold vessel
  • Filtered

Page 18 of 36

19 of 36

Residue Dissolution Glovebox

Page 19 of 36

20 of 36

15 December 1965

  • In a related operation
    • A supervisor ordered burning of batch #1726
    • #1726 had >1% by weight U
    • Violation of criticality safety limit for the furnace
  • After burning batch #1726 was
    • Sampled and sent to a dissolution feed staging glovebox with other batches
      • Before receiving sample results

Page 20 of 36

21 of 36

The Lead-Up Events

  • An operator, preparing material for dissolution discovered that batch #1726 had no analysis results
    • Phoned the analytical laboratory
    • Informed batch #1726 was 0.32% by weight uranium
  • In reality:
    • The operator had been given the analytical results of batch #1826
    • #1726 was 44% by weight uranium, 138 times greater

Page 21 of 36

22 of 36

The Lead-Up Events on 16 December 1965

  • 5 kg of #1726 were loaded into dissolution vessel #1
      • 2.2kg of U(90)
        • 1980 g of 235U
      • Criticality safety limit was 300 grams
      • Unknowingly the limit was violated by > 6
  • After 40 minutes the process was shutdown
    • Accommodate cleaning for shift change

Page 22 of 36

23 of 36

The Accident

  • 10 minutes after shutting the system down the nearest criticality alarm sounded momentarily
  • The operator reported to the control room per procedure
      • While at the control room the alarm again sounded
      • Shortly thereafter ~22:10 additional more distant alarms began sounding
      • The building was evacuated (tunnel muster point)

Page 23 of 36

24 of 36

The Response

  • Dissolution vessel #1 or its holding vessel was determined to be the accident location based on
    • Personnel interviews
    • Accountability records
    • System schematics
  • Surveys indicated
    • ~8 R/h @ 2m from the glovebox during minima

Page 24 of 36

25 of 36

The Response (cont’d)

  • Accident monitored from a nearby building (~50m)
    • Between ~22:10 and 23:00 four additional power peaks were observed
      • The accident was clearly on-going and cyclical
    • 23:00 emergency response personnel arrived
      • Criticality safety, facility management, health physics
      • Determined the control room could be safely re-entered and moved their recovery operations

Page 25 of 36

26 of 36

The Response (cont’d)

  • After the 9th excursion, Cd poisoned solution was remotely pumped to the holding vessel
  • Arguments between the criticality safety representative and process supervision developed
      • Process supervision wanted to re-occupy the area and begin recovery/clean-up
  • After ~20 minutes, while the argument was still on-going, a 10th excursion occurred
      • Firmly established that the accident site as dissolution vessel

Page 26 of 36

27 of 36

The Response (cont’d)

  • Draining or adding Cd solution to the dissolution vessel was considered too dangerous
    • Multiple operators
    • Time intensive valve manipulations
  • The recovery team decided to send personnel in separately to:
    • Remove the gloves from two glovebox ports
    • Unlock and open the feed hopper lid
    • CAREFULLY insert a wadded-up piece of Cd foil into the nitric acid solution

Page 27 of 36

28 of 36

The Response (cont’d)

  • After preparation
    • Tasks 1 and 2 were accomplished separately
      • Two specially chosen operators
      • ~30 and ~60 seconds, respectively
  • Recovery was then halted as radiation reading indicated that an 11th excursion was underway

Page 28 of 36

29 of 36

The Response (cont’d)

  • After this excursion and appropriate waiting period
    • A senior engineer (NCS specialist) entered the area
    • Placed the foil on top of the solution through the hopper
    • The foil dissolved and the excursions were terminated

Page 29 of 36

30 of 36

Consequences

  • 5.5 x 1017 fissions total, 26 liters, 69 g235U/l
  • Exposures
    • Recovery team members limited to 0.3 rem
    • 3 between 0.2 and 0.27 rem
    • 7 between 0.1 and 0.2 rem
    • 17 @ 0.1 rem or less
  • Operations resumed the next day
  • 94% of process equipment was replaced with favorable geometry over the next 2 to 3 years

Page 30 of 36

31 of 36

Causality: The New View

  • Prior to 1990, accident discussion often focused on “the cause”.
  • The 2000 report emphasizes “no single cause”. Each accident resulted from a series of conditions or events that, in combination, set the stage.
  • Consistent with Sidney Dekker’s book:
    • Excellent resource to understand and address failures in complex systems

Page 31 of 36

32 of 36

Notable Differences in the 2000 Revision

  • Importance of sharing the information
  • Less emphasis on non-routine operations
  • Highlights lack of familiarity with the operations
  • Integrating NCS with material accountability
    • Recent emphasis on holdup monitoring
    • NCSP training class has a module on NDA
  • Operations should know how to respond to malfunctions and mistakes
  • Avoid unapproved actions after evacuation
  • Awareness of the hazard and stop work authority

Page 32 of 36

33 of 36

Notable Differences in the 2000 Revision

  • Making ease of operation a goal
  • Support for self-reporting of upsets (more learning, less punishing)
  • Key conclusion: All accidents have been dominated by design, managerial, and operational failures. The focus for prevention should be on these issues.

Page 33 of 36

34 of 36

Follow-Up Efforts

  • In early 2000’s more meetings were held to promote further collaborations between US & Russian Labs
  • Technical representatives from Arzamas met with us at LANL
    • Held a review of the Zhakarov accident 17 June, 1997

Page 34 of 36

35 of 36

Conclusion

  • Including the Russian experience makes the 2000 Report a much more valuable resource.
    • Particularly the section on Observations & Lessons Learned
    • Further illumination of “the human element”
  • Collective experience is key to doing a thorough hazard analysis (or safety case) for new or modified processes

Page 35 of 36

36 of 36

Q&A Time

36