Modern Methods of Construction (MMC)�- Benefits for Mackay -
By Simon McCarthy
Director & Principal Structural / DfMA Engineer�MIEAust, CPEng, NER, APEC Engineer, IntPE(Aus), �Registered Professional Engineer – Qld, NSW, Vic, Tas.�Board Director - PrefabAUS
17 September, 2025
Simon McCarthy
Principal Structural / DfMA Engineer & Founding Director of Systemised Design Group.
25 years of experience as structural engineer in the Aust building industry.
Chartered Professional Engineer & Registered in Qld, NSW, Vic and Tas.
Developing the structural / DfMA design of multi-storey modular buildings since 2014.
Experience gained in DfMA from working on projects in UK, Europe, US, S.E. Asia and Australia
Specialise in design and documentation of buildings to utilise�modular, kit-of-parts construction techniques for low to mid-rise construction
Definitions
MMC = Modern Methods of Construction� Utilises offsite construction, manufacturing processes� Includes modular construction, panelised, 3D printing, etc.
Modular = standardised, repetitive shapes that can be � configured into regular patterns
Volumetric = 3D prefabricated, pre-finished frames � with internal fitout completed in factory
Flat pack = 2D prefabricated panels to be erected on site.� walls, floor cassettes, roof trusses, etc..
Kit-of-parts = IKEA approach to using standard, consistent and adaptable connections
DfMA = Design for Manufacturing and Assembly (design building to a known system)
Perceptions
Permanent modular construction utilizes prefabrication to construct in a controlled, manufacturing environment,
rather than taking all materials and trades to site in a traditional construction process.
Temporary�- portable (not shipping containers!)
- Non-complaint to Building Code of Australia,
- Cheap / low quality
- Uncomfortable and noisy
Permanent
- Compliant to Building Code of Australia
- High quality (built in a controlled factory environment),
- Planned, refined and adds value.
- Energy efficient
What is MMC?
Modern Methods of Construction (MMC)
utilises refined design practice (DfMA)
to prefabricate as many building elements
as possible.
MMC = Less trades attending site
What is MMC?
Comparison of trade traffic through bathroom door.�- 1250 movements for bathroom constructed on-site�- 250 movements for the same bathroom in the factory��The efficiency in using a fixed sequence in manufacture �- reduced construction traffic by 80%.�- reduced construction time by 30%�- reduced construction waste by 50%
MMC uses BIM / Digital Documentation
BIM = Building Information Modelling�
3D model – visual representation of coordinated disciplines� - automatic bill of quantities
4D model – animated representation of construction sequence
5D model – financial representation of construction cost
MMC uses Steel, Timber and Concrete
MMC Building Types
Residential
Single level houses�Granny flats / teenager retreats
Worker accommodation
Student accommodation (CQU above)
Multi-family / apartments�Hotels / resorts
Worker accommodation
Education
School classrooms
University classrooms
MMC Building Types
Multi-level carparks�Multi-level storage facilities�- concurrent construction�- 6 storeys complete in 6 months
Vertical extensions�6 storeys added in CLT� or�3 storeys if conventional concrete
Hospitals & healthcare facilities�Mental Health Retreats�Standardised layouts and�high-end proprietary ligatures
Productivity – Australia Wide
Productivity in construction has reduced 0.2% in the last 30 years!
Productivity in other industries have increased by 33% over the same period.
�We are still doing the same building techniques as the mid 1980’s.
Housing Shortage – Mackay
https://www.theurbandeveloper.com/articles/undersupply-drives-regional-qld-over-50s-land-lease-plans
Housing Shortage – Mackay
The rental vacancy rate in Mackay has been below 1% in early 2025�and less than the balanced market rate of 2-3%.
Mackay’s local economy is booming, thanks in large part to:
Status quo approach to construction is not keeping up.
Housing Shortage – Mackay
2023 to 2046�- Population to increase 32,454 (25.6% projected growth)�- Need approval for at least 16,000 new housing projects over 20 years.�- Need at least 800 new houses per year from now on.
2013 to 2023�- Population increased 8029 new residents (6.8% growth)�- 3984 new housing projects were approved over the same period�- 306 new housing projects in 2024 alone.
Reference: Mackay Regional Council – Economic Profile 2024
Status quo approach to construction is not going to keep up.
Construction Cost Comparison
Locality Cost Index�Used to compare the same project from one site to another.�Adjusts costs for increase in transportation of labour & materials to site, plus allowances.
Reference: Locality Index – September 2023, GRC Quantity Surveyors
Locality | 2024 Locality Index |
Brisbane | 100 |
Brisbane CBD | 103 |
Mackay | 116 |
Sunshine Coast | 104 |
Gold Coast | 103 |
Bundaberg | 107 |
Rockhampton | 117 |
Townsville | 115 |
Cairns | 109 |
Why Consider Modular Construction?
Mackay is falling behind in construction (not building enough each year)
�Mackay has high construction cost (compared to other areas of Queensland)
Mackay has limited building trades & building techniques (always build the same way)
Mackay has a limited supply chain
Mackay needs extra construction worker accommodation for large projects
Mackay has seasonal interference (rain / cyclone season)
Why Consider Modular Construction?
Queensland Government have been using MMC / Offsite Construction for:
Why Consider Modular Construction?
September is�Queensland Manufacturing Month!
Why Consider Modular Construction?
Queensland have modular building manufacturers with capability and capacity
to support projects in Mackay.
Supporting Qld modular manufacturers will provide win-win effects:�- Mackay could supply more housing, in a shorter period of time than expected.�- Modular suppliers will have increased pipeline to train staff and build capability� in the lead-up to Brisbane 2032.
Why Consider Modular Construction?
Consider utilizing construction resources from South-East Queensland
Why Consider Modular Construction?
Saving time creates other benefits.��Using MMC will enable 3 to 4 projects to be completed every 2 years, compared to one using traditional construction!�
Reflecting on the projected need to develop 800 homes per year for the next 20 years,�MMC / offsite construction could allow for�1600 to 2400 homes per year using modular,�compared to �800 homes per year with traditional construction
By utilizing MMC resources in SE Queensland.
Why Consider Modular Construction?
Saving cost creates other benefits.��Saving 10% on 10 apartments = 1 free, or 11.�Saving 10% on 100 = 10 extra families off streets
Reflecting on the projected need to develop 800 homes per year for the next 20 years,�Saving 10% on 800 apartments equates to: �A) 10% reduction in housing cost (attractive!) or,�B) reduced budget (approx. 730 homes / year or, C) 880 apartments for the same budget.�
Why Consider Modular Construction?
Early return on investment
Consider cost plan
E.g. 5 storey hotel (100 rooms)�Feasibility comparison indicates that adopting modular construction will allow hotel to open 18 months earlier than traditional construction.
Repetition in 5 module types allows for price of modular construction to also match const of construction.
�100 rooms x $170 per night.�70% occupancy (average)�= $6.5M in revenue 18 months early.�
Get ahead of Brisbane 2032!
Regional Qld has a few years left to take advantage of using building manufacturers
in South-East Queensland, before their local wave in population growth will take over.
South-East Queensland currently have a lag while infrastructure is being developed in preparation for the surge in population as the Olympic Games approaches.
Limited building capability will escalate construction costs – people will look elsewhere that is more affordable.
The largest demand in Mackay is�workforce accommodation.
The time to act is NOW!
Get ahead of Brisbane 2032!
Get ahead of Brisbane 2032!
The Queensland Tourism Industry Council (QTIC) Strategic Plan 2025-2028, �issued Mon 8 Sept 2025, �highlights the urgent need for tourism infrastructure investment, �which is particularly relevant for popular regions such as the Whitsundays.
�SEQ currently has just 46,000 hotels rooms �- less than half of Los Angeles (120,000) and Paris (133,000). ��Even with committed developments, capacity is expected to grow �to only 51,000 rooms by 2030, leaving Qld significantly short �of what is needed to meet demand as Brisbane 2032 approaches.
Reference: www.qtic.com.au� www.wildmodular.com.au/hook-island
How to get started in using MMC?
This well-recognised graph known as the MacLeamy Curve �can also be used to show the ability to influence the type of construction
How to get started in using MMC?
Buildings that use MMC need to be designed to the specific type of MMC.
Trying to adapt an existing building design for modular is often too hard and won’t work.
How to get started in using MMC?
Easier access to construction loan funding
How to get started in using MMC?
QLD Dept of Housing development of guidelines on low to mid-rise housing using MMC
How to get started in using MMC?
Q-CHIP – Queensland – Community Housing Investment Pipeline
Just this week, the Queensland Gov't announced �an "always-open" procurement program called �Queensland Community Housing Investment Pipeline (Q-CHIP)
- funding is readily available
- no time limit grants
Using this process with MMC will allow more community housing in a shorter timeframe.
How to get started in using MMC?
Use design teams with DfMA experience (One of the most popular questions I am asked!)
Do design consultants have case studies?�- Use an Architect to obtain better value than a building designer / draftsperson�- Beware of the “expert” who has done one modular project.
Do modular manufacturers have prototypes?
Conduct feasibility study to confirm MMC vs traditional construction
- Include comparison of overall costs� MMC may be more expensive to build, � but the early return on revenue may be better
How to get started in using MMC?
Reach out to attendees here today:
Architect:
Dennis Butler – Vabasis Architecture, Spring Hill
Modular Manufacturers:
Karen Gear – Sigma Build, Brisbane
Demi Pressler-McHugh – McHugh Steel, Bundaberg
Tahi Merrilees – Wild Modular
PrefabAUS Members:
www.prefabaus.org.au
How to get started in using MMC?
Epic Builds: The 90 Day Challenge �Channel 9 – Oct. 2025�Hosted by Adam Spencer.
The program follows construction crews as they complete innovative modular and prefab building projects, �such as schools and homes, �within an extreme 90-day deadline.
Thank you!
Robert Cocco
Nic Willis
Good Design = Good Value = Investment
Your DfMA Consultant of Choice
We understand complexity, but believe in simplicity
Simon McCarthy�Principal Structural / DfMA Engineer�smccarthy@systemiseddesign.com�https://www.linkedin.com/in/simon-mccarthy-b605ab19/
Structural Engineering | DfMA Studies | Modular (Volumetric & Kit-of-Parts)