Unit 13 �Measurement Techniques �in Construction
Dr Adewale Abimbola, FHEA, GMICE.
Aim: �Types of quantity take-offs (2)
Use the Spon’s A&B price book to determine the approximate estimate of construction projects.
List the two types of quantity take-offs.
Explain detailed or accurate quantities.
Objectives: At the end of the lesson, the students should be able to:
Approximate Estimate - RECAP
Table 1. Tender price indices (AECOM Ltd, 2022)
Approximate Estimate - RECAP
Figure 1. Location factor (AECOM Ltd, 2022)
Key terminology:
Gross Internal Floor Area (GIFA or GIA): this is the area of a building measured to the internal face of the perimeter walls at each floor level.
Consult: https://www.designingbuildings.co.uk/wiki/Gross_internal_area_GIA for more information.
Worked Example 1
A new sixth form college
Floor area = 15,000 m2
Cost plan prepared with current TPI = 132
Start on site October 2023, TPI = 130 (pg, 52)
Location: East Midlands = 0.87 (adjustment = -13%)
From Building Prices per Square Metre = £2,075 per m2(pg, 86)
|
| Cost (£) |
College rate | £2,075/m2 X 15,000 m2 | 31,125,000 |
Adjust for inflation to start date | | -469,988 |
Adjust for location | Subtotal X 0.87 | 30,655,012
|
Allow for contingencies | Subtotal Say, 10% | 26,669,860 2,666,986 |
| Total order of cost estimate | 29,336,846 |
At this stage, the main contractor’s preliminaries, overheads and profit need not be added to the cost of building works as they are included within the Spon’s building prices per square metre rates, but you will need to add on professional fees such as QS, architects, Town and County Planning fees, etc., and other facilitating type costs such as demolition, external works, car parking, bringing services to site, etc.
Worked Example 2
Three storey semi-detached housing
Floor area = 102 m2
Cost plan prepared with current TPI = 132
Start on site March 2023, TPI = 126.7 (pg, 52)
Location: Wales = 0.86 (adjustment = -14%)
From Building Prices per Square Metre = £1,675 per m2 (pg, 87)
|
| Cost (£) |
College rate | £1,675/m2 X 102 m2 | 170,850 |
Adjust for inflation to start date | | -6868 |
Adjust for location | Subtotal X 0.86 | 163,982
|
Allow for contingencies | Subtotal Say, 10% | 141,025 14,102 |
| Total order of cost estimate | 155,127 |
At this stage, the main contractor’s preliminaries, overheads and profit need not be added to the cost of building works as they are included within the Spon’s building prices per square metre rates, but you will need to add on professional fees such as QS, architects, Town and County Planning fees, etc., and other facilitating type costs such as demolition, external works, car parking, bringing services to site, etc.
Self-assessment Task
a. Using the Building Prices per Square Metre method in Spon’s A&B price book 2022, produce the range (lower and upper) of the total order of cost estimate for a three-storey terrace house in Cardiff, Wales.
Additional information
Total gross internal floor area = 100 m2.
Cost plan prepared with current TPI = 132
Start on site May 2023.
b. Then, compare your estimates to the current price of such similar structure.
What could have caused the variations?.
[https://www.zoopla.co.uk/]
[https://www.rightmove.co.uk/property-for-sale.html]
Definition - Recap�
Take-off Quantities - Types
Accurate Quantities
Figure 1. Role of measurement in construction process (summary)
Accurate Quantities - Importance
Accurate Quantities - Importance
Bibliography
AECOM Ltd (2022) Spon’s Architects’ and Builders’ Price Book. 147th edn. Oxon: Taylor & Francis.
Pearson (2017) BTEC national construction student book. London: Pearson.