1 of 13

2024 NISD Bond

Update: Phases 2 & 3

May 18, 2026

2 of 13

Phase 2

  • High Point Chiller  (1)
  • Webb Elem. Chillers (2)
  • Admin AHU Replacements (5)
  • Administration Building 2nd Floor SPED Renovation/HVAC
  • Jr. High exterior door replacements
  • High Point Wastewater Treatment Plant
  • Bus Barn Driveway/Parking Lot

3 of 13

Phase 2

  • High Point Chiller  (1)
  • Webb Elem. Chillers (2)
  • Admin AHU Replacements (5)
  • Administration Building 2nd Floor SPED Renovation/HVAC
  • Jr. High exterior door replacements
  • High Point Wastewater Treatment Plant
  • Bus Barn Driveway/Parking Lot

4 of 13

Phase 2

  • High Point Chiller  (1)
  • Webb Elem. Chillers (2)
  • Admin AHU Replacements (5)
  • Administration Building 2nd Floor SPED Renovation/HVAC
  • Jr. High exterior door replacements
  • High Point Wastewater Treatment Plant
  • Bus Barn Driveway/Parking Lot

5 of 13

Phase 2

  • High Point Chiller  (1)
  • Webb Elem. Chillers (2)
  • Admin AHU Replacements (5)
  • Administration Building 2nd Floor SPED Renovation/HVAC
  • Jr. High exterior door replacements
  • High Point Wastewater Treatment Plant
  • Bus Barn Driveway/Parking Lot

6 of 13

Phase 2

  • High Point Chiller  (1)
  • Webb Elem. Chillers (2)
  • Admin AHU Replacements (5)
  • Administration Building 2nd Floor SPED Renovation/HVAC
  • Jr. High exterior door replacements
  • High Point Wastewater Treatment Plant
  • Bus Barn Driveway/Parking Lot

7 of 13

Phase 2

  • High Point Chiller  (1)
  • Webb Elem. Chillers (2)
  • Admin AHU Replacements (5)
  • Administration Building 2nd Floor SPED Renovation/HVAC
  • Jr. High exterior door replacements
  • High Point Wastewater Treatment Plant
  • Bus Barn Driveway/Parking Lot

8 of 13

Phase 2

  • High Point Chiller  (1)
  • Webb Elem. Chillers (2)
  • Admin AHU Replacements (5)
  • Administration Building 2nd Floor SPED Renovation/HVAC
  • Jr. High exterior door replacements
  • High Point Wastewater Treatment Plant
  • Bus Barn Driveway/Parking Lot

9 of 13

Phase 3

  • High School Outdoor Covered Bus Ramp (moved from Phase 2)
  • Webb replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, Webb Library drainage corrections and downspouts, and Webb secure vestibule, replace counter tops in classrooms and washing stations in hallways
  • High Point Elem replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, replace counter tops in classrooms and washing stations in hallways
  • Brule Elem. replace classroom and hallway lighting
  • Jr High replace classroom, locker rooms, and hallway lighting where needed, replace ceiling grids

10 of 13

Phase 3

  • High School Outdoor Covered Bus Ramp (moved from Phase 2)
  • Webb replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, Webb Library drainage corrections and downspouts, and Webb secure vestibule, replace counter tops in classrooms and washing stations in hallways
  • High Point Elem replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, replace counter tops in classrooms and washing stations in hallways
  • Brule Elem. replace classroom and hallway lighting
  • Jr High replace classroom, locker rooms, and hallway lighting where needed, replace ceiling grids

11 of 13

Phase 3

  • High School Outdoor Covered Bus Ramp (moved from Phase 2)
  • Webb replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, Webb Library drainage corrections and downspouts, and Webb secure vestibule, replace counter tops in classrooms and washing stations in hallways
  • High Point Elem replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, replace counter tops in classrooms and washing stations in hallways
  • Brule Elem. replace classroom and hallway lighting
  • Jr High replace classroom, locker rooms, and hallway lighting where needed, replace ceiling grids

12 of 13

Phase 3

  • High School Outdoor Covered Bus Ramp (moved from Phase 2)
  • Webb replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, Webb Library drainage corrections and downspouts, and Webb secure vestibule, replace counter tops in classrooms and washing stations in hallways
  • High Point Elem replace carpet in classroom and library, classroom and hallway lighting, ceiling grid, replace counter tops in classrooms and washing stations in hallways
  • Brule Elem. replace classroom and hallway lighting
  • Jr High replace classroom, locker rooms, and hallway lighting where needed, replace ceiling grids

13 of 13

Phase 3

  • High School replace ceiling grid in older classrooms and hallways and offices
  • NELC/Bizzell update front door secure vestibule
  • Brosig Loading Dock modifications
  • Brule replace quarry tile in hallway
  • Jr. High pour epoxy flooring in locker rooms/coaches offices
  • High School pour epoxy flooring in locker rooms/coaches offices
  • Parking lot expansion for Brosig
  • Jr. High Cafeteria floor replacement
  • Extend driveway for drop off at High Point Elem