Progress Konstruksi�
Jakarta, 28 Januari 2026
PT PLN Nusantara Power
www.plnnusantarapower.co.id
Ringkasan Eksekutif
PLTS TERAPUNG TEMBESI
(35 MWac)
PLTA BATANG TORU
(510 MW)
PLTS KARANGKATES
(100 MWac)
ADD ON MUARA TAWAR
(650 MW)
PLTA SALU URO
(95 MW)
Konstruksi
www.plnnusantarapower.co.id
Milestone | Progress | Plan | Actual |
Land Acquisition | 100% | 31 Okt 2016 | 31 October 2016 |
Signing EPC Contract | 100% | 31 Jul 2016 | 31 July 2016 |
Financing Date | 100% | 31 Mar 2017 | 31 Aug. 2017 |
Switchyard & Transmission Line | 77% | 30 April 2025 | |
Back feeding Power for test | | 31 March 2026 | |
Special Facilities testing | | 30 April 2026 | |
1st Synchron. | | 30 April 2026 | |
Comm. date 1st | | 31 May 2026 | |
Comm. date 2nd | | 31 July 2026 | |
Comm. date 3rd | | 30 Sept. 2026 | |
Comm. date 4th | | 30 Nov. 2026 | |
Commissioned date for the Plant | | 31 Dec. 2026 | |
Required COD | | 31 Dec. 2026 | |
PLTA BATANG TORU (510 MW)
Item | Deskripsi |
Owner | PT North Sumatera Hydro Energy (Consortium PLNNR – SDIC –Genting Energy) |
Lokasi Proyek | Marancar Sipirok, Tapanuli Selatan, Provinsi Sumatera Utara (660,3 Ha) |
Kontraktor EPC | Sinohydro |
Kontrak PPA | 21 Desember 2015 |
Financial Close | 31 Agustus 2017 |
Nilai Kontrak | USD 1.668.000.000 |
Sumber Pendanaan | IPP |
Target COD | 31 Desember 2026 |
MILESTONE
DOKUMENTASI
SKEMA BISNIS
S- CURVE
Engineering
2,98%
/3,08%
Procurement
Construction
Deviasi
-2,28%
-0,21%
OVERALL PROGRESS 89,49%/91,77%
23,01%
/23,52%
63,50%
/64,95%
Per W4 Maret 2026
Switchyad
DAM
PLTA BATANG TORU (510 MW)
Project Milestne
2025
2024
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
2026
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
Milestone PPA
Required COD
Initial Unit Synchron
Backfeeding Power
Dam
Impounding
SF Completion
2025
2024
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
2026
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
Forecast COD
Initial Unit Synchron
Backfeeding Power
Dam
Impounding
SF Completion
2025
2024
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
2026
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
SF Completion
Backfeeding Power
Initial Unit Synchron
Forecast COD
Dam
Impounding
Milestone Sebelum Bencana
Milestone Setelah Bencana
Faktor Penentu Utama:
1
2
3
4
5
6
7
9
8
12
11
13
15
18
14
16
10
10
15
17
19
22
21
23
24
25
26
27
28
29
21/11/25
26/12/25
10/07/26
01/12/25
01/12/25
01/12/25
27/03/26
27/03/26
31/03/26
30/05/26
10/06/26
10/06/26
11/04/26
09/08/26
28/08/26
20/04/26
27/10/26
29/06/26
24/07/26
10/07/26
03/11/26
07/11/26
11/11/26
10/11/26
21/11/26
11/12/26
01/12/26
21/12/26
31/12/26
35
116
75
135
45
30
14
60
75
30
116
70
7
30
30
3
38
60
90
50
60
60
120
120
4
4
1
10
10
10
10
10
11/11/26
Plenary Meeting
Impounding Permit
Ready for Initial Impounding
First Impounding
Water Filling Test
Comm Unit 4
Comm Unit 3
Comm Unit 2
Comm Unit 1
Syncrhone Unit 4
Syncrhone Unit 3
Syncrhone Unit 2
Syncrhone Unit 1
COD
BackFeeding
Indentify Damage of DAM
Indentify Damage of Powerhouse
Indentify Damage of Tower and re-design tower schedule
Pengadaan Lahan
Soil Investigasi
Desain Tower
Desain Foundation
Procurement
Foundation Construction
Procurement and Transportation Hydrolic Hoist
Damage Repair Hydrolic Hoist
Damage Repair
Damage Repair
Procurement and Transportation EDG and HAC
Procurement and Transportation Dam Crest Gantry Crane and Trash Racks
Continue pre- Commissioning and Commissioning Unit
Completed Transmission Line
Final Chech by Pusertif and PTP Test
Ready for Interconnection
Interconnection Line GSW
Energized Line GSW
Energized Line OPGW
Interconnection Line OPGW
Commissioning Prior to RLB
Troubleshooting Function Test at Swichyard
Tower and Stringing Construction
PLTA BATANG TORU (510 MW)
RECOVERY PLAN
Faktor Utama
Progress Konstruksi
PLTA BATANG TORU (510 MW)
No | Item Works | Progress | Isu | Target Penyelesain |
1 | DAM dan Aksesorisnya | DAM & Intake Body (100%) DAM HM (98%) BOT/DT (95%) |
| 13 Agustus 2026 15 September 2026 |
2 | Headrace tunnel | Concrete lining 100 % | - | - |
3 | Penstock | Installation 100 % | - | - |
4 | Powerhouse | Pekerjaan Arsitektural sedang berjalan Sedang berjalan slope proteksi di sisi kanan, kiri serta upstream powerhouse (30%) Pemasangan EM work unit 1 dan 2 | Terdapat kerusakan pada EDG dan HVAC Terdapat kerusakan pada slope sisi kanan dan kiri powerhouse | 26 Juni 2026 |
5 | Transmission Line | Foundation/Erection/Stringing 89 Tower (100%) / 89 Tower (100%) / 91 span (98%) | Terdapat kerusakan 6 tower roboh, 6 tower mengalami kerusakan structural serta 19 tower memerlukan proteksi segera | 26 Oktober 2026 |
6 | Swicthyard | Civil 96% / EM 98% |
| 12 Mei 2026 |
6 | Akses Road | 67% permanent road / 72% temporary road/ 92% Bridge | Terdapat sedikitnya 7 titik lokasi yang terputus serta 1 jembatan hanyut | 22 Desember 2026 |
No | Item Works | Progress | Isu | Target Penyelesain | |||
| | Unit 1 | Unit 2 | Unit 3 | Unit 4 | | |
1 | Document and Design Review | 94% | 94% | 94% | 94% | | 31 September 2026 |
2 | RLB | 48,7% | 50,25% | 55% | 55,2% |
| 12 Oktober 2026 |
3 | Water filling and rolling water turbine | 11,57% | 11,7% | 16,17% | 20,1% | | 1 Juli 2026 |
4 | Sinkron | 19,6% | 19,6% | 22,75% | 26,6% |
| 8 November 2026 |
5 | Load Test | 0% | 0% | 0% | 0% | | |
6 | Load Rejection | 0% | 0% | 0% | 0% | | |
7 | Reability Run | 0% | 0% | 0% | 0% | | |
8 | Performance Test | 0% | 0% | 0% | 0% | | |
9 | Environmental Impact | 0% | 0% | 0% | 0% | | |
10 | SLO | 0% | 0% | 0% | 0% | | |
Progress Commisiioning
Transmission Line
8
PLTA BATANG TORU (510 MW)
Ruang Lingkup | Scope | Progress | Target |
Transmission Line
| Pre execution works | Pekerjaan LIDAR survey untuk validasi penentuan Lokasi tower baru telah selesai dan saat ini dalam tahap data processing |
|
Desain engineering | 16 Maret 2026 telah dilakukan pembahasan awal dengan PLN dan akan dilanjutkan pada 30 Maret 2026. | | |
Procurement | | | |
Construction | Pekerjaan proteksi pondasi sementara sedang dilakukan. |
| |
Test Com | |
|
Recovery
Access Road and Permanent Bridge
9
PLTA BATANG TORU (510 MW)
PLTA BATANG TORU (510 MW)
Activity | Due Date | Progress |
Switchyard 275 kV Complete | On Going (W4 Okt 2026) |
|
Impounding DAM | On Going (W4 Mei 2026) |
|
COD | On Going (W4 Des 2026) � |
|
Transmission Line | On Going (W4 Okt 2026) |
|
Sanksi administrasi KLH (SK 3559/2025) | ||
| Info |
|
| On Going (W4 Maret 2026) |
|
ISSUE TINDAK LANJUT
PLTA BATANG TORU (510 MW)
Activity | Due Date | Progress |
Sanksi administrasi KLH (SK 3559/2025) | ||
| On Going (W4 Maret 2026) | DLH Tapanuli Selatan telah melakukan verifikasi lapangan dengan progress positif di mana 21 lokasi spoil bank telah disetujui, revegetasi area quary sudah 90% (4,5Ha/5,04Ha), serta perlu dilakukan penyelesaian segera untuk penguatan slope. |
Gugatan Perdata Nomor 60/Pdt.Sus-LH/2026/PN Jkt. Sel | ||
| |
|
Sprindik Kemenhut Nomor: SP.DIK.05/PPNS/PPK/GKM.03/B/01/2026 tanggal 13 Januari 2026 | ||
| |
|
ISSUE TINDAK LANJUT
Milestone | Progress | Plan | Actual |
Effective Date PPA | 100% | 8 Juli 2024 | 8 Juli 2024 |
Signing EPC Contract | 100% | 10 Juli 2024 | 10 Juli 2024 |
Financing Date | 100% | 8 Okt. 2024 | 8 Okt. 2024 |
AMDAL | 93% | 26 Sept. 2025 | |
IPSDA | 79% | 25 Jan. 2025 | |
IPPKH | 44% | 12 Okt. 2025 | |
Site Handover | | Okt. 2025 | |
COD Stage 1 | | Feb. 2026 | |
COD Stage 2 | | Mar. 2026 | |
PLTS TERAPUNG TEMBESI (35 Mwac)
Item | Deskripsi |
Owner | PLN Batam |
Lokasi Proyek | Tembesi, Kec Sagulung, Kota Batam, Kepulauan Riau. |
Kontraktor EPC | PT Hypec International |
Kontrak PPA | 12 Februari 2024 |
Financial Close | 4 Oktober 2024 |
Nilai Kontrak | N/A |
Sumber Pendanaan | IPP |
Target COD | Maret 2026 |
MILESTONE
DOKUMENTASI
SKEMA BISNIS
S- CURVE
Construction
Test Comm
OVERALL PROGRESS 56,508%/100%
Procurement
52,197%
/80,958%
2,169%
/15,860%
0,000%
/0,761%
LAGGING -43,498%
Engineering
2,142%
/2,421%
Per W4 Maret 2026
Permit Status Forecast
PLTS TERAPUNG TEMBESI (35 Mwac)
| 2024 | 2025 | 2026 | |||||||||||||||||||||||||||
| 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | 11 | 12 | 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | 11 | 12 | 01 | 02 | 03 | 04 | 05 | 06 |
KKPR | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Multipurpose Waduk | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Sublease Waduk | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
AMDAL | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
IPSDA | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
PPKH Darat | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
PPKH Waduk | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
KKPR Terbit
04-09-2024
Multipurpose Waduk Terbit
10-12-2024
Sublease Waduk Signed
13-02-2025
AMDAL Terbit
IPSDA Terbit
PPKH Darat Terbit
PPKH Waduk Terbit
PLTS TERAPUNG TEMBESI (35 Mwac)
Milestone COD
2025
Jul
Agu
Sep
Okt
Nov
Des
2024
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
2026
Jul
Jan
Feb
Mar
Apr
Mei
Jun
COD Tahap-2
28 MW
PPA Milestone
COD Tahap-1
7 MW
PPA Efektif
Financing Date
Back Feeding
1st Synchron
EPC Contract
EPC Contract Signed
All Main Equipment Arrived at Site
Multipurpose Waduk
AMDAL
Agu
PPKH Darat
Sublease Waduk
IPSDA
PPKH Waduk
COD
Forecast COD*
Site Handover & Pullout Test
Permits Milestone
*) Telah dilakukan diskusi EOT dengan PLN Batam dan disepakati target COD adalah ±6,5 bulan sejak perizinan didapatkan pada Oktober 2025, yaitu Mei 2026
Sep
Okt
Nov
Des
Construction Progress
PLTS TERAPUNG TEMBESI (35 Mwac)
No | Item Material | Progress | Isu | Target Penyelesain |
1 | PV Modul | On Site (100%) | | |
2 | Floater | On Site (100%) | | |
3 | Inverter | On Site (100%) | | |
4 | MV Transformer | PO Signed | Keterbatasan storage | Juli 2026 |
5 | LV MV AC Cable (PV Plant) | Ready to Shipment | Keterbatasan storage | Juli 2026 |
6 | DC Cable | Ready to Shipment | Keterbatasan storage | Juni 2026 |
7 | FO Cable | Ready to Shipment | Keterbatasan storage | Juli 2026 |
8 | Grounding Cable | PO Signed | Keterbatasan storage | Juli 2026 |
9 | LV / MV Switchgear | PO Signed | Keterbatasan storage | Juli 2026 |
10 | Auxiliary Transformer | PO Signed | Keterbatasan storage | Juli 2026 |
No | Item Drawing | Total Drawing | Isu | Target Penyelesain |
1 | PV Plant | 60/60 | Cat-2 : 35 dokumen | COD (as built drawing) |
2 | Substation | 156/156 | Cat-2 : 83 dokumen | COD (as built drawing) |
3 | General Area | 16/16 | Cat-2 : 9 dokumen | COD (as built drawing) |
| Total | 232/232 | | |
Engineering Progress
Procurement Progress
No | Item Works | Progress | Isu | Target Penyelesain |
1 | Anchor Block Production | 861/861 (100%) | | selesai |
2 | Pull Out Test | Preparation | Belum terbitnya izin | Mei 2026 |
PLTS TERAPUNG TEMBESI (35 Mwac)
ISSUE TINDAK LANJUT
Activity | Due Date | Progress |
Perizinan
| �Info On Going (W4 April 2026) � �On Going (W4 April 2026) On Going (W4 April 2026) |
|
EPC | On Going (W4 April 2026) |
|
Kenaikan sewa | On Going (W4 April 2026) |
|
Milestone | Progress | Plan | Actual |
Effective Date PPA | 100% | 20 Januari 2025 | 20 Januari 2025 |
Signing EPC Contract | 100% | 11 April 2025 | 11 April 2025 |
KKPR | 100% | 9 Mei 2025 | 28 Juli 2025 |
LUA | 56% | 30 Juni 2025 | |
AMDAL | 50% | 30 September 2025 | 5 Januari 2026 |
IPPKH | 43% | 31 Oktober 2025 | |
IPSDA | 11,11% | 29 November 2025 | |
UKL UPL | 20% | 15 Desember 2025 | |
Start Construction | | November 2025 | |
Financing Date | | 20 Januari 2026 | |
Back Feeding | | Oktober 2026 | |
COD | | 20 Januari 2027 | |
PLTS TERAPUNG KARANGKATES (35 Mwac)
Item | Deskripsi |
Owner | PT Nusantara Guodian Karangkates Indonesia |
Lokasi Proyek | Desa Karangkates, Kecamatan Sumberpucung, Kabupaten Malang, Jawa Timur |
Kontraktor EPC | SDEPCI |
Kontrak PPA | 23 Desember 2024 |
Financial Close | N/A |
Nilai Kontrak | Rp 1,595 T (USD 111,166 jt) |
Sumber Pendanaan | Project Financing |
Target COD | 2027 |
MILESTONE
DOKUMENTASI
ISSUE TINDAK LANJUT
SKEMA BISNIS
S-Curve
Procurement
Construction
Test Comm
Engineering
1,25%
/1,33%
Deviasi
4,45%
17,61%
/20,58%
8,85%
/7,29%
OVERALL PROGRESS 30,68%/26,23%
Procurement
Construction
Per W4 Maret 2026
Material on site
PLTS TERAPUNG KARANGKATES (35 Mwac)
Project Milestone
2025
Des 2024
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
2026
Jan
Feb
Mar
Apr
Mei
Jun
Jul
Agu
Sep
Okt
Nov
Des
COD
15 April 2026
First batch PV Module, inverter On Site
Sign PPA
20 Januari 2025
PPA Effective
11 April 2025
Kontrak EPC Sign
5 Januari 2026
AMDAL Terbit
30 Juni 2026
Main Tranfo On Site
11 September 2026
Commissioning
28 Juli 2025
KKPR Terbit
15 Mei 2026
Start Site Wide Grounding Construstion
6 Juli 2026
Start Cable laying
Milestone
PLTS TERAPUNG KARANGKATES (35 Mwac)
PLTS TERAPUNG KARANGKATES (35 Mwac)
20
Procurement
No | Name Equipment | Seller/ Manufacturer | Status | "ETA“ (Est. Time of Arrival at site) |
1 | Anchor | PT Indo Fudong (termasuk Substation)�Batching Plant - Bimasena | Contract Signed | Produksi akan dimulai 20 Maret setelah persetujuan BTB |
2 | Mooring Line & Accessories | PT Sungrow Floating Indonesia | On Site (133 MWp) | Dec 2025 |
3 | Floater (with support) | PT Sungrow Floating Indonesia | Batch I (35 MW) : On Site�Batch II : FAT 30 MW done | Dec 2025 – 30 May 2026 |
4 | PV Module (sdepci nunggu kepastian pembayaran 15 maret) | Trina Solar Co. LTD | Start produksi W1 Maret FAT 10 Maret On shipment 80 MWp | 5 Batch 22 Mar-30 Apr |
5 | Grounding (PV Area) | Hypec | Contract Signed | May – Jul 2026 |
6 | DC Cable & Accessories (PV Module to Inverter) | N/A | Tender Process | May – Jul 2026 |
7 | String Inverter | Digital China System Integration Services Limited | Contract Signed�FAT W2 April | May 2026 |
8 | AC Cable & Accessories (Inverter to MV Trafo) | N/A | Tender Process | 15 Jun – Aug 2026 |
9 | Grounding Transformer Sets and Station Transformer | Baoding Tianwei Hengtong Electrical Co. LTD | FAT done | 30 May 2026 |
10 | Box Type Transformer | Jiangsu Daqian Box-Type Transformer Technology Co. LTD | Contract Signed | 15 Jun 2026 |
11 | AC Cable & Accessories (MV Trafo to Substation) | N/A | Tender Process | 15 Jun – Aug 2026 |
12 | AC/DC Power Supply System | Hangzhou Zhongheng Electric Co. Ltd | Contract Signed | 30 May 2026 |
13 | High and Low Voltage Switchgear | Chint Electric Co. Ltd | Tender Process | 30 Jun 2026 |
14 | Comprehensive Automation System | N/A | Tender Process | 30 Aug 2026 |
15 | DC Cable & Accessories (PV Module to Inverter) | N/A | Tender Process | May – Jul 2026 |
16 | AC Cable & Accessories (Inverter to MV Trafo) | N/A | Tender Process | 15 Jun – Aug 2026 |
17 | AC Cable & Accessories (MV Trafo to Substation) | N/A | Tender Process | Aug 2026 |
18 | Weather Station | N/A | Tender Process | TBD |
19 | Video Surveillance System | Hebei Jiuv Electronic Technology Co., Ltd. | Contract Signed | 30 Apr 2026 |
20 | Photovoltaic Area Intelligent Drone System | N/A | Tender Process | 30 Aug 2026 |
21 | Insulated Tubular Busbar | Jinan Forte Electrical Technology Co. Ltd | Contract Signed | 30 Aug 2026 |
22 | HVAC Equipment (Air Conditioning) | N/A | Tender Process | 30 Jul 2026 |
PLTS TERAPUNG KARANGKATES (35 Mwac)
Activity | Due Date | Progress |
AMDAL Dokumen Andal dan RKL RPL terkirim ke Sekretariat pada 31 Oktober 2025. | Info |
|
IPSDA
| On Going (W4 April 2026) |
|
IPPKH
| On Going (W4 Mei 2026) |
|
LUA
| On Going (W4 Mar 2026) |
|
Penataan KJA | Info | Telah selesai pada 29 Januari 2026 |
Financing Date | Info | Telah tercapai pada 20 Januari 2026 |
EPC Payment | On Going (W4 Jan 2026) |
|
ISSUE TINDAK LANJUT
Development
www.plnnusantarapower.co.id
Engineering
Procurement
Construction
Test Comm
OVERALL PROGRESS (PRA KONSTRUKSI)
PLTB TANAH LAUT (70 MW)
PRA KONSTRUKSI
MILESTONE
DOKUMENTASI
Progress
SKEMA BISNIS
Item | Deskripsi |
Pemenang Lelang | Konsorsium Total Eren – PT Adaro Power (30%) |
Jangka Waktu Perjanjian | 25 tahun sejak COD 30 MW |
Kontrak PPA | 23 Desember 2024 |
Financing Date | 12 bulan sejak Tanggal Efektif |
Nilai Kontrak | USD 118.690.000 |
Sumber Pendanaan | Project Financing |
Target COD | COD 30 MW : 14 bulan sejak Financing Date COD 40 MW : 18 bulan sejak Financing Date |
Milestone | Plan | Actual |
EPC Contract Signing | Juni 2026 | |
Efective Date PPA | Juli 2026 | |
Site AMDAL – IUPTLU Effective | November 2026 | |
LNTP | Desember 2026 | |
Jetty Permit | Januari 2027 | |
PPKH | Maret 2027 | |
Financial Close | Juni 2027 | |
COD 1 ( 30 MW) | Agustus 2028 | |
COD 2 (70 MW) | Desember 2028 | |
Deskripsi | Aktivitas |
Effective Date |
|
EPC |
|
AMDAL | Terdapat perubahan desain yang berpotensi berdampak pada perubahan AMDAL Eksisting. PLTB Tanah Laut sudah memiliki AMDAL Eksisting dengan lingkup AMDAL Pembangkit. Namun terdapat perubahan desain Lokasi yg awalnya didesain untuk WTG menjadi Transmission Line |
Engineering
Procurement
Construction
Test Comm
OVERALL PROGRESS (PRA KONSTRUKSI)
PLTS DEDIESELISASI TAHAP 1
PRA KONSTRUKSI
MILESTONE
Progress
Jawa dan Madura
2 Lokasi
Kalimantan
15 Lokasi
Sumatra
31 Lokasi
SKEMA BISNIS
Item | Deskripsi |
Owner | PT PLN NUSANTARA POWER |
Lokasi Proyek | 48 Lokasi (Kalimantan, Sumatera, Jawa & Madura) |
Kontraktor EPC | - |
No Kontrak | - |
Nilai Kontrak | - |
Sumber Pendanaan | - |
Target COD | 2029 (Estimasi) |
Milestone | Plan | Actual |
Penerbitan tarif Hybrid ESDM (T0) | T0 | |
Penandatanganan New Letter of Intent (LoI) | T0 + 2 Months | |
Persetujuan Anggaran (TVV-KI) (T1) | T0 + 4 Months | |
Signing PPA (T2) | T1+ 3 Months | |
COD | T2 + 42 Months | |
Deskripsi | Aktivitas |
KKPR | PTP Terbit 48 Lokasi dan KKPR Terbit 47 Lokasi |
Persetujuan Tarif |
|
SHA | Koordinasi dengan PLN NR dan LRC perihal Share Holder Agreement dan Sponsor Agreement “Masih dalam proses pembahasan, Finalisasi dilakukan setelah persetujuan tarif oleh ESDM” |
Engineering
Procurement
Construction
Test Comm
OVERALL PROGRESS (INISIASI)
PLTA Jawa Bali (Kuota) Tersebar
PLTA WADO (50 MW)
INISIASI
MILESTONE
SKEMA BISNIS
DOKUMENTASI
Item | Deskripsi |
Owner | Konsorsium PT PLN NR & PT Waskita Wado Energi |
Lokasi Proyek | DAS Cimanuk, Desa Cipasang, Kecamatan Cibugel,�Kabupaten Sumedang, Provinsi Jawa Barat |
Kontraktor EPC | - |
No Kontrak | - |
Nilai Kontrak | - |
Sumber Pendanaan | - |
Target COD | 2029 |
JVC IPP
PPA
35%
65%
PARTNER
Milestone | Plan | Actual |
Due Dilligence | Apr – Jun 2025 | |
SHA Sign | TW 4 2025 | |
PPA | TW 4 2025 | |
EPC Contractor | TW 4 2025 | |
Financial Close | TW 3 2026 | |
Start �Construction | TW 1 2026 | |
COD | Des 2029 | |
Progress
Deskripsi | Aktivitas |
LOI |
|
SHA | PLN NP bersama konsultan independen sedang dalam proses finalisasi SHA antara PLN NR dan WWE. |
PLTA SALU URO (95 MW)
Item | Deskripsi |
Owner | Tirta Energi Cemerlang (TEC) (Consortium PLNNR – Kencana Sulawesi Energi) |
Lokasi Proyek | Kecamatan Seko, Kabupaten Luwu Utara, Provinsi Sulawesi Selatan |
Kontraktor EPC | - |
Kontrak PPA | - |
Financial Close | - |
Nilai Kontrak | - |
Sumber Pendanaan | IPP |
Target COD | 60 bulan sejak PPA |
MILESTONE
PROGRESS
SKEMA BISNIS
Engineering
Procurement
Construction
Test Comm
OVERALL PROGRESS (PRA KONSTRUKSI)
PRA KONSTRUKSI
Milestone | Plan | Actual |
PPA Signed | T0 | |
Effective Date | T1 | |
Financing Date | T1 + 12 Months | |
Completion of Site Preparation | T1 +18 Months | |
Completion of Installation GITET 275 kV & Special Facilities | T1 + 56 Months | |
Completion of Power Plant Construction & Backfeeding | T1 + 57 Months | |
Plant COD | T1 + 60 Months | |
Deskripsi | Aktivitas |
SHA |
|
CSSA |
|
PPA dan Sponsor Agreement |
|
PLN NR Internal GRC Process | Menunggu finalisasi dokumen di SHA dan CSSA |
Korespondensi PLN-NP-Partner |
|
Activity | Due Date | Progress |
SHA | On Going (W4 Apr 2026) |
|
CSSA | On Going (W4 Apr 2026) |
|
PPA dan Sponsor Agreement | On Going (W4 Apr 2026) |
|
PLN NR Internal GRC Process | On Going (W4 Apr 2026) | Menunggu finalisasi dokumen di SHA dan CSSA |
Korespondensi PLN-NP-Partner | On Going (W4 Apr 2026) |
|
COD
www.plnnusantarapower.co.id
Add On Muara Tawar Blok 2,3 dan 4
Item | Deskripsi |
Owner | PT PLN Nusantara Power) |
Lokasi Proyek | Desa Segara Jaya Kecamatan Taruma Jaya Kabupaten Bekasi Provinsi Jawa Barat |
Kontraktor EPC | Konsorsium Doosan Enerbility - PT Hutama Karya (Persero) |
No Kontrak | 0125.PJ/DAN.02.01/DIR/2017 |
Kontrak | 29 Maret 2017 |
Nilai Kontrak | 64,2 Juta USD |
Sumber Pendanaan | 68% ECA dan 32% APLN |
Target COD | Blok 2 : 31 Desember 2022 Blok 3 : 28 Juni 2024 Blok 4 : 3 Desember 2024 |
MILESTONE
DOKUMENTASI
ISSUE TINDAK LANJUT
SLO
Procurement
Construction
Test Comm
Engineering
Deviasi
OVERALL PROGRESS (COD)
Procurement
Construction
COD
Milestone | Plan | Actual |
First piling | 21 Desember 2017 | 21 Desember 2017 |
Erection HRSG | 9 Januari 2019 | 19 Januari 2019 |
Foundation STG | 21 April 2021 | 19 Juni 2021 |
Power Receiving | 19 Februari 2023 | 14 Desember 2023 |
HRSG Hydro Test | 25 Juni 2022 | 25 Juni 2022 |
Steam Blowing out | 30 Juni 2023 | 9 Agustus 2024 |
Steam Admission | 23 Agustus 2023 | 1 Oktober 2024 |
Syncron | 28 Agustus 2023 | 14 Oktober |
COD | 31 Oktober 2023 | 3 Desember 2024 |
SLO Block #3 terbit tanggal 28 Juni 2024
SLO Block #4 terbit pada 3 Desember 2024
SLO Block #2 terbit tanggal 21 Desember 2022
Milestone Block #3
Milestone Block #4
19 Oktober 2023
Gen Test
29
19 Oktober 2023
Synchronization Test
11 Maret 2024
Optimization Test
15 Maret 2024
Load Change Test
16 Maret 2024
Capacity Test
25 Maret 2024
Disturbance Test
26 Maret 2024
Full Load Rejection Test
7 June 2024
Reliability Test
10 May 2024
Performance Test
ADD ON MUARA TAWAR 650 MW
29
28 Juni 2024
COD
14 December 2023
Power Receiving
Done
On Going
22 July 2024
Cond System Flushing
25 July 024
HRSG Function Test
26 July 2024
HRSG Blowdown With Sump Pump
05 August 2024
FW System Flushing
07 August 2024
SST 4.0 Turning Gear Operation
20 August 2024
Steam Blow
03 Desember
2024
COD
01 Oktober 2024
Steam Admission
14 Oktober 2024
Synchronization
06 August 2024
Water Quality Improvement
30-31 Oktober 2024
Performance Test
22-25 Oktober 2024
Reliability Test
PLTS IKN
Item | Deskripsi |
Owner | Nusantara Sembcorp Solar Energi |
Lokasi Proyek | Penajam, Kalimantan Timur |
Kontraktor EPC | 10 MW : PLN NPC, PLN NPS 40 MW : SEPEC - ZTPI |
Kontrak PPA | 29 Februari 2024 |
Financial Date | - |
Nilai Kontrak | 64,2 Juta USD |
Sumber Pendanaan | 70% Loan, 30% Equity |
Target COD | 10 MW : 29 Februari 2024 40 MW : 28 Desember 2024 |
MILESTONE
SKEMA BISNIS
ISSUE TINDAK LANJUT
SKEMA BISNIS
Engineering
Deviasi
OVERALL PROGRESS (COD)
Procurement
Construction
COD
Milestone | Plan | Actual |
Effective Date PPA | 29 Februari 2024 | 29 Februari 2024 |
Pekerjaan Site Development | 24 Mei 2024 | 24 Mei 2024 |
Start Konstruksi 10 MW | 31 Mei 2024 | 31 Mei 2024 |
Synchron 10 MW | 29 Februari 2024 | 29 Februari 2024 |
Start Land Clearing 40 MW | 16 Mei 2024 | 16 Mei 2024 |
Install Pile Foundation | 2 Agustus 2024 | 4 Agustus 2024 |
Install Mounting PV | 2 Agustus2024 | 6 September 2024 |
Install PV Module | 14 Oktober 2024 | 14 Oktober 2024 |
Install string Inverter | 23 Oktober 2024 | 23 Oktober 2024 |
COD | 28 Desember 2024 | 28 Desember 2024 |
Operasional 50 MW
Operasional 10 MW
05
LAYOUT PLTS
PLTS IKN 50 MW
31
1
7
2
3
4
5
6
RUPS PLN NP Penugasan PLTS IKN
10/03/23
29/02/24
PPA SIGN
14/04/24
Start Pekerjaan Konstruksi
PLTS 40 MW
PLTS IKN 10 MW Beroperasi
29/02/24
25/10/24
Start Commisioning BESS�PLTS 40 MW
09/02/23
Penugasan pembangunan infrastruktur ketenagalistrikan KIPP dari Menteri BUMN kepada PLN
31/05/23
Start Pekerjaan
Kontruksi 10 MW
12/04/23
Start Pekerjaan Land Clearing area PLTS
Start Pekerjaan Site Dev Switchyard
24/05/23
Start Commisioning PV Module �PLTS 40 MW
15/10/24
Reliability Run & Performance Test�PLTS 40 MW
13/11/24
28/12/24
COD�PLTS IKN 50 MW
03
TIMELINE PROYEK PLTS IKN – 50 MW
PLTS IKN
32
STS 1
STS 2
STS 3
STS 4
STS 5
STS 6
STS 7
STS 8
STS 9
STS 10
SERTIFIKAT LAIK OPERASI (SLO)
Relokasi Jakabaring - Batanghari
Item | Deskripsi |
Owner | PT PLN Nusantara Power) |
Lokasi Proyek | Desa Segara Jaya Kecamatan Taruma Jaya Kabupaten Bekasi Provinsi Jawa Barat |
Kontraktor EPC | Konsorsium Doosan Enerbility - PT Hutama Karya (Persero) |
No Kontrak | 0125.PJ/DAN.02.01/DIR/2017 |
Kontrak | 29 Maret 2017 |
Nilai Kontrak | 64,2 Juta USD |
Sumber Pendanaan | 68% ECA dan 32% APLN |
Target COD | Blok 2 : 31 Desember 2022 Blok 3 : 28 Juni 2024 Blok 4 : 3 Desember 2024 |
MILESTONE
DOKUMENTASI
ISSUE TINDAK LANJUT
SLO
Procurement
Construction
Test Comm
Engineering
Deviasi
OVERALL PROGRESS (COD)
Procurement
Construction
COD
Milestone | Plan | Actual |
Dismantling PLTG | 29 Juni 2022 | 10 Juni 2022 |
Transportasi PLTG | 10 September 2022 | 14 Oktober |
Inspection & perbaikan | 17 Juni 2022 | 7 Juli 2022 |
Revitalisasi | 2 November 2022 | 13 November 2022 |
Foundation ready | 26 Oktober 2022 | 26 Oktober 2022 |
Assembly & individual test | 24 Januari 2023 | 27 Januari 2023 |
WTP, WWTP & Fire protection Commissioning | 28 Februari 2023 | 24 Juli 2023 |
Trafo Commissioning | 7 Maret 203 | 25 Maret 2023 |
HSD fuel oil system & treatment commissioning | 7 Maret 2023 | 14 November 2023 |
Assembly GT 2 to PLTG 3 | 25 Juni 2023 | 17 Mei 2024 |
Sinkron | 30 Juni 2023 | 19 Juni 2024 |
UNIT 5
UNIT 1
UNIT 2
UNIT 3
UNIT 4
DOKUMENTASI
14 Juni – 29 Okt 22
Inspection & Perbaikan Non GT
16 Aug – 06 Sep 22
Transportasi GT Jakabaring Workshop OEM
11 Maret 2024
Repair GT Di Workshop OEM (Major Overhaul)
30 Desember 2022
Foundation Ready
08 Aug 2023
Trafo Commissioning
06 Maret 2024
Transportasi GT Workshop OEM Ke Haltim
26 Mei 2024 Assembly Engine
18 Juni 2024
Revitalisasi LCR & Tuning
Milestone PLN – ANTAM Haltim #5
35
RELOKASI PLTG (JAKABARING & BATANGHARI)
30 Juni 2024
COD
Milestone PLN – ANTAM Haltim #2
26 Apr 24
Mobilization Crews, tools and consumable
26 Jun 2024
Complete Inspection of Generator Rotor
24 Jun 2024
Remove GRR & rotor Insulation
30 Juli 2024
Cleaning Rotor Coils
28 Sep 2024
Manufacture Balance Weight Generator Rotor
02 Oct 24
Final Inspection Generator Rotor
26 Agus 2024
Rotor Generator Re- Insulations
31 Oct 24
Final Electrical Test
5 Juli 2024
Supply Rotor Insulation
PLTU Sumbagsel 1
Item | Deskripsi |
Owner | PT SSPewali |
Lokasi Proyek | Desa Kebon Agung, Kecamatan Semidang Aji, Kabupaten Ogan Komering Ulu (OKU), Provinsi Sumatera Selatan.r |
Kontraktor EPC | ZTPC |
Kontrak PPA | 17 Desember 2018 |
Financial Close | 18 Desember 2020 |
Nilai Kontrak | USD 443.900.807 |
Sumber Pendanaan | Project Financing |
Target COD | Unit 1 : 24 Desember 2024 Unit 2 :24 Maret 2025 |
MILESTONE
SKEMA BISNIS
ISSUE TINDAK LANJUT
SLO
Engineering
Deviasi
OVERALL PROGRESS (COD)
Procurement
Construction
COD
Milestone | Plan | Actual |
Effective Date PPA | | |
First Structure Concrete pouring | | |
Unit 1 Boiler foundation takeover | | |
Unit 1 Back feeding | | |
First Dematerialized Water | | |
First Synchronization of unit 1 | | |
Completion unit 1 RR | | |
Completion unit 2 RR | | |
SLO Unit 1 | | |
COD | | |
17 Desember 2018 | 17 Desember 2018 |
15 April 2023 | 14 April 2023 |
| |
18 Juli 2023 | 25 Juli 2023 |
| |
13 Juli 2024 | 7 Agustus 2024 |
5 Juli 2024 | 6 Juli 2024 |
18 Desember 2024 | 5 Oktober 2024 |
20 Desember 2024 | 7 November 2024 |
20 Maret 2025 | 15 Februari 2025 |
22 Maret 2025 | 17 Februari 2025 |
24 Maret 2025 | 24 Maret 2025 |
DOKUMENTASI
MILESTONE PROYEK
31 Maret 2017
Financing Date
30 Maret 2022
DAM Permit Issued by IDSC
14 April 2023
First Structure Concrete Pouring
25 Juni 2023
Unit 1# Boiler Foundation Take over
30 January 2024
Completion of Chimney Outer Cylinder
06 August 2024
Unit #1 Back Feeding Power
20 Desember 2024
Unit #1 Reliability Running Test
20 Maret 2024
Unit #2 Reliability Running Test
Done
On Going
PLTU MT Sumbagsel-1 (2 x150 MW)
37
24 December 2024
Commission Date Unit #1
18 Oktober 2024
Synchrone
24 Maret 2025
COD
Milestone | Plan | Actual |
Dismantling PLTG Maleo | | |
Transportasi PLTG Maleo | | |
Gas Turbine Foundation | | |
Konstruksi Daily tank & bundwall | | |
Konstruksi transfer pump, pre filtration, forwarding pump & ultra filtration | | |
Konstruksi oil pit, oil trap & profil tank | | |
kontruksi GSUT & UAT | | |
Instalasi PLTG Compartment | | |
instalasi HSD Fuel oil system | | |
Intalasi GSUT, UAT &NGR | | |
instalasi MV LV Switchgear & cabling system | | |
Instalasi Emergency diesel generator | | |
Commissioning | | |
Syncron | | |
SLO | | |
Engineering
4,337%
/5,000%
Construction
Commissioning
OVERALL PROGRESS 94,31%/100%
Procurement
Item | Deskripsi |
Owner | PT PLN NUSANTARA POWER |
Lokasi Proyek | PLTG MALEO #3 - PT ANTAM HALTIM – BULI, HALTIM TO PLTD KOLAKA, KOLAKA, SULAWESI TENGGARA |
Kontraktor EPC | PLN NPS |
No Kontrak | - |
Nilai Kontrak | - |
Sumber Pendanaan | - |
Target COD | Juli 2025 |
50,159%
/51,000%
MILESTONE
DOKUMENTASI
RELOKASI PLTG MALEO KE PLTD KOLAKA (25MW)
Dismantling
9,000%
/9,000%
26,316%
/30,000%
4,5%
5,000%
5 Juni 2024 | 5 Juni 2024 |
11 Agustus 2024 | 24 Agustus 2024 |
20 Juli 2024 | 27 Juli 2024 |
9 Oktober 2024 | 4 September 2024 |
15 November 2024 | 21 November 2024 |
8 Oktober 2024 | 23 Agustus 2024 |
8 Oktober 2024 | 8 Oktober 2024 |
8 September 2024 | 12 September 2024 |
18 Maret2025 | 31 Mei 2025 |
10 Mei 2025 | 31 Mei 2025 |
27 Mei 2025 | 28 Juni 2025 |
26 Mei 2025 | 7 mei 2025 |
1 Juli 2025 | |
4 Juli 2025 | |
5 Juli 2025 | |
S-Curve
W3 November 2025
94,31%
Per W3 November 2025
05 Juni 2024
Penugasan
20 Juni 2024
Site Preparation
31 Juli 2024
Gas Turbine Foundation
30 November 2025
COD
Done
28 September 2025
Sinkron
On Going
04 September 2024
Engine On Base
We Are Here.
27 Agustus 2024
Oil pit & oil trap Foundation
22 Oktober 2025
Commissioning System
08 September 2025
Installation Work
01 Juli 2025
Individual Test
PLTS SUBSTITUSI PS
DATA PROYEK | ||
Proyek | Pemasangan PLTS Substitusi PS | |
Deskripsi Proyek | Pemasangan PLTS Sebagai substitusi pemakaian sendiri (“PS”) di 3 Lokasi yaitu UP Gresik, UP Paiton dan UP Muara Tawar | |
Owner | PT PLN Nusantara Power | |
Kapasitas | | |
UP Gresik | 4.915,98 kWp | |
UP Paiton | 862,31 kWp | |
UP Muara Tawar | 202,4 kWp | |
Lokasi | | |
UP Gresik | Ex. Lapangan Golf, Ex Oil Tank Area | |
UP Paiton | Gedung Workshop, Outlet Tunnel, WTP Rooftop | |
UP Muara Tawar | Parkir Damkar, Gedung K3, Lapangan Futsal, Gedung Olahraga | |
Kontraktor | PT PLN Nusantara Power Construction | |
No SPPBJ | 5514/DAN.01.03/PLNNP010000/2024 | |
Tanggal SPPBJ | 29 April 2024 | |
No Kontrak | ZZB011.PJ/061/2024 | |
Tanggal Kontrak | 26 Juni 2024 | |
Progres 3 Lokasi | |||
Description | Plan | aktual | Devisiasi |
Engineering | 5.75% | 5.72% | -0.03% |
Procurement | 24.30% | 24.30% | 0,00% |
Construction | 4.98% | 4.94% | -0,04% |
Commissioning | 0,49% | 0,15% | -0.34% |
Total | 35,53% | 35,12% | -0,40% |
Deviasi disebabkan oleh hal-hal sbb.:
•Engineering : -0,03% (As Built Drawing)
•Procurement : 0,00 %
•Construction : -0,04% (Pekerjaan Walkway MTW)
Commissioning : - 0,34% (SLO, SOP, Individual &Funcion PLTS)
Terima Kasih