SAP Project System (PS)
PS Master Data
Create and Analyze Project Verions
To Document the status of projects regularly and test unplanned changes using simulation versions. Before you update your operative project with data from the simulation version, you sue a projec version to document the original status of the project.
Create a Project Version
Use this Standard DB Profile
Choose EXECUTE
Project version created
Transfer Simulative Project to
Operative Project
Source is Simulation version
SIM##A
Verison -> Operative Data
E-98##
Transfer
YES to update the Operative Data
A log will appear displaying whether data was updated correctly.
Check Administrative data
OK. Press Enter
COPIED
INACTIVE
Open Operative Project E-98##
Copied from Sim##A to Operative Project
E-98##
Compare updated operative project E-98## with the data of project version 1##
Select “Version data” check box
Click Version data
Proj Version 1##
EXECUTE
Compare line by line
2 lines for each object
Updated E-98## vs
Project veriosn 1##