1 of 81

ETAP Power System Analysis Online Course For Electrical Engineer

(Real Industrial Projects Based Training Program)

Course Objective

This course is designed to provide hands-on practical exposure using ETAP for real-world electrical systems such as substations, industrial plants, and renewable energy integration.

🔰 Module 1: ETAP Basics & Interface (Beginner Level)

Topics:

  • Introduction to ETAP & Applications

  • Interface, Toolbar, Project Setup

  • Standards: IEC vs ANSI
  • Base Values & Per Unit System Practical:

  • Create first SLD
  • Add basic components Assignment:

  • Develop SLD of a simple 11 kV system

2 of 81

⚙️ Module 2: Equipment Modeling & SLD Development

Topics:

  • Transformers, Cables, Motors, Generators

  • Circuit Breakers, CT, PT

  • Busbars & Loads
  • Data input (real industrial parameters) Practical:
  • Model industrial plant SLD Assignment:
  • Build full plant electrical system

⚡ Module 3: Load Flow Analysis (Power Flow Study)

Topics:

  • Load Flow Methods (Newton-Raphson)

  • Voltage Profile Analysis

  • Loss Calculation
  • Power Factor Improvement Practical:
  • Load flow on industrial system Real Case:

  • Voltage drop problem in plant

3 of 81

Assignment:

  • Improve voltage profile

⚡ Module 4: Short Circuit Analysis

Topics:

  • Fault Types (3-phase, L-G, L-L)
  • IEC 60909 / ANSI standards
  • Fault Current Calculation
  • Breaker Rating Selection Practical:
  • Fault analysis at different buses Assignment:

  • Select correct breaker rating

🔒 Module 5: Protection & Relay Coordination

Topics:

  • Overcurrent Protection

  • Time Current Curves (TCC)

  • Relay Coordination

  • Differential Protection

4 of 81

Practical:

  • Relay setting in ETAP
  • Curve plotting Assignment:
  • Achieve selectivity

🔥 Module 6: Arc Flash Study & Safety

Topics:

  • Arc Flash Theory

  • IEEE 1584

  • Incident Energy Calculation
  • PPE Category Practical:
  • Arc flash simulation Assignment:

  • PPE calculation

5 of 81

📊 Module 7: Harmonic Analysis & Power Quality

Topics:

  • Harmonics sources

  • THD calculation

  • Filters design (Passive/Active)
  • IEEE 519 Practical:
  • Harmonic analysis in VFD system Assignment:
  • Design harmonic filter

🏗️ Module 8: Substation Design (33/11 kV Project)

Topics:

  • Substation layout

  • Equipment selection

  • Protection scheme
  • Earthing design Practical:
  • Complete substation modeling in ETAP

6 of 81

Assignment:

  • Design full 33/11 kV substation

🏭 Module 9: Industrial System Design Project

Topics:

  • Plant load calculation
  • Motor load analysis
  • Distribution system Practical:
  • Full industrial plant design Assignment:

  • Submit plant study report

Course Deliverables

  • ETAP Project Files
  • Calculation Sheets
  • Design Templates
  • Industrial Case Studies
  • Certification (Tips Engineer Zone)

7 of 81

🔰 Module 1: ETAP Basics & Interface (Detailed Learning)

1. Introduction to ETAP & Applications

  • What is ETAP?

ETAP is a powerful electrical engineering software used to:

    • Design electrical systems
    • Simulate real power networks
    • Analyze faults and performance

Where it is used?

    • Substations (33/11 kV, 132/33 kV)
    • Industrial plants (steel, cement, oil & gas)
    • Solar & renewable energy systems
    • Utility power systems

Why ETAP is important?

In real industry:

    • Before installing equipment → engineers simulate in ETAP
    • To avoid failures → load flow + fault study is done
    • For safety → arc flash study is mandatory

8 of 81

2. Interface, Toolbar & Project Setup

  • Step 1: Open ETAP
    • Click → New Project
    • Enter:
      • Project Name (e.g., “11kV_System”)
      • Frequency (50 Hz for India)
      • Standard → IEC

  • Step 2: Understand Interface Main Sections:
    • One-Line Diagram (SLD) Window → where you draw system
    • Toolbar → contains all electrical components
    • Project View → shows project files
    • Output Window → results & errors

9 of 81

  • Step 3: Toolbar Components (Very Important)

You will use these daily:

    • Bus
    • Transformer
    • Cable
    • Load
    • Circuit Breaker
    • Generator

These are same as real electrical equipment

3. Standards: IEC vs ANSI

IEC (India, Europe)

    • Units: kV, kA
    • Used in most Indian projects

ANSI (USA)

    • Different fault calculation methods

What to choose?

Always select IEC for:

    • India
    • Gulf countries
    • Most industrial projects

10 of 81

4. Base Values & Per Unit System

  • What is Base Value?
    • Reference value used in calculations Example:
    • Base Voltage = 11 kV
    • Base Power = 10 MVA

  • What is Per Unit System?

Formula:

Per Unit = Actual Value / Base Value

Why important?

    • Simplifies complex calculations
    • Used in:
      • Load Flow
      • Short Circuit

11 of 81

🔧 Practical: Create First SLD (Step-by-Step)

Objective:

Create a simple 11 kV system

  • Step 1: Add Bus
    • Select Bus from toolbar
    • Place it on screen
    • Rename → “11kV Bus”
    • Set voltage → 11 kV

  • Step 2: Add Source (Grid)
    • Add Utility / Grid
    • Connect to bus

  • Step 3: Add Transformer
    • Drag transformer
    • Set:
      • Rating → 10 MVA
      • Voltage → 33/11 kV

12 of 81

  • Step 4: Add Load
    • Add Static Load / Motor Load
    • Connect to 11 kV bus
    • Example:
      • Load = 5 MW

  • Step 5: Add Circuit Breaker
    • Place between:
      • Bus & Transformer
      • Bus & Load

  • Final SLD Structure:

Grid → CB → Transformer → CB → 11 kV Bus → Load

13 of 81

📂 Assignment (Very Important for Learning)

Task:

Create SLD of simple 11 kV system

Requirements:

  • 1 Incoming source
  • 1 Transformer (33/11 kV)
  • 1 Bus (11 kV)
  • 2 Loads (e.g., 2 MW + 3 MW)
  • Circuit breakers

14 of 81

⚙️ Module 2: Equipment Modeling & SLD Development (Detailed)

Objective

Learn how to model real electrical equipment in ETAP and create a complete industrial plant SLD (Single Line Diagram).

1. Equipment Modeling (Core of ETAP)

In real projects, wrong data = wrong results

So this module is most important for accuracy

A. Transformer Modeling

  • What you enter in ETAP:
    • Rating (MVA) → e.g., 10 MVA
    • Voltage → 33/11 kV
    • Impedance (%Z) → e.g., 8%
    • Vector Group → Dyn11
    • Cooling → ONAN / ONAF

Industry Tip:

    • % Impedance directly affects fault current
    • Always take data from:
      • Transformer nameplate
      • Vendor datasheet

15 of 81

B. Cable Modeling

  • Parameters:
    • Cable type (XLPE / PVC)
    • Size (e.g., 240 sq.mm)
    • Length (important for voltage drop)
    • Installation type (tray / buried / air)
    • Resistance & Reactance

Why important?

    • Affects:
      • Voltage drop
      • Losses
      • Short circuit current

  • C. Motor Modeling

  • Input Data:
    • Power → kW (e.g., 500 kW)
    • Voltage → 11 kV / 415 V
    • Power factor
    • Efficiency
    • Starting method (DOL / Star-Delta / VFD)

16 of 81

Industry Insight:

  • Motors are major load in industries
  • Starting current = 5–7 times rated current

D. Generator Modeling

  • Parameters:
    • Capacity (MVA)
    • Voltage level
    • Subtransient reactance (Xd")
    • Power factor

Use Case:

    • Backup DG system
    • Captive power plant

2. Switchgear & Measurement Devices

A. Circuit Breaker (CB)

  • Key Inputs:
    • Rated Voltage
    • Breaking Capacity (kA)

17 of 81

  • Type → VCB / SF6

Role:

  • Protect system during faults

B. Current Transformer (CT)

  • Input:
    • Ratio (e.g., 1000/1 A)
    • Accuracy class (5P10, 0.2)

Use:

    • Measurement + Protection

C. Potential Transformer (PT)

  • Input:
    • Voltage ratio (e.g., 33kV/110V)

Use:

    • Voltage measurement

3. Busbars & Load Modeling

Busbar

    • Voltage level (11 kV / 33 kV)

18 of 81

  • Short circuit rating

Acts as common connection point

Load Types in ETAP:

  • Static Load (kW, kVAR)
  • Motor Load
  • Lumped Load

  • Load Input Example:
    • Active Power = 5 MW
    • Power Factor = 0.85 lag

4. Data Input (Real Industrial Practice)

Where to get data?

    • Equipment datasheets
    • Site survey
    • Vendor drawings
    • Electrical BOQ

19 of 81

Golden Rule:

“Garbage In = Garbage Out” Always verify:

  • Voltage levels
  • Ratings
  • Units

🔧 Practical: Model Industrial Plant SLD

Objective:

Create a real plant electrical system

Example Plant:

  • 33 kV incoming supply
  • 10 MVA transformer
  • 11 kV distribution
  • Motors + loads

20 of 81

  • Step-by-Step SLD Creation

  • Step 1: Create 33 kV Source
    • Add Utility/Grid
    • Set:
      • Voltage = 33 kV
      • Short circuit level

  • Step 2: Add Circuit Breaker + CT/PT
    • Place CB between source & bus
    • Add CT/PT for protection

  • Step 3: Create 33 kV Bus
    • Name: BUS-33KV-01

  • Step 4: Add Transformer
    • 33/11 kV, 10 MVA
    • Connect to bus

21 of 81

  • Step 5: Create 11 kV Bus
    • Name: BUS-11KV-01

  • Step 6: Add Feeders Add:
    • Motor 1 → 500 kW
    • Motor 2 → 1 MW
    • Static Load → 2 MW

  • Step 7: Add Cables
    • Connect all loads using cables
    • Enter length & size

  • Final SLD Structure:

33 kV Grid → CB → Bus → Transformer → 11 kV Bus → Feeders → Loads

22 of 81

📂 Assignment: Build Full Plant Electrical System

Task:

Design complete industrial plant SLD

Requirements:

System must include:

  • 1 Incoming (33 kV)
  • 1 Transformer (33/11 kV)
  • 1 Main Bus (11 kV)
  • Minimum 3 Loads:
    • 1 Motor (500 kW)
    • 1 Motor (1 MW)
    • 1 Static Load (2 MW)
  • Circuit breakers for all feeders
  • Cables with proper data

23 of 81

Module 3: Load Flow Analysis (Power Flow Study)

Objective

Learn how to use ETAP to:

  • Analyze voltage at every bus
  • Calculate power flow & losses
  • Identify system problems
  • Improve overall system performance

  • 1. Load Flow Methods (Newton-Raphson)

What is Load Flow?

Load flow (power flow) calculates:

    • Voltage magnitude (kV)
    • Voltage angle (°)
    • Active power (kW)
    • Reactive power (kVAR)

For every bus in the system

24 of 81

Newton-Raphson Method (Most Important)

  • Why used?
    • High accuracy
    • Fast convergence
    • Used in real industrial software

Basic Concept:

It solves power equations:

P = V × I × cosθ Q = V × I × sinθ

Iterative method:

    • Guess initial voltage
    • Correct step-by-step
    • Reach accurate solution

In ETAP:

You don’t calculate manually — but you must:

    • Understand results
    • Validate system behavior

25 of 81

2. Voltage Profile Analysis

  • What is Voltage Profile?

Voltage at different buses:

    • Should be within ±5% of rated value Example:
    • 11 kV system → acceptable range:

o 10.45 kV to 11.55 kV

Problems:

    • Undervoltage → motors overheat
    • Overvoltage → insulation damage

In ETAP:

After load flow:

    • Check each bus color:
      • Normal

      • Problem

26 of 81

3. Loss Calculation

  • Types of Losses:
    • Cable losses (I²R)
    • Transformer losses
    • Reactive power losses

Formula:

Loss = I² × R

Why important?

    • Reduces efficiency
    • Increases electricity bill
    • Affects system design

ETAP Output:

    • Total system losses (kW)
    • Loss per branch

27 of 81

4. Power Factor Improvement

  • What is Power Factor?

PF = kW / kVA

Problem:

    • Low PF (<0.9):
      • High current
      • Higher losses
      • Penalty from utility

Solution:

    • Capacitor Bank
    • Synchronous condenser

Target:

    • Maintain PF ≥ 0.95

28 of 81

🔧 Practical: Load Flow on Industrial System

Objective:

Run load flow on your Module 2 plant model

  • Step-by-Step in ETAP:

  • Step 1: Open Your SLD
    • Ensure:
      • All components connected
      • No red errors

  • Step 2: Go to Load Flow Mode
    • Click → Load Flow Analysis

  • Step 3: Set Parameters
    • Method → Newton-Raphson
    • Tap changer → Auto (if transformer present)

29 of 81

  • Step 4: Run Simulation
    • Click → Run

  • Step 5: Analyze Results

Check:

    • Bus voltage
    • Line loading (%)
    • Transformer loading
    • Losses

Real Case: Voltage Drop Problem in Plant

Problem Scenario:

    • Plant load increases
    • Voltage at 11 kV bus drops to:

9.8 kV (Too low )

Causes:

    • Long cable length
    • Heavy motor load
    • Low power factor

30 of 81

Solutions (Industry Approach):

  • Solution 1: Increase Cable Size
    • Reduce resistance → less voltage drop

  • Solution 2: Add Capacitor Bank
    • Improve PF
    • Reduce reactive current

  • Solution 3: Adjust Transformer Tap
    • Increase output voltage

  • Solution 4: Load Distribution
    • Shift load to another feeder

Assignment: Improve Voltage Profile

Task:

Fix voltage issues in given plant system

31 of 81

Given:

  • 11 kV system
  • Voltage at bus = 10 kV (low)

You must:

  1. Run load flow
  2. Identify weak buses
  3. Apply solutions:
    • Capacitor
    • Tap change
    • Cable improvement

32 of 81

Module 4: Short Circuit Analysis (Fault Study)

Objective

Using ETAP, you will learn to:

  • Calculate fault current at different locations
  • Select correct circuit breaker ratings
  • Ensure system safety & protection

1. Fault Types (Very Important)

  • A. 3-Phase Fault (Symmetrical Fault)
    • All three phases shorted together

Characteristics:

    • Highest fault current
    • Most severe fault

Use:

    • Used for equipment rating selection

B. Line-to-Ground (L-G Fault)

    • One phase touches ground

33 of 81

Characteristics:

  • Most common fault (≈70%)
  • Lower current than 3-phase

C. Line-to-Line (L-L Fault)

  • Two phases short together

Characteristics:

  • Moderate fault current

D. Double Line-to-Ground (L-L-G)

  • Two phases + ground

Summary Table:

Fault Type

Severity

Occurrence

3-Phase

  • Highest

Rare

L-G

  • Medium

Most common

L-L

  • Medium

Less common

34 of 81

  • 2. Standards: IEC vs ANSI

IEC Standard (IEC 60909)

    • Used in India & most countries
    • Provides:
      • Initial fault current (Ik")
      • Peak current (Ip)
      • Breaking current

🇺🇸 ANSI Standard

    • Used in USA
    • Different calculation approach

What to use?

Always select IEC 60909 for:

    • India
    • Industrial projects

3. Fault Current Calculation

35 of 81

  • Basic Concept:

Fault current depends on:

    • System voltage
    • System impedance

Formula:

Fault Current (Isc) = Voltage / Impedance

Important Terms:

  • Ik" (Initial Symmetrical Current)
    • Used for breaker selection
  • Ip (Peak Current)
    • Used for mechanical strength

Example:

    • System Voltage = 11 kV
    • Impedance = low

Fault current becomes very high (danger )

36 of 81

🔌 4. Circuit Breaker Rating Selection

  • Breaker must handle:
    1. Breaking Capacity (kA)
    2. Making Capacity (Peak current)
    3. Thermal withstand

Rule:

Breaker rating must be: Breaker Capacity ≥ Fault Current

Example:

  • Fault current = 25 kA

Select breaker:

  • 31.5 kA (safe choice)

Wrong Selection:

  • Breaker explodes
  • System damage

37 of 81

🔧 Practical: Fault Analysis in ETAP

Objective:

Perform fault analysis on industrial system (Module 2 SLD)

  • Step-by-Step:

  • Step 1: Open SLD
    • Ensure:
      • All data correct
      • No errors

  • Step 2: Go to Short Circuit Mode
    • Click → Short Circuit Analysis

  • Step 3: Select Standard
    • Choose → IEC 60909

38 of 81

  • Step 4: Select Fault Type
    • 3-phase
    • L-G
    • L-L

  • Step 5: Run Simulation

  • Step 6: Analyze Results

Check:

    • Fault current at each bus
    • Breaker duty
    • Equipment rating

🏭 Practical Case: Fault Analysis at Different Buses Example System:

    • 33 kV Bus
    • 11 kV Bus

39 of 81

Observations:

  • At 33 kV Bus:
    • Lower fault current
  • At 11 kV Bus:
    • Higher fault current (closer to load)

Why?

    • Lower voltage side → lower impedance → higher current

Assignment (Important for Mastery)

Task:

Perform short circuit analysis of plant system

Requirements:

  1. Run:
    • 3-phase fault
    • L-G fault
  2. Record:
    • Fault current at each bus
    • Breaker ratings

40 of 81

🔒 Module 5: Protection & Relay Coordination

Objective

Using ETAP, you will learn:

  • How to protect electrical systems from faults
  • How to set relays properly
  • How to achieve selective tripping (only faulty section trips)

1. Overcurrent Protection (Most Common Protection)

What is Overcurrent Protection?

When current exceeds a set limit → relay sends signal → breaker trips

Types:

  • Instantaneous (High Fault)
    • Trips immediately (no delay)
  • Time-Delayed (Backup Protection)
    • Trips after some time delay

Real Example:

    • Motor feeder fault → only that feeder should trip

41 of 81

Relay Parameters:

  • Pickup Current (Ip)
  • Time Dial Setting (TDS)
  • Curve Type (Standard inverse, very inverse)

2. Time Current Curves (TCC)

  • What is TCC?

Graph between:

    • Current (X-axis)
    • Time (Y-axis)

Purpose:

    • To ensure proper coordination between relays

Example:

    • Feeder relay → fast trip
    • Main relay → slower trip

So feeder trips first

Key Rule:

42 of 81

Downstream relay must trip before upstream relay

3. Relay Coordination (Most Important Concept)

  • What is Coordination?

Ensuring:

    • Only faulty section trips
    • Rest system remains ON

Without Coordination:

    • Entire plant shutdown
    • Production loss

Coordination Chain Example:

Load → Feeder Relay → Bus Relay → Transformer Relay → Grid Relay

Fault at load → only feeder should trip

Coordination Margin:

    • Typically: 0.3 to 0.5 sec delay between relays

4. Differential Protection (Advanced Protection)

43 of 81

  • What is Differential Protection?

Compares:

Current IN = Current OUT

If mismatch:

Fault inside equipment → trip immediately

Used For:

    • Transformer protection
    • Generator protection

Advantage:

    • Fastest and most accurate protection

Practical: Relay Setting in ETAP

44 of 81

Objective:

Set relay parameters and check coordination

  • Step-by-Step:

  • Step 1: Open Your SLD
    • Ensure:

o Short circuit study completed (Module 4)

  • Step 2: Add Relay to Circuit Breaker
    • Select breaker → assign relay

  • Step 3: Enter Relay Settings Example:
    • Pickup current = 1.2 × full load current
    • Curve type = Standard inverse
    • Time dial = adjust for coordination

  • Step 4: Open TCC Curve
    • Go to → Star View / TCC
    • Select multiple relays

45 of 81

  • Step 5: Plot Curve

You will see:

    • Multiple curves (feeder, transformer, etc.)

  • Step 6: Adjust Settings

Ensure:

    • Curves do not overlap
    • Proper time gap maintained

Practical: Curve Plotting (Visualization)

Goal:

Ensure:

    • Feeder trips first
    • Transformer trips later

  • Correct Coordination:
    • Curves separated properly

Wrong Coordination:

    • Curves overlap → system failure risk

46 of 81

Assignment: Achieve Selectivity

Task:

Design relay coordination for plant system

Given System:

  • 33/11 kV transformer
  • 3 feeders

You must:

  1. Assign relays to:
    • Feeders
    • Transformer
  2. Set:
    • Pickup current
    • Time delay
  3. Plot TCC curves

Target:

Achieve selectivity:

  • Fault at feeder → only feeder trips

47 of 81

Module 6: Arc Flash Study & Safety

Objective

Using ETAP, you will learn to:

  • Analyze arc flash hazards
  • Calculate incident energy
  • Define safe working distance
  • Select proper PPE (Personal Protective Equipment)

1. Arc Flash Theory

  • What is Arc Flash?

An arc flash is a sudden electrical explosion caused by:

    • Short circuit
    • Equipment failure
    • Human error

Effects:

    • Extreme heat (up to 20,000°C )
    • Blast pressure
    • Serious injury / death

48 of 81

Where it happens?

  • Switchgear panels
  • MCC panels
  • Substations
  • Transformer terminals

Real Example:

Technician opens 11 kV panel → internal fault → arc flash → severe burn

  • 2. Standard: IEEE 1584

What it provides:

    • Formula for incident energy calculation
    • Arc flash boundary
    • PPE categories

Why important?

Mandatory for:

    • Industrial safety compliance
    • Electrical design projects

49 of 81

3. Incident Energy Calculation

  • What is Incident Energy?

Energy received by a person at a distance from arc

Unit:

    • cal/cm²

Concept:

Incident Energy Fault Current × Time × Distance

Key Factors:

    • Fault current (from short circuit study)
    • Clearing time (relay + breaker)
    • Working distance

Example:

    • Fault current = high
    • Trip time = slow

Incident energy becomes dangerously high

4. PPE Category (Safety Gear Selection)

50 of 81

PPE = Personal Protective Equipment

PPE Levels:

Category

Energy Range

Protection

0

< 1.2 cal/cm²

Basic clothing

1

1.2–4 cal/cm²

FR shirt

2

4–8 cal/cm²

FR suit

3

8–25 cal/cm²

Full suit

4

25–40 cal/cm²

Heavy suit

Rule:

Higher energy → higher protection

🔧 Practical: Arc Flash Simulation in ETAP

51 of 81

Objective:

Calculate arc flash hazard for plant system

  • Step-by-Step:

  • Step 1: Complete Short Circuit + Relay Study

Required input for arc flash

  • Step 2: Switch to Arc Flash Mode
    • Click → Arc Flash Analysis

  • Step 3: Enter Data
    • Working distance (e.g., 600 mm)
    • Enclosure type
    • Electrode configuration

  • Step 4: Run Simulation

52 of 81

  • Step 5: Analyze Output

Check:

    • Incident Energy (cal/cm²)
    • Arc Flash Boundary
    • PPE Category

Real Case: High Arc Flash Risk

Scenario:

    • 11 kV panel
    • Fault current = 25 kA
    • Trip time = 0.8 sec

Result:

    • Incident energy = very high
    • PPE Category 4 required

Solution:

    • Reduce relay operating time
    • Use faster breaker
    • Improve protection coordination

53 of 81

Assignment: PPE Calculation

Task:

Calculate PPE requirement for system

Given:

  • Incident Energy = 10 cal/cm²

You must:

  • Identify PPE category
  • Suggest safety measures

  • Answer:

PPE Category 3 required

54 of 81

📊 Module 7: Harmonic Analysis & Power Quality

Objective

Using ETAP, you will learn to:

  • Identify harmonic sources
  • Calculate THD (Total Harmonic Distortion)
  • Design harmonic filters
  • Improve overall power quality

1. Harmonics Sources

  • What are Harmonics?

Harmonics are distorted waveforms caused by non-linear loads.

Instead of pure sine wave → distorted wave

Common Sources in Industry:

    • VFD (Variable Frequency Drives)
    • UPS systems
    • Rectifiers / Converters
    • LED lighting
    • Computers / SMPS

55 of 81

Example:

  • Ideal waveform → smooth sine
  • With VFD → distorted waveform

Problems Caused:

  • Overheating of cables
  • Transformer losses increase
  • Equipment malfunction
  • Nuisance tripping

2. THD Calculation (Total Harmonic Distortion)

  • What is THD?

Measure of waveform distortion

Formula:

THD (%) = √(V2² + V3² + V4² + …) / V1 × 100

Where:

    • V1 = Fundamental voltage
    • V2, V3 = Harmonic components

56 of 81

Acceptable Limits:

According to IEEE 519:

  • Voltage THD < 5%
  • Current THD depends on system

If THD > limit:

System is unsafe

3. Filters Design (Very Important)

Types of Filters:

  • Passive Filter
    • Combination of:
      • Inductor (L)
      • Capacitor (C)

Tuned to specific harmonic frequency

  • Active Filter
    • Electronic device
    • Injects opposite harmonics

More advanced & costly

57 of 81

Selection:

Type Use Case

Passive Fixed load, low cost

Active Variable load, high accuracy

  • 4. Standard: IEEE 519

It defines:

    • Acceptable harmonic limits
    • Voltage distortion limits
    • Current distortion limits

Why important?

Ensures:

    • System reliability
    • Equipment safety
    • Utility compliance

Practical: Harmonic Analysis in VFD System

58 of 81

Objective:

Analyze harmonics in industrial plant

  • Step-by-Step in ETAP:

  • Step 1: Open SLD
    • Include:
      • VFD loads
      • Motors

  • Step 2: Enable Harmonic Analysis
    • Switch to → Harmonic Mode

  • Step 3: Define Harmonic Source
    • Select VFD
    • Enter:
      • Harmonic spectrum (5th, 7th, 11th…)

  • Step 4: Run Simulation

59 of 81

  • Step 5: Analyze Results

Check:

    • THD at bus
    • Voltage distortion
    • Current distortion

Real Case: Harmonic Problem in Plant

Scenario:

    • Multiple VFDs installed
    • THD = 12%

Issues:

    • Transformer overheating
    • Capacitor bank failure

Solution:

    • Install harmonic filter
    • Reduce THD < 5%

60 of 81

Assignment: Design Harmonic Filter

Task:

Design filter to reduce harmonics

Given:

  • THD = 10%
  • Required THD < 5%

You must:

  1. Identify harmonic order (5th, 7th)
  2. Select filter type:
    • Passive / Active
  3. Design parameters:
    • Inductance (L)
    • Capacitance (C)

Expected Output:

  • Reduced THD
  • Improved waveform

61 of 81

Module 8: Substation Design (33/11 kV Project)

Objective

Using ETAP, you will learn to:

  • Design a complete 33/11 kV substation
  • Select correct equipment ratings
  • Implement protection & earthing system
  • Perform full system validation (load flow + fault + protection)

1. Substation Layout (Concept + Practical)

  • What is Substation Layout?

Arrangement of electrical equipment in:

    • Outdoor yard (33 kV side)
    • Transformer area
    • Indoor control room

62 of 81

Layout Sections:

A. 33 kV Incoming Yard (Outdoor)

Includes:

  • Lightning Arrester (LA)
  • Isolator
  • CT/PT
  • Circuit Breaker
  • Busbar

Sequence:

Line → LA → Isolator → CT/PT → CB → Bus

B. Transformer Section

  • 33/11 kV Transformer
  • Oil pit + Fire wall
  • Marshalling box

C. 11 kV Indoor Switchgear

  • 11 kV Bus
  • VCB Panels
  • Feeders (to plant/load)

63 of 81

D. Control Room

  • Protection panels
  • Relay panels
  • Battery & charger
  • SCADA

Industry Tip:

Always plan for future expansion (20–30%)

  • 2. Equipment Selection (Very Important)

A. Transformer Selection

Example:

    • Load = 8 MW

Select:

    • 10 MVA transformer

Key Parameters:

    • Voltage → 33/11 kV
    • Impedance → 8–10%
    • Cooling → ONAN / ONAF

64 of 81

B. Circuit Breaker Selection

Based on:

  • Voltage level
  • Fault current

Example:

  • Fault level = 25 kA

Select:

  • 31.5 kA breaker

C. CT/PT Selection CT:

  • Ratio → e.g., 800/1 A
  • Accuracy → 5P10

PT:

  • Ratio → 33kV / 110V

D. Busbar Selection

  • Material → Aluminium / Copper
  • Current rating
  • Short circuit withstand

65 of 81

3. Protection Scheme Design

Objective:

Protect:

  • Transformer
  • Feeders
  • Busbar

Protection System:

  • Transformer Protection:
    • Differential Protection
    • REF Protection
    • Buchholz Relay

  • Feeder Protection:
    • Overcurrent Relay
    • Earth Fault Relay

66 of 81

  • Bus Protection:
    • Bus differential (optional)

Coordination:

    • Feeder trips first
    • Transformer backup later

4. Earthing Design (Safety Critical)

  • Purpose:
    • Protect human life
    • Ensure fault current path

Components:

    • Earth grid (mesh)
    • Earth rods
    • Equipment earthing
    • Neutral earthing

67 of 81

Design Target:

  • Earth resistance < 1 Ohm

Key Calculations:

  • Grid size
  • Step voltage
  • Touch voltage

🔧 Practical: Substation Modeling in ETAP

Objective:

Create full 33/11 kV system in ETAP

  • Step-by-Step:

  • Step 1: Create 33 kV Source
    • Utility/Grid
    • Set fault level

68 of 81

  • Step 2: Add 33 kV Bus
    • Name: BUS-33KV

  • Step 3: Add Incoming Equipment
    • CB + CT/PT + Isolator

  • Step 4: Add Transformer
    • 33/11 kV, 10 MVA

  • Step 5: Add 11 kV Bus
    • Name: BUS-11KV

  • Step 6: Add Feeders
    • 3–5 feeders
    • Motor + load

  • Step 7: Add Protection
    • Assign relays to breakers

69 of 81

  • Step 8: Run Studies
    • Load Flow
    • Short Circuit
    • Relay Coordination

📂 Assignment: Design Full 33/11 kV Substation

Task:

Design complete substation system

Requirements:

System Must Include:

    • 33 kV incoming
    • Transformer (10 MVA)
    • 11 kV bus
    • Minimum 3 feeders

70 of 81

  • Equipment Data:
    • Transformer rating
    • Breaker rating
    • CT/PT ratios

Protection:

    • Transformer protection
    • Feeder protection

Studies Required:

    • Load flow
    • Short circuit
    • Relay coordination

71 of 81

🏭 Module 9: Industrial System Design Project

Objective

Using ETAP, you will:

  • Design a complete industrial electrical system
  • Perform accurate load calculation
  • Analyze motor behavior
  • Build distribution network
  • Generate a professional plant study report

1. Plant Load Calculation (Step-by-Step)

  • Step 1: Identify All Loads Typical Industrial Loads:
    • Motors (major load)
    • Lighting
    • HVAC
    • Auxiliary systems

72 of 81

📊 Example Plant Data:

Equipment

Rating

Motor 1

500 kW

Motor 2

1000 kW

Motor 3

750 kW

Lighting

200 kW

Utility Load

300 kW

Total Connected Load = 2.75 MW

  • Step 2: Apply Demand Factor

Maximum Demand = Connected Load × Demand Factor

Assume Demand Factor = 0.8

Demand Load = 2.2 MW

  • Step 3: Add Future Margin

Add 25% extra:

Final Load = 2.2 × 1.25 = 2.75 MW

73 of 81

Final Design Load:

≈ 3 MW (Rounded for safety)

  • 2. Motor Load Analysis (Critical Part)

Why Important?

Motors = 70–80% plant load

🔧 Motor Data Required:

Parameter

Example

Power

500 kW

Voltage

11 kV

PF

0.85

Efficiency

95%

74 of 81

Starting Current:

Starting Current = 5 to 7 × Rated Current

Causes:

  • Voltage dip
  • Stress on system

Solutions:

  • Soft Starter
  • VFD
  • Proper cable sizing

3. Distribution System Design

📘 Power Flow Structure:

Grid → Transformer → 11 kV Bus → Feeders → Motors/Loads

75 of 81

Step-by-Step Design:

  • Step 1: Source
    • 33 kV Utility supply

  • Step 2: Transformer Selection

Load ≈ 3 MW

Select:

    • 5 MVA transformer (safe margin)

  • Step 3: Bus Design
    • 11 kV main bus
    • Rated for full load + fault

  • Step 4: Feeder Design

Example:

    • Feeder 1 → Motor Loads
    • Feeder 2 → Lighting
    • Feeder 3 → Utility

76 of 81

  • Step 5: Cable Sizing

Based on:

    • Current
    • Voltage drop
    • Fault level

  • Step 6: Protection
    • Circuit breakers
    • Relays (overcurrent + earth fault)

77 of 81

🔧 Practical: Full Industrial Plant Design in ETAP

Objective:

Create full plant system in ETAP

  • Step-by-Step:

  • Step 1: Create Grid
    • 33 kV source

  • Step 2: Add Transformer
    • 33/11 kV, 5 MVA

  • Step 3: Create 11 kV Bus

  • Step 4: Add Feeders
    • Motor feeder
    • Lighting feeder
    • Utility feeder

78 of 81

  • Step 5: Add Loads
    • Motors + static loads

  • Step 6: Add Protection
    • Breakers + relays

  • Step 7: Perform Studies
    • Load Flow
    • Short Circuit
    • Relay Coordination
    • Arc Flash

Real Industrial Case

Problem:

    • Voltage drop at motor bus
    • Transformer overload

Solution:

    • Increase transformer size
    • Add capacitor bank
    • Redistribute loads

79 of 81

📂 Assignment: Submit Plant Study Report

Task:

Design complete industrial electrical system

Requirements:

System Must Include:

  • 33 kV source
  • Transformer
  • 11 kV bus
  • Minimum 3 feeders
  • Motors + loads

Studies Required:

  • Load Flow
  • Short Circuit
  • Relay Coordination
  • Arc Flash

80 of 81

📤 Final Submission Format:

1. SLD Diagram

Complete plant diagram

2. Load Calculation Sheet

All loads + demand factor

3. Equipment Sizing

  • Transformer
  • Cable
  • Breaker

4. Study Results

  • Voltage profile
  • Fault current
  • Losses

5. Protection Scheme

  • Relay settings
  • Coordination

81 of 81

6. Safety Report

  • Arc flash
  • PPE