MONITORING & MANAGING CONSTRUCTION PROJECTS
Defect Analysis & Quality Control
Dr Adewale Abimbola, FHEA, GMICE.
Aim & Objectives
At the end of the lesson, the students should be able to:�
2
Defect Analysis
&
Quality Control
Learning Outcome and Assessment Criteria
M2 Analyse the difference between patent and latent defects and their associated implications for remedial actions
D1 Evaluate the relationship between client requirements, statutory requirements and addressing defects with regard to the impact on quality and safety.
Defect Analysis
4
1
2
Patent & Latent Defects
RECORDING DEFECTS ON CONSTRUCTION SITES
SNAGGING LISTS/DEFECT INSPECTION FORMS
DIGITAL DEFECT MANAGEMENT SOFTWARE
6
Figure 1. Snagging list (Davide, 2022).
Figure 2. Snagmaster (Snagmaster, 2025).
RECORDING DEFECTS ON CONSTRUCTION SITES
PHOTOGRAPHIC RECORDS
WRITTEN REPORTS AND LOGS
7
Figure 3. Photographic records (BibLus, 2025).
Figure 4. Building defect report (Sitemate, 2025).
Patent Defects: Implications for Remedial Actions
Latent Defects: Implications for Remedial Actions
Stakeholder Impact
Group-assessment Task
Quiz: Sort the Construction Defects
Defect | Defect Type (Latent or Patent) | Explanation (Why) |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
For each defect below, decide whether it is a latent defect or a patent defect by placing it in the correct category. Explain briefly why.
Managing construction project
Quality Assurance and Quality Control.
12
QUALITY ASSURANCE AND QUALITY CONTROL
QUALITY ASSURANCE
QUALITY CONTROL
13
KEY QUALITY ASSURANCE PROCESSES IN CONSTRUCTION
DOCUMENT CONTROL
DRAWING REGISTER
14
KEY QUALITY ASSURANCE PROCESSES IN CONSTRUCTION
SPECIFICATION USE
SITE TESTING
15
KEY QUALITY ASSURANCE PROCESSES IN CONSTRUCTION
OFF-SITE TESTING
DIMENSIONAL QUALITY CONTROL
16
Typical tests
Self-assessment task
18
Story:
During the construction project, the (1) team implemented a systematic process to ensure that all works met the client’s expectations and legal requirements. This process focused on prevention and establishing standards before work began.
Meanwhile, the (2) team was responsible for verifying that the materials and workmanship complied with the set standards through regular inspections and tests.
Effective (3) was critical to keep track of all project documentation and ensure that the latest versions of drawings and specifications were used. The (4) helped monitor revisions and ensured that all site staff worked from current drawings.
Correct (5) of materials and procedures was essential to maintain consistency and avoid defects.
During construction, both (6) and (7) were conducted. The former involved testing materials and workmanship directly on site, while the latter involved testing samples or components at specialized off-site laboratories.
To guarantee structural fit and finish, (8) was applied to check measurements against design tolerances.
Fill-in-the-Blanks Exercise: Quality Assurance and Quality Control Story
Complete the story by filling in the blanks with the appropriate terms from the word bank.
Word Bank:
Compliance with statutory liaison
19
COMPLIANCE WITH STATUTORY LIAISON
20
COMPLIANCE WITH STATUTORY LIAISON
LOCAL PLANNING AUTHORITIES
BUILDING CONTROL
21
COMPLIANCE WITH STATUTORY LIAISON
NATIONAL HOUSE BUILDING COUNCIL (NHBC):
ENVIRONMENT AGENCY
22
COMPLIANCE WITH STATUTORY LIAISON
TRUNK ROAD AGENTS
UTILITY COMPANIES
23
Compliance with statutory liaison
Cadw (for projects in Wales):
Quality Control Responsibilities
25
QUALITY CONTROL RESPONSIBILITIES
26
QUALITY CONTROL RESPONSIBILITIES
ARCHITECT/DESIGNER
CIVIL ENGINEER
27
QUALITY CONTROL RESPONSIBILITIES
CLERK OF WORKS
CLIENT
28
QUALITY CONTROL RESPONSIBILITIES
CONTRACTOR AND SUBCONTRACTOR
SITE STAFF
29
Group-assessment task
30
Scenario:
A commercial building project is underway. During foundation works, persistent issues have been detected with soil compaction and concrete strength tests failing to meet the specified standards. These problems risk delaying the project and increasing costs.
Task:
References/Bibliography
References/Bibliography