Executive Staff Meeting

September 05, 2013

OPEN SOURCE

OPEN SOURCE

2 of 9

Shuttleworth Expectations

  1. CEB Press design is revised, the 3 machines are updated with the new design elements and successfully used during the microhouse build scheduled for 28 September.

  • The LifeTrac design is revised to version 6, the LifeTrac 6 machine built and used effectively together with the CEB Presses during the microhouse build scheduled for 28 September.

  • The build, test, and data collection of the ironworker and backhoe is complete.

  • Only GVCS machines are used in the microhouse build of 28 September.

  • The microhouse build is completed successfully by 30 October 2013.

OPEN SOURCE

OPEN SOURCE

3 of 9

3rd Quarter Priorities (July - September)

  1. Development Process

  • Projects
  • Microhouse
  • CEB
  • Build, Test, and Data Collection of
        • Backhoe (complete by October 30)
        • Iron worker (complete by October 30)

  • Schedule objectives for 4th Quarter (Oct -Dec)

OPEN SOURCE

OPEN SOURCE

4 of 9

Current Week Priorities

Week Priorities

Previous Week

Current Week

Issues/Risk

Quarterly Goal

Project Manager Scheduling

Schedule

  1. Microhouse
  2. Soil Pul
  3. 50Pwr Cube
  4. Backhoe
  5. Ironworker

Review in PM

  1. Microhouse
  2. Soil Pul (N/A)
  3. 50PC (N/A)
  4. Backhoe
  5. Ironworker

Schedule projects in PM through

4th Quarter

LifeTrac 6

Implementing use of Development Boards (ongoing)

BOM, Identifying missing parts

Build LifeTrac 6 while beta testing process

OPEN SOURCE

OPEN SOURCE

5 of 9

Current Week Priorities

Week Priorities

Previous Week

Current Week

Issues/Risk

Quarterly Goal

Microhouse

None

None

Pitch to Shuttleworth

Sept 28: Complete

DPV and Design Sprint Recruiting

Recruiting, Newsletter

Sept 30:

3 DPVs

OSE Structuring

Sourced 2 quotes.

Forwarded healthcare quotes to 3rd party to decide (Sept 04)

Make decision by Sept 5

CAB Step by Step

Working

OPEN SOURCE

OPEN SOURCE

6 of 9

Resources and Personnel

  • OSE Ford Ranger
    • Need to verify whether oil has been added.
    • Truck must be returned to M & R Automotive for permanent hood and gas tank repair and oil check/top off
  • OSE Personnel
    • Marcin Off Site re: Working - September 5-6
    • Katie Off Site re: Vacation - September 6
    • Audrey Off Site re: Vacation - September 27 and 30
    • Audrey Off Site re: Vacation - October 7
    • Katie Off Site re: Vacation - October 7 and 8
    • Patriots Day is not a recognized holiday
    • Marcin Off Site re: Working - October 16-18
    • Marcin Off Site re: Working - November 10-14

7 of 9

Schedule Review

  • OSE Schedule - wiki page
    • Project Manager
    • OSE Schedule

  • Significant Schedule Items to discuss
    • Design Sprint Agenda (nothing specific, weekly)

OPEN SOURCE

OPEN SOURCE

8 of 9

Other Tasks

Date Added

Tasks

Status

August 22

Development Process - Product Development Board’s Step Instructions and Sample Deliverables

Ongoing

July 15

Cloverdale steel pick up

Aug 30 - Chad out of the office - call back Tuesday to confirm pickup date ($760)

August 16

August 26

Sweiger Shop - steel pick up

August 20

Mo-kan Fasteners (KC) bolts pick up

Urgent - going out of business

August 30

DPV Orientation, Message Board and check out

August 30

OSE Ford Ranger repairs

Sept 04

The Feast needs Marcin’s Presentation by Sept 20

DM is working Prezi as of Sept 03

Sept 05

Microhouse BOM

Chris to provide

OPEN SOURCE

OPEN SOURCE

9 of 9

Strategic Issues for Discussion

  1. Development: Development Process Issues Identified
  2. Infrastructure: gravel lay down and bridge - put in Parking Lot
  3. Logistics: Potluck dinners during tractor build
    1. Action needed: Direct DPV

OPEN SOURCE

OPEN SOURCE