Energy
Conservation / Efficiency / �Resilience / Renewability
Water
Conservation Protection �Restoration
Waste
Reduce / Reuse
Recycle / Repurchase
Air
Pollution Reduction�Climate Resilience
OMD Strategic �Sustainability Plan (SSP)
Key Elements Reporting�
Key Strategic Focus�
2
OMD Strategic �Sustainability Plan (SSP)
3
Table 2: OMD Sustainability Roadmap | ||||||
Category Fed / State | Baseline | Data Collection | Target Reduction | Target Date | First Interim Target | Interim Target Achieved |
1. Energy |
|
|
|
|
|
|
1.1 Energy Intensity | EUI of 44 �(OMD FY2015) | Annual ongoing | 2.5% annually �25% | 2015-16�2025 | N/A�TBD | No TBD |
* |
| Annual ongoing | 50 EUI�(Avg of all state buildings > 5,000 SF) |
|
| Yes � |
Agency advocate/monitor = AGI - O&M, Energy Mgr, CFMO. | ||||||
Implementation Option: reduce energy use at sites with highest intensity, shown in Attachment 3. These sites include the Anderson Readiness Center, the Central Oregon Readiness Center, the Redmond Armory, Smith Hall and LaGrande Armory; consider other sites where cost-effective options exist. | ||||||
1.2 Renewable Energy | Current Year Consumption | Annual ongoing | 25% of total consumption �from FY15 | 2025 | 1.6% �FY 15-16 | TBD |
** |
|
|
| � |
| TBD |
Agency advocate/monitor = AGI – MILCON, O&M, DCSLOG/G-4 SMM/Fleet Mgr. | | | ||||
Implementation Option: continue to develop new renewable energy sources; at FY15 consumption levels, renewable generation levels of about 211,000 kWh is equal to 1% of total. | ||||||
OMD Strategic �Sustainability Plan (SSP)
4
Source: AEWRS, for OMD/ARNG �Federal tracking – DoD roll-up
Energy Intensity, Category 1.1
OMD Strategic �Sustainability Plan (SSP)
5
Energy Intensity, Category 1.1
Energy Use Index�FY17 & FY18
OMD Strategic �Sustainability Plan (SSP)
6
OMD Strategic �Sustainability Plan (SSP)
7
Water Use Intensity, Category 2.1
Source: AEWRS, for OMD/ARNG
OMD Strategic �Sustainability Plan (SSP)
8
Water Use Intensity, Category 2.1
FY17 & FY18
OMD Strategic �Sustainability Plan (SSP)
9
OMD Strategic �Sustainability Plan (SSP)
10
DoD Roll-up Snapshot across Services�for GHG Emissions
11
Source: DoD Strategic Sustainability Performance Plan – FY2016
Environmental Management
12
13
Sustainability Scorecard FY2016 | | Copy and Paste for Score | |||||||
State: Oregon |
| GREEN | AMBER | RED | |||||
|
|
|
|
|
|
| | | |
| DoD Goal Area | Baseline | Mandate | Target | Evaluation | Status | State�FY16 Score | Comments | Planned Actions |
Energy | Energy Intensity Reduction | FY15 | EO 13693�§3(a)(i) | Annually reduce 2.5% relative to FY15 total of 25% by 2025. | Green: Achieved ≥ 2.5% EUI reduction in FY16��Amber: Achieved 0-2.5% EUI reduction in FY16� �Red: Achieved EUI increase in FY16 | FY15-FY16: 20.33% | | Large increcease in FY16 SF from FY15 | ECIP - Statewide light project to be completed in FY17 |
Renewable Electricity Use | NA | EO 13693� [§3(c)] | Obtain specified shares of electric energy from renewable electric energy by FY 2025. ��.....≥10% by FY2016 & FY2017�.....≥15% by FY2018 & FY2019�.....≥20% by FY2020 & FY2021�.....≥25% by FY2022 & FY2023�.....≥30% by 2025 and thereafter | Green: Obtained ≥ 10% of electricity from electrical renewables in FY2016 and increased renewables use by ≥2.5% during FY15-FY16��Amber: Obtained < 10% of electricity from electrical renewables in FY2016 but achieved ≥2.5% increase use of renewables during FY15-FY16��Red: Obtained <10% of electricity from electrical renewables in FY2016 and <2.5% increase use of renewables during FY15-FY16 | FY16: 4.12%�FY15-FY16: 2.98% | | Addition PV projects under development | Additional funding received for OR Statewide PV project. | |
Clean Energy Use | NA | NDAA 2010 Section 2852 ��EO 13693 [§3(b)]�� 10 USC2911 (e)(A) | 25% of facility energy consumed need be produced or procured from electrical or thermal renewable sources by FY2025 | Green: On track to source 25% of electricity from electrical or thermal renewables by FY2025. (≈2.15% increase)��Red: Not on track to source 25% of electricity from electrical or thermal renewables by FY2025 (<2.15% increase) | FY16: 4.12 %�FY15-FY16: 2.98 % | | Additional PV and Biomass projects being completed |
| |
Reduction in Fleet Petroleum Use (non tactical) | FY15 | EO 13693�[§3(g)(ii)] | Reduce fleet-wide GHG emissions by 30% by FY2025. Reduction of 3% annually through 2025. ��Metric Changed to GHG/mile from MGAL or GGE . | Green: Achieved reduction in FP use of ≥ 3% between FY2015 and FY2016��Amber: Achieved reduction in FP use between 0-3% between FY2015 and FY2016��Red: Achieved ≥0% increase of FP use between FY2015 and FY2016 | FY15-FY16: 13.05 % | |
| Plan to be addressed | |
Water | Potable Water Intensity Reduction | FY07 | EO 13693�[§3(f)(i)] | 36% reduction by FY2025. Reduce water consumption intensity by 2% annually through FY2025 relative to FY07 baseline. | Green: Achieved reduction in WUI of ≥ 2% between FY2015 and FY2016 and on track to achieve 36% reduction by FY2025 (18% by FY16)��Amber:Achieved reduction in WUIof < 2% between FY2015 and FY2016 but on track to achieve 36% reduction by FY2025 (18% by FY16)��Red: Achieved reduction in WUI of < 2% between FY2015 and FY2016 and not on track to achieve 36% reduction by FY2025 (18% by FY16) | FY07-FY16: 55.48%�FY15-FY16: 28.24% | | | Continous monitoring |
Industrial, Landscaping, and Agricultural (ILA) Water Use Reduction | FY10 | EO 13693�[§3(f)(iii)] | 2% annually through 2025 relative to FY2010. | Green: Achieved reduction in ILA use of ≥ 2% between FY2015 and FY2016 ��Red: Achieved reduction in ILA use of < 2% between FY2015 and FY2016 | FY10-FY16: 98.6%�FY15-FY16: 23.5% | |
| Oregon EO-15-09 to reduce non-essential water use by 15% by 2020. | |
Solid Waste | Non-hazardous Solid Waste Diversion | NA | DoD Strategic Sustainability Performance Plan (FY2016)�Sub-Goal 5.2 ��EO 13693�[§3(j)(ii)] | 50% Annual Diversion Rate | Green: Achieved ≥50% diversion rate in FY2016��Red: Did not achieve ≥50% diversion rate by FY2016 | 22.5% | | SWARweb down, no access | Plan to be reviewed and updated |
Construction and Demolition Debris Diversion | NA | DoD Strategic Sustainability Performance Plan (FY2016)�Sub-Goal 5.3 ��EO 13693�[§3(j)(ii)] | 60% Annual Diversion Rate | Green: Achieved ≥60% diversion rate by FY2016 ��Red: Did not achieve ≥60% diversion rate by FY2016 | 22.5% | | SWARweb down, no access | Plan to be reviewed and updated | |
Planning and Auditing | Comprehensive Energy and Water Management Plans | NA | AR 420-1�Part Five�Chapter 22� | 100% updated on a 5-yr cycle (and annually reissued based on current operations) | Green: Yes, with revision date within past 5 years (both plans)��Amber: Yes, with revision date > 5 years ago OR no revision date listed (for either or both plans)��Red: No plan exists | Energy: Yes/No�Date of Last Revision: �Water: Yes/No�Date of Last Revision: | |
| Plan to be reviewed and updated |
Integrated Solid Waste Management Plan | NA | AR 420-1�Part Five�Chapter 23 | 100% updated on a 5-yr cycle | Green: Yes, with revision date within past 5 years (both plans)��Amber: Yes, with revision date > 5 years ago OR no revision date listed (for either or both plans)��Red: No plan exists | Yes/No�Date of Last Revision: | | No SWARweb access | Plan to be reviewed and updated | |
Energy Security Plan | NA | AR 420-1 �DEPPM 92-1 | DEPPM 92-1: energy vulnerability analyses and energy emergency preparedness plans must be established and reviewed annually. ��100% updated on a 5-yr cycle (and annually reissued based on current operations) | Green: Yes, with revision date within past 5 years ��Amber: Yes, with revision date > 5 years ago OR no revision date listed��Red: No plan exists | Yes/No�Date of Last Revision: | |
| Plan to be reviewed and updated | |
Comprehensive Energy and Water Audits | NA | AR 420-1�[§III(22-16]��EISA 2007�Pub. L. No. 110-140�§432, 3(A)��DoD Instruction 4170.11�Enclosure 3�Section 3�Paragraph A�Subparagraph 2 | ��AR 420-1: ≥10% of their facilities each year ��EISA 2007: Annually audit 25% of total federal square footage that represent 75% of total energy consumption. ��Dod Instuction 4170.11: Annually audit 25% of facilities | Green: Square footage audited in FY16 is ≥ 25% of total square footage. ��Red: Square footage audited in FY16 is < 25% of total square footage. | 0.00 | | Audits were not entered in AEWRS | Plan to be reviewed and updated | |
Sustainable Buildings | Net Zero Building Inventory | N/A | EO 13693�[§3(h)(iii)] | Agencies are to set percentage of the agency's existing buildings above 5,000 gross square feet intended to be energy, waste, or water net-zero buildings by fiscal year 2025 and implementing actions that will allow those buildings to meet that target; | TBD |
|
|
|
|
High Performance and Sustainable Buildings |
| Army Sustainable Design and Development Policy Update (Dec 2013)�[§5(b)(i)] | 15% of Existing Buildings Conform to the Guiding Principles on High Performance and Sustainable Buildings By FY25. | TBD |
|
|
|
| |
Net Zero Building Design | N/A | EO 13693�[§3(h)(i)] | Agencies are to set their own FY2025 goal for % of new buildings that meet Net Zero . All new buildings (over 5,000 gross square feet) that enter design in �FY2020 and after achieve net zero energy, and where possible net zero water and waste by FY2025 | TBD |
|
|
|
| |
Oregon Sustainability Scorecard - FY18
14
Sustainability Scorecard FY2016 | | Copy and Paste for Score | |||||||
State: Oregon |
| GREEN | AMBER | RED | |||||
|
|
|
|
|
|
| | | |
| DoD Goal Area | Baseline | Mandate | Target | Evaluation | Status | State�FY16 Score | Comments | Planned Actions |
Energy | Energy Intensity Reduction | FY15 | EO 13693�§3(a)(i) | Annually reduce 2.5% relative to FY15 total of 25% by 2025. | Green: Achieved ≥ 2.5% EUI reduction in FY16��Amber: Achieved 0-2.5% EUI reduction in FY16� �Red: Achieved EUI increase in FY16 | FY15-FY16: 20.33% | | Large increcease in FY16 SF from FY15 | ECIP - Statewide light project to be completed in FY17 |
Renewable Electricity Use | NA | EO 13693� [§3(c)] | Obtain specified shares of electric energy from renewable electric energy by FY 2025. ��.....≥10% by FY2016 & FY2017�.....≥15% by FY2018 & FY2019�.....≥20% by FY2020 & FY2021�.....≥25% by FY2022 & FY2023�.....≥30% by 2025 and thereafter | Green: Obtained ≥ 10% of electricity from electrical renewables in FY2016 and increased renewables use by ≥2.5% during FY15-FY16��Amber: Obtained < 10% of electricity from electrical renewables in FY2016 but achieved ≥2.5% increase use of renewables during FY15-FY16��Red: Obtained <10% of electricity from electrical renewables in FY2016 and <2.5% increase use of renewables during FY15-FY16 | FY16: 4.12%�FY15-FY16: 2.98% | | Addition PV projects under development | Additional funding received for OR Statewide PV project. | |
Clean Energy Use | NA | NDAA 2010 Section 2852 ��EO 13693 [§3(b)]�� 10 USC2911 (e)(A) | 25% of facility energy consumed need be produced or procured from electrical or thermal renewable sources by FY2025 | Green: On track to source 25% of electricity from electrical or thermal renewables by FY2025. (≈2.15% increase)��Red: Not on track to source 25% of electricity from electrical or thermal renewables by FY2025 (<2.15% increase) | FY16: 4.12 %�FY15-FY16: 2.98 % | | Additional PV and Biomass projects being completed |
| |
Reduction in Fleet Petroleum Use (non tactical) | FY15 | EO 13693�[§3(g)(ii)] | Reduce fleet-wide GHG emissions by 30% by FY2025. Reduction of 3% annually through 2025. ��Metric Changed to GHG/mile from MGAL or GGE . | Green: Achieved reduction in FP use of ≥ 3% between FY2015 and FY2016��Amber: Achieved reduction in FP use between 0-3% between FY2015 and FY2016��Red: Achieved ≥0% increase of FP use between FY2015 and FY2016 | FY15-FY16: 13.05 % | |
| Plan to be addressed | |
Water | Potable Water Intensity Reduction | FY07 | EO 13693�[§3(f)(i)] | 36% reduction by FY2025. Reduce water consumption intensity by 2% annually through FY2025 relative to FY07 baseline. | Green: Achieved reduction in WUI of ≥ 2% between FY2015 and FY2016 and on track to achieve 36% reduction by FY2025 (18% by FY16)��Amber:Achieved reduction in WUIof < 2% between FY2015 and FY2016 but on track to achieve 36% reduction by FY2025 (18% by FY16)��Red: Achieved reduction in WUI of < 2% between FY2015 and FY2016 and not on track to achieve 36% reduction by FY2025 (18% by FY16) | FY07-FY16: 55.48%�FY15-FY16: 28.24% | | | Continous monitoring |
Industrial, Landscaping, and Agricultural (ILA) Water Use Reduction | FY10 | EO 13693�[§3(f)(iii)] | 2% annually through 2025 relative to FY2010. | Green: Achieved reduction in ILA use of ≥ 2% between FY2015 and FY2016 ��Red: Achieved reduction in ILA use of < 2% between FY2015 and FY2016 | FY10-FY16: 98.6%�FY15-FY16: 23.5% | |
| Oregon EO-15-09 to reduce non-essential water use by 15% by 2020. | |
Solid Waste | Non-hazardous Solid Waste Diversion | NA | DoD Strategic Sustainability Performance Plan (FY2016)�Sub-Goal 5.2 ��EO 13693�[§3(j)(ii)] | 50% Annual Diversion Rate | Green: Achieved ≥50% diversion rate in FY2016��Red: Did not achieve ≥50% diversion rate by FY2016 | 22.5% | | SWARweb down, no access | Plan to be reviewed and updated |
Construction and Demolition Debris Diversion | NA | DoD Strategic Sustainability Performance Plan (FY2016)�Sub-Goal 5.3 ��EO 13693�[§3(j)(ii)] | 60% Annual Diversion Rate | Green: Achieved ≥60% diversion rate by FY2016 ��Red: Did not achieve ≥60% diversion rate by FY2016 | 22.5% | | SWARweb down, no access | Plan to be reviewed and updated | |
Planning and Auditing | Comprehensive Energy and Water Management Plans | NA | AR 420-1�Part Five�Chapter 22� | 100% updated on a 5-yr cycle (and annually reissued based on current operations) | Green: Yes, with revision date within past 5 years (both plans)��Amber: Yes, with revision date > 5 years ago OR no revision date listed (for either or both plans)��Red: No plan exists | Energy: Yes/No�Date of Last Revision: �Water: Yes/No�Date of Last Revision: | |
| Plan to be reviewed and updated |
Integrated Solid Waste Management Plan | NA | AR 420-1�Part Five�Chapter 23 | 100% updated on a 5-yr cycle | Green: Yes, with revision date within past 5 years (both plans)��Amber: Yes, with revision date > 5 years ago OR no revision date listed (for either or both plans)��Red: No plan exists | Yes/No�Date of Last Revision: | | No SWARweb access | Plan to be reviewed and updated | |
Energy Security Plan | NA | AR 420-1 �DEPPM 92-1 | DEPPM 92-1: energy vulnerability analyses and energy emergency preparedness plans must be established and reviewed annually. ��100% updated on a 5-yr cycle (and annually reissued based on current operations) | Green: Yes, with revision date within past 5 years ��Amber: Yes, with revision date > 5 years ago OR no revision date listed��Red: No plan exists | Yes/No�Date of Last Revision: | |
| Plan to be reviewed and updated | |
Comprehensive Energy and Water Audits | NA | AR 420-1�[§III(22-16]��EISA 2007�Pub. L. No. 110-140�§432, 3(A)��DoD Instruction 4170.11�Enclosure 3�Section 3�Paragraph A�Subparagraph 2 | ��AR 420-1: ≥10% of their facilities each year ��EISA 2007: Annually audit 25% of total federal square footage that represent 75% of total energy consumption. ��Dod Instuction 4170.11: Annually audit 25% of facilities | Green: Square footage audited in FY16 is ≥ 25% of total square footage. ��Red: Square footage audited in FY16 is < 25% of total square footage. | 0.00 | | Audits were not entered in AEWRS | Plan to be reviewed and updated | |
Sustainable Buildings | Net Zero Building Inventory | N/A | EO 13693�[§3(h)(iii)] | Agencies are to set percentage of the agency's existing buildings above 5,000 gross square feet intended to be energy, waste, or water net-zero buildings by fiscal year 2025 and implementing actions that will allow those buildings to meet that target; | TBD |
|
|
|
|
High Performance and Sustainable Buildings |
| Army Sustainable Design and Development Policy Update (Dec 2013)�[§5(b)(i)] | 15% of Existing Buildings Conform to the Guiding Principles on High Performance and Sustainable Buildings By FY25. | TBD |
|
|
|
| |
Net Zero Building Design | N/A | EO 13693�[§3(h)(i)] | Agencies are to set their own FY2025 goal for % of new buildings that meet Net Zero . All new buildings (over 5,000 gross square feet) that enter design in �FY2020 and after achieve net zero energy, and where possible net zero water and waste by FY2025 | TBD |
|
|
|
| |
Oregon Sustainability Scorecard - FY18