Lexington High School Project
Other High School cost information for School Building Committee
August 12th, 2024
LHS Anticipated Project Timeline - Estimating
Town Meeting & Debt Exclusion Votes – Nov/Dec 2025
2025
2026
2024
2027
2028
2029
2030
Initial Design
Finish Design / Early Site
Construction
2031
Move-in
2029/2030
April 24
PDP
Conceptual Cost
Comparisons
Nov 24
PSR
Initial Estimate
Aug 25
SD
Estimate
March 26
DD
Estimate
August 26
CD 60%
Estimate
Jan 27
CD 90%
Estimate
May 27
GMP
Final Bids
PDP = Preliminary Design Program
PSR = Preferred Schematic Report
SD = Schematic Design Drawings
DD = Design Development Drawings
CD = Construction Documents
GMP = Guaranteed Maximum Price (Final Bid)
2
August 12th, 2024
Conceptual Pricing
The costs for the various PDP Options indicated below are intended to be an analysis of the relative costs between options and NOT a prediction of the actual final cost of any individual option. Major variables such as geotechnical, site grading, wetland determination, structural system and final MEP systems have yet to be designed and costs will vary significantly from the benchmark cost estimating included as part of this PDP cost analysis. The costs outlined in this report should not be represented as the FINAL construction budget and have a +/- 10% degree of accuracy.
PDP estimates utilize SF data from all recent high schools
3
August 12th, 2024
Conceptual Pricing
Table A - Massing Study Alternates | | Construction Costs Only | | | | | |||
Scope Option | Scope Description | GSF | Average between 2 cost estimators | Structured Parking | Total Construction $psf | Soft cost (20%) | Owner Contingency (5%) | Modulars | Total Project Cost |
Option A.1 | Base Repair/Code Upgrade - No architetcural | 352,000 | $ 222,000,000 |
| $ 222,000,000 | $ 44,400,000 | $ 11,100,000 | $ 23,100,000 | $ 301,000,000 |
Option B.1 | Add/Reno - Phased in place, retaing buildings G&J structure | 440,816 | $ 493,000,000 |
| $ 493,000,000 | $ 98,600,000 | $ 24,650,000 | $ 19,250,000 | $ 636,000,000 |
Option B.2 | Add/Reno - Addition on fields, retaing building G&J structure | 440,816 | $ 475,000,000 |
| $ 475,000,000 | $ 95,000,000 | $ 23,750,000 |
| $ 594,000,000 |
Option B.3 | Add/Reno - 4 story. Includes structure parking. Phased in place retaining buildings C&D | 440,816 | $ 501,000,000 | $ 22,016,250 | $ 523,016,250 | $ 104,603,250 | $ 26,150,813 | $ 11,550,000 | $ 665,000,000 |
Option C.1a | New Construction - 3 Story. On fields, 1 phase | 440,816 | $ 487,000,000 |
| $ 487,000,000 | $ 97,400,000 | $ 24,350,000 |
| $ 609,000,000 |
Option C.1b | New Construction - 4 story. On fields, 1 phase | 440,816 | $ 479,000,000 |
| $ 479,000,000 | $ 95,800,000 | $ 23,950,000 |
| $ 599,000,000 |
Option C.1c | New Construction - 5 story. On fields, 1 phase | 440,816 | $ 478,000,000 |
| $ 478,000,000 | $ 95,600,000 | $ 23,900,000 |
| $ 598,000,000 |
Option C.1d | New Construction - Includes structure parking. 4 Story. On fields, 1 phase, reduced wetlands impact | 440,817 | $ 476,000,000 | $ 22,016,250 | $ 498,016,250 | $ 99,603,250 | $ 24,900,813 |
| $ 623,000,000 |
Option C.2a | New Construction - 3 story. On fields, 1 phase | 440,816 | $ 485,000,000 |
| $ 485,000,000 | $ 97,000,000 | $ 24,250,000 |
| $ 606,000,000 |
Option C.2b | New Construction - 4story. On fields, 1 phase | 440,816 | $ 478,000,000 |
| $ 478,000,000 | $ 95,600,000 | $ 23,900,000 |
| $ 598,000,000 |
Option C.3a | New Construction - 3 story. On fields, 1 phase | 440,816 | $ 484,000,000 |
| $ 484,000,000 | $ 96,800,000 | $ 24,200,000 |
| $ 605,000,000 |
Option C.4a | New Construction - 3 story. On fields, 1 phase | 440,816 | $ 489,000,000 |
| $ 489,000,000 | $ 97,800,000 | $ 24,450,000 |
| $ 611,000,000 |
Option C.4b | New Construction - 4 story. On fields, 1 phase | 440,816 | $ 481,000,000 |
| $ 481,000,000 | $ 96,200,000 | $ 24,050,000 |
| $ 601,000,000 |
Option C.4c | New Construction - Includes structure parking. 4 story. On fields, 1 phase, reduced wetlands impact | 440,816 | $ 480,000,000 | $ 22,016,250 | $ 502,016,250 | $ 100,403,250 | $ 25,100,813 |
| $ 628,000,000 |
Option C.5 | New Construction - 4 story. On fields, 1 phase | 440,816 | $ 477,000,000 |
| $ 477,000,000 | $ 95,400,000 | $ 23,850,000 |
| $ 596,000,000 |
Option C.5b | New Construction - Includes structure parking. 4 story. On fields, 1 phase, reduced wetlands impact | 440,816 | $ 473,000,000 | $ 22,016,250 | $ 495,016,250 | $ 99,003,250 | $ 24,750,813 |
| $ 619,000,000 |
Option C.6 | New Construction - 4 story. On existing building footprint, multiple phases, reduced wetland and Article 97 impacts. | 440,816 | $ 481,000,000 |
| $ 481,000,000 | $ 96,200,000 | $ 24,050,000 | $ 11,550,000 | $ 613,000,000 |
Option D.1 | New Construction - 4 story. On fields, multiple phases | 440,816 | $ 486,000,000 |
| $ 486,000,000 | $ 97,200,000 | $ 24,300,000 |
| $ 608,000,000 |
| | | | | | | | | |
| New Construction options average (C.1a thru D.1) | 440816 | $ 481,000,000 |
|
| $ 96,200,000 | $ 24,050,000 |
| $ 601,250,000 |
| | |
| | | | | |
|
Average Construction cost of all new options $1,091psf Total project cost $1,364psf
4
August 12th, 2024
Comparison to other High Schools
| Arlington | Belmont | Revere | Waltham | Lexington |
Size | 408,590 | 445,100 | 422,600 | 414,854 | 440,816 |
Enrollment | 1,755 | 2,215 | 2,450 | 1,830 | 2,395 |
Construction Cost | $ 235,286,827 | $ 236,647,607 | $ 412,006,854 | $ 298,647,409 | $ 481,000,000 |
Construction $psf | $ 557 | $ 560 | $ 975 | $ 707 | $ 1,091 |
Soft cost | $ 55,564,993 | $ 58,511,582 | $ 85,511,047 | $ 75,919,978 | $ 120,250,000 |
Soft cost % vs construction | 24% | 25% | 21% | 25% | 25% |
Project Cost | $ 290,851,820 | $ 295,159,189 | $ 497,517,901 | $ 374,567,387 | $ 601,250,000 |
Project $psf | $ 688 | $ 698 | $ 1,177 | $ 886 | $ 1,364 |
Bid Date | April 2019 | April 2019 | March 2025 | End 2021 | July 2028 |
5
August 12th, 2024
Escalation
Basis of the historical data can be found here
6
August 12th, 2024
Comparison to other High Schools
| Arlington | Belmont | Revere | Waltham | Lexington |
Size | 408,590 | 445,100 | 422,600 | 414,854 | 440,816 |
Enrollment | 1,755 | 2,215 | 2,450 | 1,830 | 2,395 |
Construction Cost | $ 235,286,827 | $ 236,647,607 | $ 412,006,854 | $ 298,647,409 | $ 481,000,000 |
Construction $psf | $ 557 | $ 560 | $ 975 | $ 707 | $ 1,091 |
Soft cost | $ 55,564,993 | $ 58,511,582 | $ 85,511,047 | $ 75,919,978 | $ 120,250,000 |
Soft cost % vs construction | 24% | 25% | 21% | 25% | 25% |
Project Cost | $ 290,851,820 | $ 295,159,189 | $ 497,517,901 | $ 374,567,387 | $ 601,250,000 |
Project $psf | $ 688 | $ 698 | $ 1,177 | $ 886 | $ 1,364 |
Bid Date | April 2019 | April 2019 | March 2025 | End 2021 | July 2028 |
Project Cost Escalated to 7/2028 | $ 425,734,352 | $ 432,039,263 | $ 542,294,512 | $ 482,442,794 | N/A |
Escalated Project cost $psf | $ 1,042 | $ 971 | $ 1,283 | $ 1,163 | $ 1,364 |
7
August 12th, 2024
Lexington Scope included in PDP estimates
8
August 22, 2024
Comparison to other High Schools
9
August 12th, 2024
Other cost considerations
10
August 12th, 2024
Other cost considerations
We have provided a document that breaks down option C2b so people can have an understanding of how the overall $psf is broken down in uniformat section
We have also provided a similar breakdown for Waltham HS for comparison
11
August 12th, 2024
MSBA Policies
MSBA reimbursement Caps/limits
Ineligible costs
12
August 12th, 2024
MSBA Policies
The Following Spaces shall be categorically ineligible for Authority funding
13
August 12th, 2024
MSBA Policies
The Following Spaces are subject to size limits
* Grossing factor to be determined at end of schematic design
14
August 12th, 2024
Lexington Scope included in PDP estimates
15
August 22, 2024
Incentives
16
August 22, 2024
Preliminary 75-year LCCA Analysis - Systems' Costs
17
| Heating and Cooling Systems (HVAC) | |
Air Source Heat Pump (ASHP) | Ground Source Heat Pump (GSHP) | |
Estimated Systems Costs ($) | $65,000,000 | $81,000,000 |
Incentives ($) (MassSave) | $3,582,500 | $8,862,500 |
Estimated Payback (years) (MassSave) | 1.1 | 2.2 |
Incentives ($) (MassSave + IRA) | $3,582,500 | $26,952,500 |
Estimated Payback (years) (MassSave and IRA) | 1.1 | 0.75 |
Estimated Operational Carbon Reduction | 51-53% | |
August 12th, 2024
Benefits of Solar, Geothermal, and Battery Storage
18
August 12th, 2024
Project Cost
Project Cost $600M
MSBA Grant amount -$100M
Incentives and Rebates -$39M * $20M from MSBA above
Actual cost to town $461M
TOL Stabilization -$40M
Plus operational savings annually
19
August 12th, 2024
MSBA Policies
Thank you