DEPARTMENT OF
PUBLIC WORKS
Thank you for joining us
Please Mute Your Device
Click to Mute
VERNON PUMPING STATION �IMPROVEMENTS�
WATER CONTRACT NO. 1229
Additional improvements include interior and exterior architectural upgrades, replacement of existing valves and valve vaults and site, structural, HVAC, instrumentation and electrical improvements
Existing 48-inch main, 48-inch discharge, as well as 24-inch overflow pipes are nearing 50-year life expectancy mark and will be replaced with a new 72-inch main, 66-inch discharge, and 48-inch overflow which will travel underneath I-83.
The 18’ X 15’ Utility Tunnel beneath I-83 will accommodate:
Tunneling beneath I-83 may require the use of explosives to remove rock within the tunnel alignment. This would likely occur during nighttime hours and would require the brief stoppage of traffic on I-83.
Construction is expected to start by the end of June or early July of 2024.