FROM WASTE ENERGY�TO BUSINESS VALUE
Turning Energy Losses into Savings, Productivity & New Value
Energy Efficiency • Recovery • Reuse • Monetization
Slamet Ristono, ST. MM
PART I
BACKGROUND & REGULASI
The Energy Paradox
ENERGY PURCHASED
ENERGY USED
Useful work
Comfort
Production
Services
ENERGY WASTED
Heat
Exhaust
Losses
Standby / inefficiency
The opportunity is hidden between “energy purchased” and “useful energy delivered.”
Electricity
Fuel
Steam
Cooling / Heating
kerangka untuk menilai apakah suatu perusahaan menjalankan bisnis secara berkelanjutan, bertanggung jawab, dan dikelola dengan baik.
Why Waste Energy Is Now a Business Issue
Energy cost ↑
Regulatory pressure ↑
Carbon / ESG expectations ↑
Asset performance expectations ↑
Operational resilience matters more than ever
THE BUSINESS QUESTION
How much energy are we buying?
How much are we actually using?
How much are we throwing away?
How much can be converted into value?
Environmental, Social, and Governance (ESG): kerangka untuk menilai apakah suatu perusahaan menjalankan bisnis secara berkelanjutan, bertanggung jawab, dan dikelola dengan baik.
Indonesia Regulatory Landscape
From compliance to value creation
LAW
GOV. REG.
Konservasi
Energi
ESDM
BUILDING
CORPORATE
Regulation is the driver; measurement, projects and business cases turn compliance into economic value.
Landasan kebijakan untuk implementasi manajemen energi, efisiensi energi, dan penguatan ekosistem jasa konservasi energi
1
PP No. 33 Tahun 2023
Konservasi Energi
•
Melindungi upaya konservasi energi nasional
•
Mendorong konservasi energi pada pengguna energi, pengguna sumber energi, dan pengusaha energi
•
Mendukung manajemen energi secara efisien & hemat, penghematan, ESCO, pengadaan konservasi, dan kerja sama
2
Permen ESDM No. 8 Tahun 2025
Manajemen Energi
•
Mengatur kewajiban pelaksanaan manajemen energi bagi entitas di sektor tertentu
•
Mendorong efisiensi energi, audit energi, pelaporan aktivitas, serta pemberian dan penghargaan
•
Memuat pembiayaan, sertifikasi kompetensi, skema kredit-karbon
3
Permen ESDM No. 3 Tahun 2025
Konservasi Energi oleh Pemerintah dan Pemerintah Daerah
•
Mengatur peran pemerintah dan pemerintah daerah dalam konservasi energi
•
Mendorong penghematan energi pada bangunan, fasilitas, dan operasional pemerintah
•
Memperkuat peran pemerintah sebagai teladan efisiensi energi
4
Permen ESDM No. 1 Tahun 2026
Usaha Jasa Konservasi Energi
•
Mengatur penyelenggaraan usaha jasa konservasi energi/ESCO
•
Mendorong layanan energi yang efisien, kompetitif, berbasis, dan pemeliharaan
•
Memperkuat ekosistem implementasi proyek konservasi energi
Keterkaitan Regulasi
PP 33/2023 → Permen 8/2025 → Permen 3/2025 → Permen 1/2026
Pesan Utama
Regulasi berawal dari kebijakan umum menuju implementasi teknis�Fokusnya tidak hanya kepatuhan, tetapi juga penghematan biaya dan penurunan emisi. Sinergi regulasi mempercepat transisi energi dan daya saing industri
Regulasi Kunci Konservasi Energi
From Regulatory Compliance to Business Strategy
1 COMPLIANCE
Meet requirements
2 MONITORING
Know consumption
3 EFFICIENCY
Reduce waste
4 OPTIMIZATION
Improve systems
5 RECOVERY
Capture waste energy
6 MONETIZATION
Create value
TARGET:
to
“energy value creation”
move from “energy compliance”
PART II
WHERE IS THE WASTE?
Where Does Energy Go?
Energy in → useful energy + waste energy
Potential source of avoidable loss
Energy Waste Mapping
ENERGY AUDIT
ENERGY BALANCE
WASTE IDENTIFICATION
QUANTIFICATION
RECOVERY
POTENTIAL
BUSINESS CASE
You cannot manage on what you cannot measure.
Measure 🡪 Analyze 🡪 Decide
Energy Balance — Find the Hidden Asset
INPUT
1,000 MWh
USEFUL ENERGY
650 MWh
DISTRIBUTION + EQUIPMENT LOSS
250 MWh
OTHER / WASTE
100 MWh
KEY QUESTION
How much of the 350 MWh “non-useful” energy can be eliminated, optimized or recovered?
That is the opportunity pipeline.
Measurement & Verification
MEASURE → ANALYZE → VERIFY → IMPROVE
Use ISO 50001 / ISO 50002 / ISO 50015 principles as appropriate.
Build a defensible baseline before claiming savings.
PART III
FROM WASTE ENERGY TO RECOVERY
Five Strategies to Create Value
REDUCE
Eliminate unnecessary demand
OPTIMIZE
Improve system efficiency
RECOVER
Capture waste energy
REUSE
Use recovered energy elsewhere
MONETIZE
Convert savings into business value
The highest-value projects often combine more than one strategy.
Waste Heat Recovery
Example: chiller condenser heat
BEFORE
Chiller
→ Condenser
→ Cooling Tower
→ Atmosphere
RECOVERY
Chiller
→ Heat Exchanger
→ Hot Water
→ Storage / Distribution
VALUE
Reduce boiler / electric-heater demand
Reduce cooling tower rejection
Improve overall system efficiency
Reduce OPEX + CO₂
The Business Value Equation
WASTE ENERGY
Heat
Exhaust
Losses
Rejected energy
RECOVERY / EFFICIENCY
Technology
Controls
Optimization
Reuse
BUSINESS VALUE
Energy saving
OPEX reduction
CO₂ reduction
Asset performance
ROI / NPV / IRR
Annual Financial Saving = Energy Saving × Applicable Tariff
Decision Framework
TECHNICAL
Feasibility, safety, reliability
FINANCIAL
CAPEX, OPEX, NPV, IRR
OPERATIONAL
Maintainability, uptime, integration
ESG
Energy, carbon, reporting
STRATEGIC
Scalability, resilience, reputation
PART IV
IMPLEMENTATION
Case Study Energy Audit
Temperature, Humidity & Water Flowrate Measurement
entering, leaving the evaporator
Chiller Unit
a.
Performing Installation 4 sets of data loggers (temperature, Humidity sensors) in operational conditions:
Cooling Tower
b.
water in, water out
air in, air out
Chiller Unit
a.
Performing Installation 3 sets of Ultrasonic Water Flow Meter (UWFM) in operational conditions:
Chiller Plant
b.
leaving evaporator
1
2
leaving header evaporator
Delivery:
ΔT Evaporator (°C)
3
ΔT Condensor (°C)
Water Flowrate Evaporator (GPM)
Water Flowrate Condenser (GPM)
Methodology Of VAC Audit
ambient
entering condensor
entering condensor
ambient
Temp. (°C). RH Ambient (%)
Power Quality Analyzer & IR-Thermography Measurement
Electrical distribution panel
Chiller Unit
a.
Performing Installation 2 sets of Power Quality Analyzer (PQA) in operational conditions
Chiller Plant (Main Panel CHWPp, Main panel CHWPs dan main panel CWP & CT)
b.
1
Delivery:
Power (Watt)
Voltage (Volt)
Current (Ampere)
KVAR & KVA
Power Factor
Frequency
THDF Current
THDF Voltage
physical thermal profile of the panel
3
IR – Thermography inspection
2
VAC SYSTEM AUDIT
Electrical distribution panel
PART V
RESULT AUDIT
PART V
NAME PLATE CHILLER PLANT
ITEM | DESCRIPTION |
Chilled Water Pump Primer (CHWPp) | |
Merk | EBARA |
Model | 300 x 250 CNGA |
Power | 5 x 90 KW - (Standby 1 unit) |
Waterflow Capacity | 5 x 3,740 GPM |
Head | 80 ft |
ITEM | DESCRIPTION |
Condenser Water Pump (CWP) | |
Merk | EBARA |
Model | 400 x 350 CNFA |
Power | 5 x 185 KW - (Standby 1 unit) |
Waterflow Capacity | 5 x 7,000 GPM |
Head | 80 ft |
ITEM | DESCRIPTION |
Chilled Water Pump Secondary (CHWPs) Zone 1 | |
Merk | EBARA |
Model | 250x150 CNJA |
Power | 2 x 150 KW - (Standby 1 unit) |
Waterflow Capacity | 2 x 2,180 GPM |
Head | 240 ft |
Chilled Water Pump Secondary (CHWPs) Zone 2A & 2B | |
Merk | EBARA |
Model | 300 x 250 CNHA |
Power | 3 x 335 KW - (Standby 1 unit) |
Waterflow Capacity | 3 x 5,800 GPM |
Head | 180 ft |
Chilled Water Pump Secondary (CHWPs) Zone 3 & 4 | |
Merk | EBARA |
Model | 300 x 200 CNJA |
Power | 2 x 250 KW - (Standby 1 unit) |
Waterflow Capacity | 2 x 3,760 GPM |
Head | 180 ft |
NAME PLATE CHILLER PLANT
Evaporator | Leaving | Entering | ΔT Temp | Water flowrate |
[°C] | [°C] | [°C] | [GPM] | |
Chiller - 1 | 6.57 | 11.59 | 5.01 | 3345.60 |
Chiller - 2 | 6.97 | 11.87 | 4.91 | 3349.81 |
Chiller - 3 | 6.92 | 11.76 | 4.84 | 3188.70 |
Chiller - 4 | 6.99 | 11.72 | 4.72 | 3415.49 |
Total | | | | 13299.6 |
RINGKASAN PERFORMA CHILLER UNIT 1-4
Condenser | Leaving | Entering | ΔT Temp | Water flowrate � |
[°C] | [°C] | [°C] | [GPM] | |
Chiller - 1 | 33 | 30 | 3.46 | 5229 |
Chiller - 2 | 34 | 30 | 3.30 | 5287 |
Chiller - 3 | 34 | 30 | 3.40 | 4889 |
Chiller - 4 | 34 | 31 | 3.28 | 5371 |
Total | | | | 20776 |
CHILLER UNIT�WDC 126 CAACM | Design | Actual working load | ||||
Chiller-1 | Chiller-2 | Chiller-3 | Chiller-4 | TOTAL | ||
Cooling Capacity [TR] | 2100.00 | 1258.29 | 1231.33 | 1156.59 | 1209.78 | 4856.00 |
Power [kW] | 1183.10 | 991.35 | 882.85 | 894.88 | 845.67 | 3614.75 |
Heat Rejection [TR] | 2662.67 | 1358.26 | 1307.82 | 1247.19 | 1318.93 | 5232.21 |
Loads Cooling Capacity [%] | 100% | 60% | 59% | 55% | 58% | 58% |
Efficiency |
|
|
|
|
|
|
KW/TR Chiller Unit | 0.563 | 0.790 | 0.718 | 0.781 | 0.703 |
|
COP Chiller Unit | 6.24 | 4.45 | 4.90 | 4.51 | 5.00 |
|
Audit Energi HVAC I Bandara Soekarno Hatta T-3
11/09/2026
RINGKASAN PERFORMA COOLING TOWER
COOLING TOWER�KMB-2600R | Design | Actual working load | ||||
CT-1 | CT-2 | CT-3 | CT-4 | TOTAL | ||
Cooling Capacity [TR] | 2626.67 | 1366.08 | 1365.48 | 1217.21 | 1300.07 | 5248.84 |
Water flow rate [GPM] | 6996.16 | 5049.88 | 4965.13 | 4939.83 | 4862.66 | 19817.49 |
Water Inlet [°C] | 36.00 | 34.14 | 33.58 | 32.33 | 33.34 |
|
Water Oulet [°C] | 31.00 | 30.53 | 29.92 | 29.05 | 29.78 |
|
Performance Heat Rejection |
|
|
|
|
| |
Loads Cooling Capacity [%] | 100% | 52% | 52% | 46% | 49% | 49% |
Cooling Tower | Temp Water in | Temp Water Out | Water flowrate | ||
[°C] | [°C] | [GPM] | Design [GPM] | Percentage [%] | |
Cooling Tower - 1 | 34 | 31 | 5049.88 | 6996.16 | 72% |
Cooling Tower - 2 | 34 | 30 | 4965.13 | 6996.16 | 71% |
Cooling Tower - 3 | 32 | 29 | 4939.83 | 6996.16 | 71% |
Cooling Tower - 4 | 33 | 30 | 4862.66 | 6996.16 | 70% |
TOTAL | | | 19817.49 | 27984.63 | 71% |
11/09/2026
RINGKASAN PERFORMA CHILLER PLANT
CHILLER PLANT | Design | Weekday | Weekend | ||||
Actual working load | Percentage [%] | Efficiency�[kW/TR] | Actual working load | Percentage [%] | Efficiency �[kW/TR] | ||
Cooling Capacity [TR] | 8400.00 | 4749.68 | 57% | 1.130 | 4982.38 | 59% | 1.054 |
Power [kW] | 6999.99 | 5343.95 | 77% | 5232.06 | 75% | ||
Heat Rejection [TR] | 10650.68 | 5043.98 | 47% | 5340.06 | 50% | ||
No | Panel | | Power (kW) | |||
| | Maksimal | Rata-Rata | Minimal | ||
1 | LV-8A1 | | | 629.70 | 383.63 | 98.40 |
2 | LV-8B1 | | | 882.80 | 567.00 | 215.20 |
3 | LV-8H1 | | | 1237.10 | 944.38 | 637.50 |
Average Total Power Chiller :
3552.21 kW
Average Power Pump & Cooling Tower :
1729.43 kW
Unit | Design (kW) |
Chiller Unit | 4732.4 |
Cooling Tower | 97.5 |
CHWPs | 1070 |
CHWPp | 360 |
CWP | 740 |
TOTAL | 6999.9 |
Ringkasan PQA Panel LVMDP (Distribusi: Pompa CHWPp, CHWPs, CWP, Cooling Tower & Utility)
RINGKASAN PENGUKURAN TERHADAP DESAIN
Chiller Unit | Chilled Water Pump primary (CHWPp) | Chilled Water Pump Secondary (CHWPs) | ||||||||
Unit | Water flowrate�Evap [GPM] | Water flowrate�Evap [GPM] | Load Capacity�[TR] | Unit | Water flowrate�[GPM] | Actual | Unit | Water flowrate�[GPM] | Actual Running | |
Chiller - 1 | 3,700 | 3,700 | 2,100 | CHWPp - 1 | 3,740 | 3,740 | CHWPs - (Zone 1)-1 | 2,180 | 2,180 | |
Chiller - 2 | 3,700 | 3,700 | 2,100 | CHWPp - 2 | 3,740 | 3,740 | CHWPs - (Zone 1)-1.1 | 2,180 | standby | |
Chiller - 3 | 3,700 | 3,700 | 2,100 | CHWPp - 3 | 3,740 | 3,740 | CHWPs - (Zone 2A & Zone 2B)-1 | 5,800 | 5,800 | |
Chiller - 4 | 3,700 | 3,700 | 2,100 | CHWPp - 4 | 3,740 | 3,740 | CHWPs - (Zone 2A & Zone 2B)-2 | 5,800 | 5,800 | |
Chiller - 5 | 3,700 | standby | standby | CHWPp - 5 | 3,740 | standby | CHWPs - (Zone 2A & Zone 2B)-3 | 5,800 | standby | |
| CHWPs - (Zone 3 & Zone 4)-1 | 3,760 | 3,760 | |||||||
CHWPs - (Zone 3 & Zone 4)-2 | 3,760 | standby | ||||||||
TOTAL | 18,500 | 14,800 | 8,400 |
| 18,700 | 14,960 |
| 29,280 | 17,540 | |
Actual Measurement AVG | 13,300 | 4,856 |
| 13,949 | ||||||
Dev | 1,500 | 3,544 | 3,591 | |||||||
Percentage | 90% | 58% | 80% | |||||||
COOLING LOAD CHILLER PLANT (CH 1 - CH 4) - WEEKDAY
COOLING LOAD CHILLER PLANT (CH 1 - CH 4) - WEEKDAY
PERFOMANCE CHILLER PLANT (CH 1 - CH 4) - WEEKDAY
PART VI
PERFORMA AHU
Audit Energi HVAC I Bandara Soekarno Hatta T-3
33
11/09/2026
RINGKASAN PERFORMA ACTUAL LOAD PER ZONE & BTU/h/m2
Cooling Capacity. per Zone | Design AHU | Weekday | Weekend | ||
Actual working load | Percentage [%] | Actual working load | Percentage [%] | ||
Zone 1 [TR] | 1158.18 | 689.58 | 60% | 732.84 | 63% |
Zone 2A & 2B [TR] | 6054.30 | 2951.57 | 49% | 3065.60 | 51% |
Zone 3 & 4 [TR] | 2013.39 | 1108.54 | 55% | 1151.43 | 57% |
TOTAL | 9225.87 | 4749.68 | 51% | 4949.87 | 54% |
Zone | Area | Design | Actual working load | |||
Weekday | Weekend | |||||
[m2] | [BTUH/m2] | [BTUH/m2] | Percentage [%] | [BTUH/m2] | Percentage [%] | |
Zone 1 | 24,968.42 | 556.63 | 331.42 | 59.5% | 352.21 | 63% |
Zone 2A & 2B | 77,195.18 | 941.14 | 458.82 | 48.8% | 476.55 | 51% |
Zone 3 & 4 | 39,289.92 | 614.93 | 338.57 | 55.1% | 351.67 | 57% |
Average Zone | 704.23 | 376.27 | 53% | 393.48 | 56% | |
MEASUREMENT AHU | |||||||
SAMPLING MEASUREMENT 47 AHU | Water Side | Air Side | |||||
ΔT Temp | Design Water flowrate [GPM] | Measurement Water flowrate�[GPM] | Design Load Cap [TR] | Measurement Load Cap�[TR] | Design Debit [CFM] | Measurement Debit�[CFM] | |
Zone 1 | 4.09 | 1,334 | 1,811 | 822 | 489 | 212,600 | 72,717 |
Zone 2A & 2B | 3.92 | 1,955 | 2,011 | 1,104 | 779 | 268,610 | 79,739 |
Zone 3 & 4 | 2.93 | 2,911 | 3,896 | 1,641 | 823 | 435,040 | 161,646 |
TOTAL | 6,200 | 7,718 | 3,567 | 2,092 | 916,250 | 314,102 | |
Dev |
|
| (1,518) |
| 1,475 |
| 602,148 |
Percentage |
|
| 124% |
| 59% |
| 34% |
RINGKASAN HASIL PENGUKURAN AHU TERHADAP DESAIN
Rasio Kebutuhan Aliran Udara Terhadap Kapsitas Pendinginan | Total AHU Debit (CFM) | ||||
Aktual CFM/TR | Design CFM/TR | Improvement CFM/TR | Measurement | Improve as Per Design | Efisiensi Cost / Tahun |
150,14 | 256,87 | 0,42 | 2.092,00 | 2.961,19 | Rp407.716.865 |
Summary 47 Unit AHU terukur | Water Flowrate [GPM] | Cooling Capacity [BTU/h] | Air Flow [CFM] | ||||||
Design | Actual | Percentage | Design | Actual | Percentage | Design | Actual | Percentage | |
Zone 1 | 1,470 | 1,661 | 113% | 9,925,200 | 5,870,907 | 59% | 212,600 | 72,717 | 34% |
Zone 2A & 2B | 1,955 | 2,301 | 118% | 13,196,250 | 8,405,067 | 64% | 268,610 | 79,739 | 30% |
Zone 3 & 4 | 2,911 | 3,896 | 134% | 19,646,550 | 9,877,794 | 50% | 435,040 | 161,646 | 37% |
TOTAL | 6,336 | 7,858 | 124% | 42,768,000 | 24,153,768 | 56% | 916,250 | 314,102 | 34% |
RINGKASAN HASIL PENGUKURAN KINERJA AHU SAMPLING SEMUA ZONE
PART VII
FROM ENERGY TO MONEY
CURRENT CHILLER PLANT PERFORMANCE = 1.13
Chiller Plant Efficiency Benchmark – Reference: ASHRAE Journal
Actual Chiller Plant Efficiency = 1,09 kW / TR
Chiller Plant Efficiency Target = 0,83 kW / TR
TECHNICAL DATA SHEET - DAIKIN
Actual Chiller Performance 0,75kw / TR
PERHITUNGAN OPTIMALISASI EFISIENSI KINERJA UNIT CHILLER
Pengurangan emisi:
Setara dengan penyerapan karbon oleh 14,8 ribu pohon/tahun
Index:
Unit Chiller | Kapasitas | Daya | Efisiensi Chiller | Efisiensi Cost / Tahun | Energi Efisiensi / Tahun (kWH) | Pengurangan Emisi / Bulan (ton CO2/Tahun) | ||
Design (kW/TR) | Performance Existing (kW/TR) | Improvement Performance (kW/TR) | ||||||
Chiller 1 | 2100 | 1.183,10 | 0,56 | 0,79 | 29% | Rp2,74 Miliar | 2.384.830 | 2.741 |
Chiller 2 | 2100 | 1.183,10 | 0,56 | 0,72 | 22% | Rp1,87 Miliar | 1.627.137 | 1.870 |
Chiller 3 | 2100 | 1.183,10 | 0,56 | 0,78 | 28% | Rp2,63 Miliar | 2.290.118 | 2.632 |
Chiller 4 | 2100 | 1.183,10 | 0,56 | 0,70 | 20% | Rp1,65 Miliar | 1.437.713 | 1.653 |
| | | | | Total | Rp8,9 Miliar | 7.739.798 | 8.896 |
PERHITUNGAN OPTIMALISASI EFISIENSI KINERJA CHILLER PLANT
Pengurangan emisi:
Setara dengan penyerapan karbon oleh 18 ribu pohon/tahun
Index:
Unit Chiller | Kapasitas | Daya | Efisiensi Chiller | Efisiensi Cost / Tahun | Pengurangan Emisi / Bulan (ton CO2/Tahun) | |||
Design (kW/TR) | Performance Existing Weekday (kW/TR) | Performance Existing Weekend | Improvement Performance (kW/TR) | |||||
Chiller 1-4 | 8400 | 6.999,99 | 0,83 | 1,13 | 1,05 | 23% | Rp13.368.741.173 | 10.865 |
| | | | | | Total | Rp13.368.741.173 | 10.865 |
PERHITUNGAN OPTIMALISASI EFISIENSI KINERJA UNIT POMPA SEKUNDER
Pengurangan emisi:
Setara dengan penyerapan karbon oleh 934pohon/tahun
Index:
Unit Chiller | Actual Flowrate (GPM) | Design Flowrate (GPM) | % Improvement Optimation | Daya | Efisiensi Cost / Tahun | Pengurangan Emisi / Bulan (ton CO2/Tahun) |
Pompa Sekunder | 7858 | 6336 | 24% | 1.070,00 | Rp1.479.975.689 | 46,69 |
| | | | | Rp1.479.975.689 | 46,69 |
Achievement
Indikator | Achievement / Year |
Energy Reduction | 20.422.276 kWH |
Pencapaian Efisensi |
|
Pengurangan biaya energi | Rp 24,15 miliar |
Pengurangan emisi | 20.322 Ton CO2/ Tahun |
Setara penyerapan karbon oleh pohon | 34.383 pohon |
DON’T JUST REDUCE ENERGY COST.
CREATE VALUE FROM ENERGY.
FROM WASTE ENERGY → BUSINESS VALUE
Financial value • Operational value • Strategic value