Measure D Bond Program Update
Presentation to the Measure D Citizens Bond Oversight Committee
August 27, 2026
What We’ll Cover Today
Phase One Project Team
Board of Trustees
Administration
General Contractor
Program Manager
Architect of Record
Phase One Projects:
Approved by the Board of Trustees June 10, 2025
Status Update:
Phase One - Increment one
Current Project Scope: Donald Rheem
Recommended Projects (Over 70 points):
The New Classroom and Learning Center is already approved and in progress.
There are several projects that are likely given point value, feasibility, cost, and need including:
Additional projects with matching funds:
Projects appropriate for Deferred Maintenance:
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
Current Project Scope: Joaquin Moraga
Recommended Projects (Over 70 points):
Fire alarm replacement has already been approved.
There are several projects that are likely given point value, feasibility, cost, and need including:
Additional projects with matching funds:
Projects appropriate for Deferred Maintenance:
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
Summer 2026 work
Challenges and Successes
Challenges:
Successes:
Contingencies and Allowances
Contingencies and allowances factored into project budgets:
Contractor Construction Contingency | $791,281.00 |
Owner Construction Contingency | $782,281.00 |
DSA Reconciliation Allowance in GMP | $474,183.00 |
Hazmatt Remediation Allowance | $500,00.00 |
Total Contingencies and Allowances: | $2,5247,745.00 |
At this time none of the Hazmatt Remediation Allowance has been requested. As demolition is complete we would like to reassign this allowance to accommodate the ADA Path of Travel Upgrades DSA required at Rheem ES.
Phase One - Increment two:
Rheem Modular Classrooms
Phase two projects
Bond team is initiating planning and design development for:
*Dependent upon availability of funds
Recommendations: Camino Pablo
Recommended Projects (Over 70 points):
There are several projects that are likely given point value, feasibility, cost, and need including:
Additional projects with matching funds:
Projects appropriate for Deferred Maintenance:
✔
✔
✔
✔
✔
✔
✔
✔
✔
Recommendations: Los Perales
Recommended Projects (Over 70 points):
Sewer repair has already been completed (✔).
There are several projects that are likely given point value, feasibility, cost, and need including:
Additional projects with matching funds:
Projects appropriate for Deferred Maintenance:
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
✔
Phase Two Process and Actions
Project Budget Summary (EACH SITE)
From the June 3, 2025 Measure D Project Initiation Plan Presentation to the Board of Trustees
Project Milestones
JM Furniture install
Summer 2026 work launch - Phase I
Weekly OAC meetings
July 28 - CBOC site walk
Summer work completion - Aug 8
Phase II planning
Phase I work continues
Pre-Con planning / phasing / pricing
CBOC Quarterly Mtg.?
DSA comments, feedback
Adopt GMP for Phase II projects
CBOC Quarterly Mtg.
Phase I work continues
Finalize Phase II design / submit to DSA
Conduct RFQP GC selection for Phase II
Conduct / finalize Series B bond sale
Finalize Rheem modular package
DSA plan approval of Phase II projects
Commence Summer 2027 Phase one projects
Start of Construction on Phase II projects
“Pardon Our Dust”
Phase I work continues
Initiate preconst. Planning for Phase II projects
Initiate Rheem modular project
CBOC Quarterly mtg.
Bond Program Overview
FY 2026-27
July-Sept.
Oct.-Dec.
Jan.-Feb
Mar./Apr.
May/June
Financial Report - June 2026
Committed Bond Funds- June 2026
Committed Bond Funds- June 2026
Financial Report - July 2026
Committed Bond Funds- July 2026
Series B Bond Issuance
Closing
Questions or comments?