Overview of Mineral Industry in Botswana
A Presentation to Stakeholders
Minerals & Energy
WWW.GOV.BW
BACKGROUND
Minerals & Energy
WWW.GOV.BW
�MINERAL POLICY AIMS�
Minerals & Energy
WWW.GOV.BW
4
MINERAL OPPORTUNITIES
Minerals & Energy
WWW.GOV.BW
The environment is conducive for variety of metals.
GEOLOGICAL LANDSCAPE (GEOTECHTONIC PROVINCES)
Minerals & Energy
WWW.GOV.BW
DIAMOND INDUSTRY IN BOTSWANA
State Owned Entities and Joint-Ventures to facilitate Industry Growth:-
Minerals & Energy
WWW.GOV.BW
TAX REGIME
Mineral Royalty Rates | 10% for precious stones; 5% for precious metals & 3% for other minerals, all calculated from the gross market value of mineral sales at the “Mine gate” |
Variable Income Tax Rate (VITR) | The higher of the standard company rate (22%) or the tax rate derived from the formula 70-1500/x, where x (%) = taxable income/gross in-come. (VITR is for non-diamonds minerals, diamond tax regime is negotiated and VITR can be applied if there is an agreement) |
Capital allowances | 100% depreciation of capital expenditures |
Dividend Allowable losses | Unlimited carry forward of tax losses |
Withholding Tax | 7.5% on distribution to residents and non-resident shareholders |
Import Duty | Zero-rated mining equipment and spares, otherwise duties are payable |
Value Added Tax | 14% applies to all but zero-rated items, which includes exports of minerals. VAT refunds are available upon re-export of items within six months of being brought into the country |
Taxation for Downstream procession (cutting, polishing and refining of minerals) | 15% tax rate (basic rate of 5% and an additional company tax rate of 10%) |
Development Order | 0 – 15% for downstream activities, mineral beneficiation projects such as refineries |
Minerals & Energy
WWW.GOV.BW
GEOLOGICAL LANDSCAPE & MINERAL OCCURRENCE
Minerals & Energy
WWW.GOV.BW
NATIONAL GEOPHYSICAL SURVEY COVERAGE
9
25 000 Gravity Stations
25% High Resolution (250 line spacing) Coverage of Radiometric – Eastern Botswana
1, 834, 545 line
kilometres of High-Resolution Aeromagnetic survey (90% coverage, 10% to be covered through TNDP project compled
106 760km2 Airborne Electromagnetics (20%(of Botswana Covered with Airborne Electromagnetic Surveys
Minerals & Energy
WWW.GOV.BW
GEOLOGICAL MAPPING COVERAGE
Planned under NDP 12 (2023 – 2029)
Northern Botswana Mapping Project - 2022
Eastern Botswana 1998
Central Kalahari Mapping Project - 2006
Minerals & Energy
WWW.GOV.BW
ON-GOING NATIONAL GEOCHEMICAL COVERAGE
Minerals & Energy
WWW.GOV.BW
MAJOR MINING PROJECTS AND MINING OPPORTUNITIES
There are various mining projects across the country. The following are operational mines;
Minerals & Energy
WWW.GOV.BW
MINERAL PROSPECTING IN BOTSWANA
13
Botswana offers enabling environment for mineral prospecting through;
Minerals & Energy
WWW.GOV.BW
FUTURE MINING PROJECTS FROM ACTIVE EXPLORATION
Minerals & Energy
WWW.GOV.BW
BOTSWANA RANKINGS BY FRASER INSTITUTE (2025)
Minerals & Energy
WWW.GOV.BW
POWER & ENERGY PROJECTS
OBJECTIVES | PROJECTS | COD | Q1 | Q2 | Q3 | Q4 | Comments |
1. Power Build Programme | IRP Projects | | |||||
Development of 500MW (2X250MW) Solar PV Power Plant in Maun | 2028 | | | | | Tender floating and closing on the 6 August 2025. The required land for the projects yet to be secured. | |
100MW Wind (Procurement of consultants for Resource Measurements) | 2029 | | | | | Procurement for wind resource measurement and site studies ongoing. ESIA studies commenced in June 2025 and procurement for the 100MW plant will then follow. | |
Development of 400MW (2X200MW) Solar PV Plant in Letlhakane | 2028 | | | | | Tender floating and closing on the 6 August 2025. The required land for the projects yet to be secured. | |
Development of 400MW (2X200MW) Solar PV Plant in Isang | 2028 | | | | | Land for the site has been secured with approval granted during the Land Board’s sitting of 26 June 2025. | |
Development of 600MW (2x300MW) Coal Fired Power Plants in Mmamabula | 2026 | | | | | Construction has commenced and order for major equipment has been placed. The project is on schedule and has created over 768 jobs currently, with only 16 expatriates on site. | |
Development of 2x50MW Solar Power Plant in Selebi Phikwe/ Mmadinare | 2026 | | | | | Construction for Phase 1 has been completed and commissioned. Construction for Phase 2 is in progress and is to be completed by March 2026. | |
Development of 100MW Solar Power Plant PV in Jwaneng | 2026 | | | | | The Project reached Financial Close on the 8 July 2025. Currently the project employs around 100 people. | |
36MW Small Grid Tied (12 villages) | 2027 | | | | | Two villages were commissioned in October 2023. Eight Villages are expected to reach FC by end of July 2025 FC. The capacities of the plants have been revised up to 20MW per site where evacuation capacities are available. The capacities will therefore increase from 36MW to 181MW. The two remaining sites of the total 1 sites have been awarded. | |
2. National Security of Petroleum Supply | Tshele Hills Oil Storage | | | | | | The Request for Proposal (RfP) has been approved and awaiting issuance. The project implementation strategy together with the funding model is yet to be determined. |
Minerals & Energy
WWW.GOV.BW
CONCLUSION
17
Governance/ Reporting Framework
Transparency
Impartiality
Materiality
Competency
Minerals & Energy
WWW.GOV.BW
THANK YOU
Minerals & Energy
WWW.GOV.BW