1 of 20

Lexington High School Project

Other High School cost information for School Building Committee

August 12th, 2024

2 of 20

LHS Anticipated Project Timeline - Estimating

Town Meeting & Debt Exclusion Votes – Nov/Dec 2025

2025

2026

2024

2027

2028

2029

2030

Initial Design

Finish Design / Early Site

Construction

2031

Move-in

2029/2030

April 24

PDP

Conceptual Cost

Comparisons

Nov 24

PSR

Initial Estimate

Aug 25

SD

Estimate

March 26

DD

Estimate

August 26

CD 60%

Estimate

Jan 27

CD 90%

Estimate

May 27

GMP

Final Bids

PDP = Preliminary Design Program

PSR = Preferred Schematic Report

SD = Schematic Design Drawings

DD = Design Development Drawings

CD = Construction Documents

GMP = Guaranteed Maximum Price (Final Bid)

2

August 12th, 2024

3 of 20

Conceptual Pricing

The costs for the various PDP Options indicated below are intended to be an analysis of the relative costs between options and NOT a prediction of the actual final cost of any individual option. Major variables such as geotechnical, site grading, wetland determination, structural system and final MEP systems have yet to be designed and costs will vary significantly from the benchmark cost estimating included as part of this PDP cost analysis. The costs outlined in this report should not be represented as the FINAL construction budget and have a +/- 10% degree of accuracy.

PDP estimates utilize SF data from all recent high schools

3

August 12th, 2024

4 of 20

Conceptual Pricing

Table A - Massing Study Alternates

Construction Costs Only

Scope Option

Scope Description

GSF

Average between 2 cost estimators

Structured Parking

Total Construction $psf

Soft cost (20%)

Owner Contingency (5%)

Modulars

Total Project Cost

Option A.1

Base Repair/Code Upgrade - No architetcural

352,000

$ 222,000,000

 

$ 222,000,000

$ 44,400,000

$ 11,100,000

$ 23,100,000

$ 301,000,000

Option B.1

Add/Reno - Phased in place, retaing buildings G&J structure

440,816

$ 493,000,000

 

$ 493,000,000

$ 98,600,000

$ 24,650,000

$ 19,250,000

$ 636,000,000

Option B.2

Add/Reno - Addition on fields, retaing building G&J structure

440,816

$ 475,000,000

 

$ 475,000,000

$ 95,000,000

$ 23,750,000

 

$ 594,000,000

Option B.3

Add/Reno - 4 story. Includes structure parking. Phased in place retaining buildings C&D

440,816

$ 501,000,000

$ 22,016,250

$ 523,016,250

$ 104,603,250

$ 26,150,813

$ 11,550,000

$ 665,000,000

Option C.1a

New Construction - 3 Story. On fields, 1 phase

440,816

$ 487,000,000

 

$ 487,000,000

$ 97,400,000

$ 24,350,000

 

$ 609,000,000

Option C.1b

New Construction - 4 story. On fields, 1 phase

440,816

$ 479,000,000

 

$ 479,000,000

$ 95,800,000

$ 23,950,000

 

$ 599,000,000

Option C.1c

New Construction - 5 story. On fields, 1 phase

440,816

$ 478,000,000

 

$ 478,000,000

$ 95,600,000

$ 23,900,000

 

$ 598,000,000

Option C.1d

New Construction - Includes structure parking. 4 Story. On fields, 1 phase, reduced wetlands impact

440,817

$ 476,000,000

$ 22,016,250

$ 498,016,250

$ 99,603,250

$ 24,900,813

 

$ 623,000,000

Option C.2a

New Construction - 3 story. On fields, 1 phase

440,816

$ 485,000,000

 

$ 485,000,000

$ 97,000,000

$ 24,250,000

 

$ 606,000,000

Option C.2b

New Construction - 4story. On fields, 1 phase

440,816

$ 478,000,000

 

$ 478,000,000

$ 95,600,000

$ 23,900,000

 

$ 598,000,000

Option C.3a

New Construction - 3 story. On fields, 1 phase

440,816

$ 484,000,000

 

$ 484,000,000

$ 96,800,000

$ 24,200,000

 

$ 605,000,000

Option C.4a

New Construction - 3 story. On fields, 1 phase

440,816

$ 489,000,000

 

$ 489,000,000

$ 97,800,000

$ 24,450,000

 

$ 611,000,000

Option C.4b

New Construction - 4 story. On fields, 1 phase

440,816

$ 481,000,000

 

$ 481,000,000

$ 96,200,000

$ 24,050,000

 

$ 601,000,000

Option C.4c

New Construction - Includes structure parking. 4 story. On fields, 1 phase, reduced wetlands impact

440,816

$ 480,000,000

$ 22,016,250

$ 502,016,250

$ 100,403,250

$ 25,100,813

 

$ 628,000,000

Option C.5

New Construction - 4 story. On fields, 1 phase

440,816

$ 477,000,000

 

$ 477,000,000

$ 95,400,000

$ 23,850,000

 

$ 596,000,000

Option C.5b

New Construction - Includes structure parking. 4 story. On fields, 1 phase, reduced wetlands impact

440,816

$ 473,000,000

$ 22,016,250

$ 495,016,250

$ 99,003,250

$ 24,750,813

 

$ 619,000,000

Option C.6

New Construction - 4 story. On existing building footprint, multiple phases, reduced wetland and Article 97 impacts.

440,816

$ 481,000,000

 

$ 481,000,000

$ 96,200,000

$ 24,050,000

$ 11,550,000

$ 613,000,000

Option D.1

New Construction - 4 story. On fields, multiple phases

440,816

$ 486,000,000

 

$ 486,000,000

$ 97,200,000

$ 24,300,000

 

$ 608,000,000

New Construction options average (C.1a thru D.1)

440816

$ 481,000,000

 

 

$ 96,200,000

$ 24,050,000

 

$ 601,250,000

Average Construction cost of all new options $1,091psf Total project cost $1,364psf

4

August 12th, 2024

5 of 20

Comparison to other High Schools

  • Using the average $per square foot (psf) of all new construction options, Lexington shown at $1,364psf for project costs
  • Other project cost info found on MSBA’s April board meeting can be found here
  • When comparing you need to consider Size, Student enrollment, when the projects were bid, what the scope of each project includes, etc.

 

Arlington

Belmont

Revere

Waltham

Lexington

Size

408,590

445,100

422,600

414,854

440,816

Enrollment

1,755

2,215

2,450

1,830

2,395

Construction Cost

$ 235,286,827

$ 236,647,607

$ 412,006,854

$ 298,647,409

$ 481,000,000

Construction $psf

$ 557

$ 560

$ 975

$ 707

$ 1,091

Soft cost

$ 55,564,993

$ 58,511,582

$ 85,511,047

$ 75,919,978

$ 120,250,000

Soft cost % vs construction

24%

25%

21%

25%

25%

Project Cost

$ 290,851,820

$ 295,159,189

$ 497,517,901

$ 374,567,387

$ 601,250,000

Project $psf

$ 688

$ 698

$ 1,177

$ 886

$ 1,364

Bid Date

April 2019

April 2019

March 2025

End 2021

July 2028

5

August 12th, 2024

6 of 20

Escalation

Basis of the historical data can be found here

6

August 12th, 2024

7 of 20

Comparison to other High Schools

  • Escalation applied to each project to get to same bidding timeline as Lexington High School

 

Arlington

Belmont

Revere

Waltham

Lexington

Size

408,590

445,100

422,600

414,854

440,816

Enrollment

1,755

2,215

2,450

1,830

2,395

Construction Cost

$ 235,286,827

$ 236,647,607

$ 412,006,854

$ 298,647,409

$ 481,000,000

Construction $psf

$ 557

$ 560

$ 975

$ 707

$ 1,091

Soft cost

$ 55,564,993

$ 58,511,582

$ 85,511,047

$ 75,919,978

$ 120,250,000

Soft cost % vs construction

24%

25%

21%

25%

25%

Project Cost

$ 290,851,820

$ 295,159,189

$ 497,517,901

$ 374,567,387

$ 601,250,000

Project $psf

$ 688

$ 698

$ 1,177

$ 886

$ 1,364

Bid Date

April 2019

April 2019

March 2025

End 2021

July 2028

Project Cost Escalated to 7/2028

$ 425,734,352

$ 432,039,263

$ 542,294,512

$ 482,442,794

N/A

Escalated Project cost $psf

$ 1,042

$ 971

$ 1,283

$ 1,163

$ 1,364

7

August 12th, 2024

8 of 20

Lexington Scope included in PDP estimates

  • Using values from concept pricing for each scope item and dividing by the building square footage results in a Dollar per square foot cost ($psf) for each item.

  • Corrections updated 20240822

8

August 22, 2024

9 of 20

Comparison to other High Schools

  • Taking the escalated project cost adding $psf for scope items that are currently imagined for Lexington High School to level these other projects to provide more of an apples-to-apples comparison.

9

August 12th, 2024

10 of 20

Other cost considerations

10

August 12th, 2024

11 of 20

Other cost considerations

We have provided a document that breaks down option C2b so people can have an understanding of how the overall $psf is broken down in uniformat section

We have also provided a similar breakdown for Waltham HS for comparison

11

August 12th, 2024

12 of 20

MSBA Policies

MSBA reimbursement Caps/limits

  • Building cost funding limit up to $550psf of eligible building gross square footage
  • Sitework cost funding limit up to $55psf (roughly 10%) of eligible building gross square footage
  • Soft cost reimbursement eligible up to 20% of construction cost
  • Furniture, Fixtures and Equipment (FFE) up to $1,200 per student
  • Technology up to $1,200 per student
  • Owner’s Contingency Capped at .5%
  • Construction Contingency Capped at 1%
  • OPM/Designer Fees capped at $550psf of eligible building gross square footage

Ineligible costs

  • Any education program SF above MSBA guidelines (Space Summary)
  • Designer, OPM, and Commissioning agent fees associated with ineligible SF
  • In-Building Hazardous Material Abatement (Existing school)
  • Costs associated with Article 97 or MEPA filing
  • Legal costs
  • Costs associated with temporary modular classrooms
  • Anything outside the immediate property line
  • “Other” Project costs such as mailing and moving
  • Any non educational programs or anything over size limits per MSBA (See next slides)

12

August 12th, 2024

13 of 20

MSBA Policies

The Following Spaces shall be categorically ineligible for Authority funding

  • Swimming Pools – MSBA will only allow if separate project, separate funding, and ballot vote
  • Skating Rinks
  • Field Houses (Field houses have a track vs Gymnasium) MSBA will only allow if separate project, separate funding, and ballot vote
  • District Administrative Office Space – MSBA may allow but will not participate
  • Indoor Tennis Courts
  • Other spaces as determined ineligible by MSBA

13

August 12th, 2024

14 of 20

MSBA Policies

The Following Spaces are subject to size limits

  • Auditorium shall be no more than 13,300 nsf (based upon upper limit of 1,000 seats)
  • Gymnasiums – The district may choose to build a gymnasium and associated spaces, but in no event shall the gymnasium exceed 18,000 nsf. The MSBA will participate in a gymnasium of up to 12,000 nsf unless adjusted by the MSBA to increase teaching stations for enrollment and/or the educational plan.
  • Areas in excess of the MSBA guidelines will be at the sole expense of the district;
  • Community support must be demonstrated prior to MSBA approval of a district’s proposed project scope and budget
  • The MSBA will exclude from its grant the cost of the total gross square foot (“gsf”) above guidelines for these areas. Total NSF over MSBA limits x 1.5* grossing factor. This amount will not change over the term of the grant even if the bids come in at a lower amount.

* Grossing factor to be determined at end of schematic design

14

August 12th, 2024

15 of 20

  • Corrections updated 20240822

Lexington Scope included in PDP estimates

15

August 22, 2024

16 of 20

  • Corrections updated 20240822

Incentives

16

August 22, 2024

17 of 20

Preliminary 75-year LCCA Analysis - Systems' Costs

17

Heating and Cooling Systems (HVAC)

Air Source Heat Pump 

(ASHP)

Ground Source Heat Pump 

(GSHP)

Estimated Systems Costs ($)

$65,000,000

$81,000,000

Incentives ($) (MassSave)

$3,582,500

$8,862,500

Estimated Payback (years) (MassSave)

1.1

2.2

Incentives ($) (MassSave + IRA)

$3,582,500

$26,952,500

Estimated Payback (years) (MassSave and IRA)

1.1

0.75

Estimated Operational Carbon Reduction

51-53%

August 12th, 2024

18 of 20

Benefits of Solar, Geothermal, and Battery Storage

  • Lower upfront costs (including incentives)
  • Lower operational costs
  • Lower total life cycle cost than any HS in MA
  • Generates revenue from Solar and Storage
  • Highest and healthiest air quality standards
  • Better productivity of staff and students
  • Fewer sick days
  • Teacher retention
  • Produce its own power during outage
  • Insulates town budget from energy cost increases
  • Reduce greenhouse gas emissions by over 50mlbs in 30 years

18

August 12th, 2024

19 of 20

Project Cost

Project Cost $600M

MSBA Grant amount -$100M

Incentives and Rebates -$39M * $20M from MSBA above

Actual cost to town $461M

TOL Stabilization -$40M

Plus operational savings annually

19

August 12th, 2024

20 of 20

MSBA Policies

Thank you